Contract No: HK/2009/05 Wanchai
Development Phase II and Central Wanchai Bypass Sampling,
Field Measurement and Testing Work (Stage 1) Environmental Permit no.
EP-356/2009, Further
Evironmental permit nos. fep-01/356/2009, fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009
and Fep-05/356/2009 Monthly
Environmental Monitoring & Audit Report
- September 2011 -
|
CLIENTS: |
|
Civil Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185
Gloucester Road, Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
11 October 2011 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. Status of Regulatory Compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
5.2 Real-time Noise Monitoring
6.2 Real-time noise Monitoring
6.5 Review of the Reasons for and the Implications of
Non-compliance
6.6 Summary of action taken in the event of and follow-up
on non-compliance
7. Cumulative Construction Impact due to the Concurrent
Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table I Summary of
Water Quality Monitoring Exceedances in Reporting Month
Table II Summary of
Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
Table 2.1 Schedule 2 Designated Projects under
this Project
Table 2.2 Details of
Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/11
Table 3.3 Summary of
submission status under FEP-01/356/2009 Condition
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Table 3.5 Summary of
submission status under FEP-02/356/2009 Condition
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/02
Table 3.7 Summary of
submission status under FEP-03/356/2009 Condition
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Table 3.9 Summary of
submission status under FEP-04/356/2009 Condition
Table 3.10 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2010/06
Table 3.11 Summary of submission status under
EP-356/2009 and FEP-05/356/2009 Condition
Table 4.1 Noise
Monitoring Station
Table 4.2 Real Time
Noise Monitoring Station
Table 4.3 Air
Monitoring Station
Table 4.4 Marine Water Quality Stations for Water
Quality Monitoring
Table 4.5 Marine Water
Quality Monitoring Frequency and Parameters
Table 4.6 Marine Water Quality Stations for
Enhanced Water Quality Monitoring
Table 5.1 Noise Monitoring Stations for Contract
no. HY/2009/11
Table 5.2 Noise Monitoring Station for Contract
nos. HK/2009/01, HK/2009/02 and HK/2010/06
Table 5.3 Noise Monitoring Station for Contract
no. HY/2009/15
Table 5.4 Real Time
Noise Monitoring Station for Contract no. HY/2009/11
Table 5.5 Air Monitoring Stations for Contract no.
HY/2009/11
Table 5.6 Air Monitoring Stations for Contract no.
HK/2009/01
Table 5.7 Air Monitoring Station for Contract no.
HK/2009/02
Table 5.8 Air Monitoring Station for Contract no.
HY/2009/15
Table 5.9 Water Monitoring Stations for Contract
no. HY/2009/11
Table 5.10 Water Monitoring Stations for Contract
no. HK/2009/01
Table 5.11 Water Monitoring Stations for Contract
no. HK/2009/02
Table 5.12 Water Monitoring Stations for Contract
no. HK/2009/02
Table 5.13 Water Monitoring Stations for Contract
no. HY/2009/15
Table 5.14 Summary of Water Quality Monitoring
Exceedances in Reporting Month
Table 5.15 Summary of Enhanced Dissolved Oxygen
Monitoring Exceedances in Reporting Month
Table 5.16 Details of Waste Disposal for Contract
no. HY/2009/11
Table 5.17 Details of Waste Disposal for Contract
no. HK/2009/01
Table 5.18 Details of Waste Disposal for Contract
no. HK/2009/02
Table 5.19 Details of Waste Disposal for Contract
no. HY/2009/15
Table 5.20 Details of Waste Disposal for Contract
no. HK/2010/06
Table 8.1 Summary of
Environmental Inspections for Contract no. HY/2009/11
Table 8.2 Summary of Environmental Inspections for
Contract no. HK/2009/01
Table 8.3 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.4 Summary of Environmental Inspections for
Contract no. HY/2009/15
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2010/06
Table 9.1 Cumulative
Statistics on Complaints
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Table 10.1 Construction Activities and Recommended
Mitigation Measures in Coming Reporting Month
lIST
OF FIGUREs
Figure
2.1 Project
Layout
Figure
2.2 Project
Organization Chart
Figure 4.1 Locations
of Environmental Monitoring Stations
lIST
OF APPENDIces
Appendix 3.1 Environmental Mitigation
Implementation Schedule
Appendix 4.1 Action
and Limit Level
Appendix
4.2 Copies
of Calibration Certificates
Appendix
5.1 Monitoring
Schedule for Reporting Month and Coming month
Appendix
5.2 Noise Monitoring Results and
Graphical Presentations
Appendix 5.3 Air Quality Monitoring Results and
Graphical Presentations, and Odour Patrol Results
Appendix
5.4 Water
Quality
Monitoring Results and Graphical Presentations
Appendix
5.5 Real-time
Noise
Monitoring Results and Graphical Presentations
Appendix 6.1 Event
Action Plans
Appendix 6.2 Summary for
Notification of Exceedance
Appendix
9.1 Complaint
Log
Appendix 10.1 Construction
Programme of Individual Contracts
Construction Activities for the Reported Period
¡P
Reclamation
works;
¡P
Geo-textile
laying;
¡P
Drainage
Construction works;
¡P
Outfall construction
works (Open Channel U);
¡P
Sheet Pilling;
¡P
Pre-casting of Coping;
and
¡P
Construction
& installation of Seawall Concrete Block
¡P
Installation of
silt screen (type 1) at TST;
¡P
Seawall toe
block installation for reinstating seawall at Zone B1-3;
¡P
Dredging within
HKCEC Water Channel from CH160 to CH190 for Type 1 & 2 sediment;
¡P
Trench
backfilling and seawall reinstatement for both the completed cross-harbour
watermains and the seawall near Expo Promenade (Zone B1-3);
¡P
Installation of
cross-harbour watermains nos. A8 & B8;
¡P
Final trimming
within Principle Fairway for cross-harbour watermains installation;
¡P
Platform
erection for crawler crane mobilization near the existing seawall at Salisbury
Garden had been completed and WSD¡¦s consent had been given for mobilization of
crawler crane to the jack-up barge. Mobilization;
¡P
The trench
excavation works at Zone B1-4, B4-2, A1-2, A2-4A, A3-3, A4-3B, A4-3B, A4-3C and
A5-5;
¡P
Trench
excavation works at Zone A3-2A;
¡P
Excavation for
jacking pits for pipe laying works by heading method along Convention Avenue at
Zone A1-2A, A1-4A and A2-4A;
¡P
Heading No. H2,
H5 and H6 (Mainlaying works by trenchless method); and
¡P
Trench
excavation for a 1000 dia. Watermains at Salisbury Garden
¡P
Tseung Kwan O public fill sorting facility
¡P
Steel fixing of Passenger Terminal Building was completed on 8 September
2011;
¡P
Demolition of existing ferry pier;
¡P
Racking piles and dredging work of Ferry Pier;
¡P
Formwork for lift shaft of Passenger Terminal Building;
¡P
Fixing G/F to 1/F R.C wall waling on Passenger Terminal Building;
¡P
Construction of wash out chamber at Harbour Road and access manhole at
Harbour Centre;
¡P
Reinstatement work for footpath and existing inspection chamber at Great
Eagle Centre;
¡P
Trench excavation and deck over works along Tonnochy Road;
¡P
Approximate
¡P
Grouting for the cross road pipeline of Harbour Road;
¡P
Installation of PVC and G.I cable ducts was ongoing at Harbour Road;
¡P
Wall and column construction below -0.8 mPD;
¡P
Installation of submarine outfall pipe up to CHA-105 and CHB-130, continue
backfill on the HDPE pipelines;
¡P
Dredging for submarine outfall pipe;
¡P
3 out of 12 nos of pre-bored H-pile for box culverts N1 was reached to
founding levels;
¡P
1st and 2nd loading test of New Ferry Pier;
¡P
Marine piling works for new ferry pier was ongoing. 83 out of 83 nos. marine
piles;
¡P
Dredging inside the piles was ongoing. 45 out of 83 piles;
¡P
Wall and column construction below -0.8 mPD;
¡P
Casting of the base slab of WSD Receiving Pit;
¡P
Excavation and lateral support for DSD receiving pits;
¡P
Half landing slab for P7, P8 & P9 Pumping Stations was completed,
top slab false work & formwork erection;
¡P
Expo Drive East mass concreting coping formwork erection;
¡P
Levelling for proposed bream blocks in progress at Vertical Seawall T4
to T6; and
¡P
Commenced fabricating the steel frames for water diversion and temporary
sheet piles walls for WCR2 reclamation.
¡P
Seawall block construction, reclamation work at TS4;
¡P
Maintenance dredging of navigation channel and mooring area;
¡P
Night time protection works at CHT;
¡P
Construction of dewatering well at Hung Hing Road and POC; and
¡P
Precautionary works at Abutment A
¡P
Installation of bored pile casing;
¡P
Excavation of bored piles;
¡P
Pre-drilling works; and
¡P
Installation of temporary staging platforms
Noise Monitoring
Real-time Noise Monitoring
Air Quality Monitoring
Water Quality Monitoring
Table I Summary
of Water Quality Monitoring Exceedances in Reporting Month
Water Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
||
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD15 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C8 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
|
C9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/01 |
WSD19 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD20 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD7 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C3 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C4e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C4w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/01 & HK/2010/06 |
C2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C5w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD21 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HY/2009/15 |
C7 |
2 |
0 |
0 |
0 |
0 |
0 |
4 |
0 |
0 |
0 |
0 |
0 |
Total |
2 |
0 |
0 |
1 |
0 |
0 |
4 |
0 |
1 |
1 |
0 |
0 |
Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.
Table
II Summary of Enhanced Dissolved
Oxygen Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring
Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
AL |
LL |
AL |
LL |
||
HY/2009/15 |
C6 |
2 |
2 |
4 |
1 |
C7 |
3 |
0 |
4 |
2 |
|
Ex-WPCWA SW |
0 |
3 |
0 |
9 |
|
Ex-WPCWA SE |
1 |
5 |
5 |
8 |
|
Total |
6 |
10 |
13 |
20 |
Complaints, Notifications of Summons and Successful Prosecutions
Site Inspections and Audit
Contract no. HY/2009/11- North Point Reclamation
¡P
Reclamation
works;
¡P
Slotted panel
fixing;
¡P
Geo-textile
laying;
¡P
Drainage
Construction works;
¡P
Outfall
construction works (Open Channel U);
¡P
Sheet Pilling;
¡P
Pre-casting and
Installation of Coping; and
¡P
Construction
& installation of Seawall Concrete Block
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
¡P
Dredging works
from CH190to CH260 for the reclamation of HKCEC3W would be commenced upon giving
7-day advance notice to EPD;
¡P
Reclamation of
HKCEC3W (up to CH120) within the HKCEC Water Channel;
¡P
Installation of
sheet pile water channel at Dome Promenade (from CH120 to CH160);
¡P
Installation of
silt screen (type 3) at TST;
¡P
Dredging woks
from CH50 to Ch250 for subsequent cross-harbour watermains installation off TST
would be commenced. A trial dredging operation near the Avenue of Stars would
be demonstrated to the representatives of LCSD on 22 September.
¡P
Installation of
cross harbour watermains nos. A9 &B9 and A10 & B10;
¡P
Sheet pipe pile
wall and the associated ground treatment works for the trenches of the proposed
cross harbour watermaines nos. A18 & B18 works be commenced after the
subsequent removal of the temporary steel platform;
¡P
Trench excavation
works at Zone A1-2;
¡P
Works would be continued
out at Zone A2-3B, A3-3, A3-2A, A4-3B, A4-3B, A4-3C, A5-5, B1-4, B4-2 and B4-5;
¡P
Heading Nos. H2,
H5 and H6 (Mainlaying works by trenchless method); and
¡P
Heading Nos. H3,
H4 and H9 (Mainlaying works by trenchless method) would be commenced after
their corresponding jacking pits had been excavated in Convention Avenue.
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
¡P
Operating Tseung
Kwan O Public Fill Sorting Facility;
¡P
Construction of
passenger terminal;
¡P
Demolition of
remaining finger pier;
¡P
Construction of
mass seawall coping at Expo Drive East;
¡P
Trench
excavation and pipe laying works along Harbour Road;
¡P
Trench
excavation and deck over at Tonnochy Road;
¡P
Top soffit slab
at P7, P8 & P9 pump stations;
¡P
Construction
above -0.8mPDat Wan Shing Street for WSD Salt Water Intake;
¡P
Pipeline jacking
WSD intake A.
¡P
Pre-bored sheet
pile works for salt water intake culvert Bay1b & Bay 2;
¡P
Pre-bored H-pile
for Box Culvert N1 at WCR1 Area;
¡P
The 3rd and 4th
loading test of New Ferry Pier;
¡P
All piles
excavation at new ferry pier;
¡P
Grouting plug in
piles of New Ferry Pier;
¡P
Concreting for
marine piles at new ferry pier;
¡P
Dredging and fabrication
of HDPE pipe diffuser section for submarine outfall pipes;
¡P
Backfilling of
bagged concrete and rockfills for the installed submarine outfall pipes;
¡P
Excavation and
lateral support for receiving pits at Hung Hing Road;
¡P
Installation of
temporary sheet piles wall at WCR2; and
¡P
Installation of
the temporary water diversion steel frame
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section)
¡P
Mooring
rearrangement and dredging at ME4;
¡P
Night time
protection works at CHT;
¡P
Construction of
dewatering well at Hung Hing Road and POC; and
¡P
Precautionary
works at Abutment A
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Installation of
bored pile casing;
¡P
Excavation of
bored piles;
¡P
Bored Pile
Concreting;
¡P
Pre-drilling works;
and
¡P
Installation of
temporary staging platforms
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to
work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009
and Further Environmental permit nos. FEP-01/356/2009, FEP-02/356/2009,
FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 to implement the
Environmental Monitoring and Audit (EM&A) programme as stipulated in the
EM&A Manual of the approved Environmental Impact Assessment (EIA) Report
for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring
and auditing work carried out in accordance to the Section 10.3 of EM&A
Manual and ¡§Environmental Monitoring and Audit Requirements¡¨ under
Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A works
for Environmental Permit no. EP-356/2009, Further Environmental Permit no.
FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and
FEP-05/356/2009 and during the period 28th August to 27th
September 2011. The cut-off date of reporting is at 27th of each
reporting month.
Section
1 Introduction ¡V
details the scope and structure of the report.
Section
2 Project
Background ¡V summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance ¡V
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements ¡V summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results ¡V summarizes the monitoring results
obtained in the reporting period.
Section
6 Compliance
Audit ¡V summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the
Concurrent Projects ¡V summarizes the relevant cumulative construction impact
due to the concurrent activities of the concurrent Projects.
Section
8 Site Inspection ¡V
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review
of any relevant
follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
¡V summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai
Bypass¡¨ and ¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨
(hereafter called ¡§the Project¡¨) are Designed Project (DP) under the
Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental
Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern
Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved
on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II
(WDII) is to provide land at Wan Chai North and North Point for construction of
the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed
under the project will be developed as a world-class waterfront promenade
joining that at the new Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB
to provide relief to the very congested east-west Connaught Road
Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is
currently operating beyond its capacity. The CWB will provide relief to the
existing congestion along the Corridor and cater for the anticipated growth of
traffic on Hong Kong Island. Without the CWB and its access roads, there will
not be sufficient capacity to serve the heavy traffic demands at both strategic
and local levels.
2.2.1.
The Project is located mainly in Wan Chai North,
Causeway Bay and North Point, and is demarcated by Gloucester Road and Victoria
Park Road to the south, Fenwick Pier Street to the west and Tong Shui Road
Interchange to the east, as shown in Figure 2.1.
2.2.2.
The study area encompasses existing developments
along the Wan Chai, Causeway Bay and North Point shorelines. Major land uses
include the Hong Kong Convention & Exhibition Centre (HKCEC) Extension, the
Wan Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area (ex-PCWA), the
Royal Hong Kong Yacht Club (RHKYC), the Police Officers¡¦ Club, the Causeway Bay
Typhoon Shelter (CBTS) and commercial and residential developments.
2.2.3.
The scope of the Project
comprises:
¡P
Land formation
for key transport infrastructure and facilities, including the Trunk Road (i.e. CWB) and the associated
slip roads for connection to the Trunk Road and for through traffic from Central to
Wan Chai and Causeway Bay. The land formed for the above transport infrastructure
will provide opportunities for the development of an attractive waterfront
promenade for the enjoyment of the public
¡P
Reprovisioning /
protection of the existing facilities and structures affected by the land
formation works mentioned above
¡P
Extension,
modification, reprovisioning or protection of existing storm water drainage
outfalls, sewerage outfalls and watermains affected by the revised land use and
land formation works mentioned above
¡P
Upgrading of
hinterland storm water drainage system and sewerage system, which would be
rendered insufficient by the land formation works mentioned above
¡P
Provision of the
ground level roads, flyovers, footbridges, necessary transport facilities and
the associated utility services
¡P
Construction of
the new waterfront promenade, landscape works and the associated utility
services
¡P
The Trunk Road
(i.e. CWB) within the study area and the associated slip roads for connection
to the Trunk Road.
2.2.4.
The project also contains various Schedule 2 DPs
that, under the EIAO, require Environmental Permits (EPs) to be granted by the
DEP before they may be either constructed or operated. Table 2.1
summarises the five individual DPs under this Project. Figure 2.1 shows the
locations of these Schedule 2 DPs.
Table 2.1 Schedule
2 Designated Projects under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project,
there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced. Contractors of individual contracts will
be required by the EP holder to apply Further Environmental Permits (FEP) such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized
in Table 2.2.
Table 2.2 Details
of Individual Contracts under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at Hong Kong
Convention and Exhibition Centre |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 |
||
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central ¡V Wan Chai Bypass ¡V North
Point Reclamation |
DP3 |
17 March 2010 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central - Wan Chai Bypass (CWB) ¡V Central Interchange |
DP1 |
21 April 2011 |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
2.4.1.
Civil Engineering and Development Department and Highways
Department are the overall project controllers for the Wan Chai Development
Phase II and Central-Wan Chai Bypass respectively. For the construction phase
of the Project, Project Engineer, Contractor(s), Environmental Team and
Independent Environmental Checker are appointed to manage and control
environmental issues.
2.4.2.
The proposed project organization and lines of
communication with respect to environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3:
Table
2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
China Harbour- CRBC Joint Venture |
Contractor under Contract no. HY/2009/11 |
Project Director |
Mr. Cho Yu Fun |
3157 1086 |
3157 1085 |
Project Manager |
Mr. Gregory Wong |
3157 1086 |
|||
Site Agent |
Mr. Daniel Cheung |
3157 1086 |
|||
Environmental Officer |
Mr. C. M. Wong |
3157 1086 |
|||
Chun Wo ¡V Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Director |
Mr. Simon Tong |
9124 2471 |
2634 1626 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Operation Manager |
Mr. Lau Yee Ching |
9466 3918 |
|||
Construction Manager |
Mr. Jerry Siu |
9493 3664 |
|||
Construction Manager |
Mr. Ricky Lai |
9487 6549 |
|||
Construction Manager |
Mr. KK Yuen |
3498 1213 |
|||
Environmental Officer
(Compliance Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Site Agent |
Mr. Mak Kam Wing |
3658 3044 |
|||
Quality & Environmental Manager |
Mr. C.P. Ho |
3658 3000 |
|||
Environmental Officer |
Ms. Flora Ng |
3658 3064 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Manager |
Mr. M Y Wong |
2823 7879 |
2528 5651 |
Site Agent |
Mr. Simon Tang |
3557 6358 |
2566 2192 |
||
|
|
Construction Manager |
Mr. C K Kwok |
9779 2162 |
|
|
|
Assistant Construction Manager (East) |
Mr. Gene Cheung |
6105 4880 |
|
|
|
Assistant Construction Manager (West) |
Mr. Tony Chiu |
9090 0606 |
|
|
|
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project Manager |
Mr. Simon Tong |
9124 2471 |
2529 2880 |
Site Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental Officer |
Mr. Lee Wai Man |
9481
6024 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
For Contract no. HY/2009/11, the principal work
activities in this reporting month included:
¡P
Reclamation works;
¡P
Geo-textile laying;
¡P
Drainage Construction works;
¡P
Outfall construction works (Open Channel U);
¡P
Sheet Pilling;
¡P
Pre-casting of Coping; and
¡P
Construction & installation of Seawall Concrete Block
2.4.4.
For Contract no. HK/2009/01, the principal work
activities in this reporting month included:
¡P
Installation of silt screen (type 1) at TST;
¡P
Seawall toe block installation for reinstating seawall at Zone B1-3;
¡P
Dredging within HKCEC Water Channel from CH160 to CH190 for Type 1 &
2 sediment;
¡P
Trench backfilling and seawall reinstatement for both the completed
cross-harbour watermains and the seawall near Expo Promenade (Zone B1-3);
¡P
Installation of cross-harbour watermains nos. A8 & B8;
¡P
Final trimming within Principle Fairway for cross-harbour watermains
installation;
¡P
Platform erection for crawler crane mobilization near the existing
seawall at Salisbury Garden had been completed and WSD¡¦s consent had been given
for mobilization of crawler crane to the jack-up barge. Mobilization;
¡P
The trench excavation works at Zone B1-4, B4-2, A1-2, A2-4A, A3-3,
A4-3B, A4-3B, A4-3C and A5-5;
¡P
Trench excavation works at Zone A3-2A;
¡P
Excavation for jacking pits for pipe laying works by heading method
along Convention Avenue at Zone A1-2A, A1-4A and A2-4A;
¡P
Heading No. H2, H5 and H6 (Mainlaying works by trenchless method); and
¡P
Trench excavation for a 1000 dia. Watermains at Salisbury Garden
2.4.5.
For Contract no. HK/2009/02, the principal work
activities in this reporting month included:
¡P
Tseung Kwan O public fill sorting facility
¡P
Steel fixing of Passenger Terminal Building was completed on 8 September
2011;
¡P
Demolition of existing ferry pier;
¡P
Racking piles and dredging work of Ferry Pier;
¡P
Formwork for lift shaft of Passenger Terminal Building;
¡P
Fixing G/F to 1/F R.C wall waling on Passenger Terminal Building;
¡P
Construction of wash out chamber at Harbour Road and access manhole at
Harbour Centre;
¡P
Reinstatement work for footpath and existing inspection chamber at Great
Eagle Centre;
¡P
Trench excavation and deck over works along Tonnochy Road;
¡P
Approximate
¡P
Grouting for the cross road pipeline of Harbour Road;
¡P
Installation of PVC and G.I cable ducts was ongoing at Harbour Road;
¡P
Wall and column construction below -0.8 mPD;
¡P
Installation of submarine outfall pipe up to CHA-105 and CHB-130, continue
backfill on the HDPE pipelines;
¡P
Dredging for submarine outfall pipe;
¡P
3 out of 12 nos of pre-bored H-pile for box culverts N1 was reached to
founding levels;
¡P
1st and 2nd loading test of New Ferry Pier;
¡P
Marine piling works for new ferry pier was ongoing. 83 out of 83 nos.
marine piles;
¡P
Dredging inside the piles was ongoing. 45 out of 83 piles;
¡P
Wall and column construction below -0.8 mPD;
¡P
Casting of the base slab of WSD Receiving Pit;
¡P
Excavation and lateral support for DSD receiving pits;
¡P
Half landing slab for P7, P8 & P9 Pumping Stations was completed,
top slab falsework & formwork erection;
¡P
Expo Drive East mass concreting coping formwork erection;
¡P
Levelling for proposed bream blocks in progress at Vertical Seawall T4
to T6; and
¡P
Commenced fabricating the steel frames for water diversion and temporary
sheet piles walls for WCR2 reclamation.
2.4.6.
For Contract no. HY/2009/15, the principal work
activities in this reporting month included:
¡P
Seawall block construction, reclamation work at TS4;
¡P
Maintenance dredging of navigation channel and mooring area;
¡P
Night time protection works at CHT;
¡P
Construction of dewatering well at Hung Hing Road and POC; and
¡P
Precautionary works at Abutment A
2.4.7.
For Contract no. HK/2010/06, the principal work
activities in this reporting month included:
¡P
Installation of bored pile casing;
¡P
Excavation of bored piles;
¡P
Pre-drilling works; and
¡P
Installation of temporary staging platforms
2.4.8.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract no. HY/2009/11- North Point Reclamation
¡P
Reclamation
works;
¡P
Slotted panel
fixing;
¡P
Geo-textile
laying;
¡P
Drainage
Construction works;
¡P
Outfall
construction works (Open Channel U);
¡P
Sheet Pilling;
¡P
Pre-casting and
Installation of Coping; and
¡P
Construction
& installation of Seawall Concrete Block
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
¡P
Dredging works
from CH190to CH260 for the reclamation of HKCEC3W would be commenced upon giving
7-day advance notice to EPD;
¡P
Reclamation of
HKCEC3W (up to CH120) within the HKCEC Water Channel;
¡P
Installation of
sheet pile water channel at Dome Promenade (from CH120 to CH160);
¡P
Installation of
silt screen (type 3) at TST;
¡P
Dredging woks
from CH50 to Ch250 for subsequent cross-harbour watermains installation off TST
would be commenced. A trial dredging operation near the Avenue of Stars would
be demonstrated to the representatives of LCSD on 22 September.
¡P
Installation of
cross harbour watermains nos. A9 &B9 and A10 & B10;
¡P
Sheet pipe pile
wall and the associated ground treatment works for the trenches of the proposed
cross harbour watermaines nos. A18 & B18 works be commenced after the
subsequent removal of the temporary steel platform;
¡P
Trench
excavation works at Zone A1-2;
¡P
Works would be continued
out at Zone A2-3B, A3-3, A3-2A, A4-3B, A4-3B, A4-3C, A5-5, B1-4, B4-2 and B4-5;
¡P
Heading Nos. H2,
H5 and H6 (Mainlaying works by trenchless method); and
¡P
Heading Nos. H3,
H4 and H9 (Mainlaying works by trenchless method) would be commenced after
their corresponding jacking pits had been excavated in Convention Avenue.
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
¡P
Operating Tseung
Kwan O Public Fill Sorting Facility;
¡P
Construction of
passenger terminal;
¡P
Demolition of
remaining finger pier;
¡P
Construction of
mass seawall coping at Expo Drive East;
¡P
Trench
excavation and pipe laying works along Harbour Road;
¡P
Trench
excavation and deck over at Tonnochy Road;
¡P
Top soffit slab
at P7, P8 & P9 pump stations;
¡P
Construction
above -0.8mPDat Wan Shing Street for WSD Salt Water Intake;
¡P
Pipeline jacking
WSD intake A.
¡P
Pre-bored sheet
pile works for salt water intake culvert Bay1b & Bay 2;
¡P
Pre-bored H-pile
for Box Culvert N1 at WCR1 Area;
¡P
The 3rd and 4th
loading test of New Ferry Pier;
¡P
All piles
excavation at new ferry pier;
¡P
Grouting plug in
piles of New Ferry Pier;
¡P
Concreting for
marine piles at new ferry pier;
¡P
Dredging and fabrication
of HDPE pipe diffuser section for submarine outfall pipes;
¡P
Backfilling of
bagged concrete and rockfills for the installed submarine outfall pipes;
¡P
Excavation and
lateral support for receiving pits at Hung Hing Road;
¡P
Installation of
temporary sheet piles wall at WCR2; and
¡P
Installation of
the temporary water diversion steel frame
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V
Tunnel (Causeway Bay Typhoon Shelter Section)
¡P
Mooring
rearrangement and dredging at ME4;
¡P
Night time
protection works at CHT;
¡P
Construction of
dewatering well at Hung Hing Road and POC; and
¡P
Precautionary
works at Abutment A
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Installation of
bored pile casing;
¡P
Excavation of
bored piles;
¡P
Bored Pile
Concreting;
¡P
Pre-drilling
works; and
¡P
Installation of
temporary staging platforms
3.1.1.
A summary of the current status on licences and/or
permits on environmental protection pertinent to the Project is shown in Table
3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-356/2009 |
30 Jul
2009 |
Valid |
Environmental
Permit |
EP-364/2009/A |
4 Aug
2010 |
Valid |
Environmental
Permit |
EP-364/2009 |
17 Aug
2009 |
Superseded |
Environmental
Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb
2010 |
Valid |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
FEP-04/356/2009 |
22 Nov
2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar
2011 |
Valid |
Further
Environmental Permit |
FEP-01/364/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
Valid |
Further
Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
Valid |
Further
Environmental Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
Valid |
Further
Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-07/364/2009/A |
25 Feb 2011 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project,
the status of permits and/or licences under the individual contract(s) are
presented as below:
Contract no. HY/2009/11 ¡V
Central ¡V Wanchai Bypass, North Point Reclamation
3.1.3.
Summary of the current status on licences and/or permits
on environmental protection pertinent and submission under FEP-01/356/2009 for
contract no. HY/2009/11 are shown in Table 3.2 and Table
3.3.
3.1.4.
Contractor submitted a letter dated 20 July 2011 to
confirm that the dredging works and dumping operation were completed.
Table 3.2 Cumulative
Summary of Valid Licences and Permits
under Contract no. HY/2009/11
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
N/A |
Valid |
Notification of Works Under APCO |
314911 |
9 Mar 2010 |
N/A |
Valid |
|
331892 |
4 Jul. 2011 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0330-11 |
15 Apr 2011 |
1 May 2011 to 31 Oct 2011 |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-151-C3631-02 |
12 Oct 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance |
7010037 |
13 Jan 2010 |
N/A |
Valid |
Discharge Licence |
WT00007942-2010 |
29 Nov 2010 |
30 Nov 2015 |
Valid |
Table
3.3 Summary of submission status under
FEP-01/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
18 Dec 2009 |
Condition 2.7 |
Submission of works schedule
and location plan |
8 Feb 2010 |
Condition 2.8 |
Revised Silt Curtain Deployment
Plan (Rev. 3) |
4 Dec 2010 |
Condition 2.9 |
Silt Screen Deployment Plan
(Rev. 6) |
18 May 2011 |
Condition 2.10 |
Coral Translocation Plan |
20 Nov 2009 |
Condition 2.16 |
Revised Noise Management Plan
(Rev 5) |
19 Feb 2011 |
Condition 2.17 |
Landscape Plan |
12 May 2010 |
|
Revised landscape Plan |
30 Jun 2010 |
|
Submission of Supplementary
Information - Revised Management & Maintenance Schedule for Submitted
Revised Landscape Plan |
25 Aug 2010 |
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
3.1.5.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no.
HK/2009/01 under FEP-02/356/2009 are shown in Table 3.4 and
Table 3.5.
Table
3.4 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
|
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0107-11 |
8 Feb 2011 |
16 Mar 2011 to 15 Sep 2011 |
Expired |
|
GW-RS0384-11 |
29 Apr 2011 |
27 May 2011 to 26 Nov 2011 |
Valid |
|
GW-RS0680-11 |
22 Jul 2011 |
29 Jul 2011 to 19 Jan 2012 |
Valid |
|
GW-RS0689-11 |
28 Jul 2011 |
29 Jul 2011 to 28 Jan 2012 |
Valid |
|
GW-RS0832-11 |
7 Sep 2011 |
03 Sep 2011 to 02 Mar 2012 |
Valid |
|
GW-RS0850-11 |
12 Sept 2011 |
14 Sept 2011 to 13 Mar 2012 |
Valid |
|
GW-RS0851-11 |
12 Sept 2011 |
16 Sept 2011 to 15 Mar 2012 |
Valid |
|
GW-RE0683-11 |
16 Sept 2011 |
20 Sept 2011 to 19 Oct 2011 |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
|
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
Billing account under Waste
Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
EP/MD/12-021 |
20 May 2011 |
24 May 2011 to 23 Nov 2011 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) |
EP/MD/12-043 |
2 Aug 2011 |
08 Aug 2011 to 07 Sept 2011 |
Expired |
EP/MD/12-057 |
5 Sep 2011 |
08 Sept 2011 to 07 Oct |
Valid |
|
Permit for Dumping at Sea - Dredged Sediment Requiring
Type 3 ¡V Special Treatment / Disposal contained in Geosynthetic Containers |
EP/MD/12-050 |
18 Aug 2011 |
19 Aug 2011 to 18 Sept 2011 |
Expired |
EP/MD/12-063 |
22 Sept 2011 |
23 Sept 2011 to 22 Oct 2011 |
Valid |
Table
3.5 Summary of submission status under
FEP-02/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization of Main Construction Companies |
13 Apr 2010 |
Condition 2.7 |
Works Schedule and Location
Plan |
8 Apr 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan |
19 Apr 2010 |
Condition 2.9 |
Silt Screen Deployment Plan |
19 Apr 2010 |
Conditions 2.8 and 2.9 |
Supplementary Document on Silt
Curtain and Silt Screen Deployment Plan |
19 Jul 2010 |
Report on Field Testing for
Silt Curtain |
26 Aug 2010 |
|
Report on Field Testing for
Silt Curtain (Rev. A) |
15 Nov 2010 |
|
Condition 2.12(d) |
Alternative Proposal on Concurrent
Dredging for Sewage Pipeline and Cross Harbour Water Mains |
15 Apr 2011 |
Condition 2.17 |
Noise Management Plan |
23 Apr 2010 |
Condition 2.18 |
Landscape Plan (Erection of
Decorative Screen Hoarding along Construction Site around Hong Kong
Exhibition and Convention Centre) |
15 May 2010 |
Landscape Plan (Night-time
Lighting) |
22 Oct 2010 |
|
|
Landscape Plan (Rev. B) |
15 Nov 2010 |
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
3.1.6.
Summary of the current
status on licences and/or permits on environmental protection pertinent and
submission for contract no. HK/2009/02 under FEP-03/356/2009 are shown in Table
3.6 and Table 3.7.
Table
3.6 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
|
|
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for piling equipment |
PP-RS0011-11 |
27 April
2011 |
1 June 2011 to 30 Nov 2011 |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0343-11 |
11 April 2011 |
25 Apr 2011 to 10 Oct 2011 |
Valid |
GW-RS0369-11 |
21 April 2011 |
1 May 2011 to 31 Oct 2011 |
Valid |
|
|
GW-RS0377-11 |
27 April 2011 |
1 May 2011 to 31 Oct 2011 |
Valid |
|
GW-RE0311-11 |
4 May 2011 |
5 May 2011 to 31 Oct 2011 |
Valid |
|
GW-RS0401-11 |
3 May 2011 |
18 May 2011 to 17 Nov 2011 |
Valid |
|
GW-RS0414-11 |
3 May 2011 |
9 May 2011 to 8 Nov 2011 |
Withdrawn |
|
GW-RS0423-11 |
9 May 2011 |
22 May 2011 to 21 Nov 2011 |
Valid |
|
GW-RS0430-11 |
9 May 2011 |
16 May 2011 to 15 Nov 2011 |
Withdrawn |
|
GW-RS0453-11 |
19 May 2011 |
23 May 2011 to 22 Nov 2011 |
Valid |
|
GW-RS0461-11 |
19 May 2011 |
23 May 2011 to 22 Nov 2011 |
Valid |
|
GW-RS0473-11 |
27 May 2011 |
01 Jun 2011 to 30 Nov 2011 |
Withdrawn |
|
GW-RS0496-11 |
31 May 2011 |
07 Jun 2011 to 06 Dec 2011 |
Valid |
|
GW-RS0502-11 |
8 Jun 2011 |
13 Jun 2011 to 12 Dec 2011 |
Valid |
|
GW-RS0579-11 |
22 June 2011 |
17 July 2011 to 16 Jan 2012 |
Valid |
|
GW-RS0645-11 |
18 July 2011 |
22 Jul 2011 to 21 Jan 2012 |
Valid |
|
GW-RS0649-11 |
22 July 2011 |
1 Aug 2011 to 31 Jan 2012 |
Valid |
|
GW-RS0691-11 |
25 July 2011 |
27 July 2011 to 26 Jan 2012 |
Valid |
|
GW-RS0716-11 |
2 Aug 2011 |
12 Aug 2011 to 11 Feb 2012 |
Valid |
|
GW-RS0722-11 |
2 Aug 2011 |
5 Aug 2011 to 5 Oct 2011 |
Valid |
|
GW-RS0723-11 |
12 Aug 2011 |
15 Aug 2011 to 14 Feb 2012 |
Valid |
|
GW-RS0833-11 |
8 Sept 2011 |
10 Sept 2011 to 4 Mar 2012 |
Valid |
|
GW-RS0857-11 |
16 Sept 2011 |
6 Oct 2011 to 5 Apr 2011 |
Valid |
Discharge Licence |
WT00006249-2010 |
22 Mar 2010 |
31 Mar 2015 |
Valid |
WT00006436-2010 |
15 Apr 2010 |
30 Apr 2015 |
Valid |
|
WT00006673-2010 |
14 May 2010 |
31 May 2015 |
Valid |
|
WT00006757-2010 |
28 May 2010 |
31 May 2015 |
Valid |
|
WT00007129-2010 |
28 July 2010 |
31 Jul 2015 |
Valid |
|
WT00008982-2011 |
26 April 2011 |
30 Apr 2016 |
Valid |
|
WT00009691-2011 |
1 Aug 2011 |
31 July 2016 |
Valid |
|
Billing Account under Waste
Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Billing
Account under Waste Disposal Ordinance (Marine) |
7011496 |
6 Oct 2010 |
N/A |
Valid |
Registration as Chemical Waste
Producer |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
WPN5213-839-C3593-02 |
22 Sep
2010 |
N/A |
Valid |
|
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
EP/MD/12-012 |
6 May 2011 |
29 May 2011 to 28 Nov
2011 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate
Sites) & Type 2 ¡V Confined Marine disposal) |
EP/MD/12-046 |
4 Aug 2011 |
10 Aug 2011 to 9 Sept 2011 |
Expired |
EP/MD/12-056 |
2 Sept 2011 |
10 Sept 2011 to 9 Oct 2011 |
Valid |
Table
3.7 Summary of submission status under
FEP-03/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 1.12 |
Commencement Date of
Construction of Marine Works |
8 April 2010 |
Condition 2.6 |
Management Organization of Main
Construction Companies |
10 April 2010 |
Condition 2.7 |
Works Schedule and Location
Plans |
8 April 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan
Rev. H |
15 Feb 2011 |
Condition 2.9 |
Silt Screen Deployment Plan |
21 April 2010 |
|
Supplementary Information for
Existing WSD Salt Water Intakes at Quarry Bay and Sai Wan Ho |
5 Oct 2010 |
Condition 2.12 (d) |
Alternative Proposal on
Concurrent Dredging for Sewage Pipeline and Cross Harbour Water Mains |
19 Apr 2011 |
Condition 2.17 |
Noise Management Plan |
6 May 2010 |
Condition 2.18 |
Landscape Plan (Combined
Version) |
5 Aug 2011 |
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V
Tunnel (Causeway Bay Typhoon Shelter Section)
3.1.7.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no.
HY/2009/15 under EP-356/2009 are shown in Table 3.8 and
Table 3.9.
Table
3.8 Cumulative Summary of Valid Licences
and Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0220-11 |
16 Mar 2011 |
16 Mar to 15 Sep 2011 |
Expired |
|
GW-RS0308-11 |
1 Apr 2011 |
4 Apr to 27 Sep 2011 |
Cancelled |
|
GW-RS0594-11 |
27 Jun 2011 |
29 Jun to 28 Dec 2011 |
Cancelled |
|
GW-RS0710-11 |
3 Aug 2011 |
5 Aug 2011 to 1 Feb 2012 |
Cancelled |
|
GW-RS0727-11 |
11 Aug 2011 |
24 Aug 2011 to 23 Feb 2012 |
Cancelled |
|
GW-RS0749-11 |
11 Aug 2011 |
15 Aug 2011 to 7 Feb 2012 |
Valid |
|
GW-RS0820-11 |
5 Sep 2011 |
8 Sep 2011 to 7 Mar 2012 |
Valid |
|
GW-RS0847-11 |
14 Sep 2011 |
19 Sep 2011 to 16 Mar 2012 |
Valid |
|
GW-RS0858-11 |
16 Sep 2011 |
18 Sep 2011 to 16 Mar 2012 |
Valid |
|
GW-RS0883-11 |
4 Oct 2011 |
5 Oct 2011 to 4 Apr 2012 |
Valid |
Registration as a Chemical
Waste Producer |
WPN5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Water Discharge Licence |
WT00008780-2011 |
22 Mar 2011 |
22 Mar 2011 to 31 Mar 2016 |
Valid |
|
WT00008905-2011 |
11 Apr 2011 |
11 Apr 2011 to 30 Apr 2016 |
Valid |
Billing Account under Waste Disposal Ordinance |
7011553 |
30 Sep 2010 |
27 Sep 2010 to 27 Jan 2016 |
Valid |
Billing Account under Waste Disposal Ordinance (Dumping by
Vessel) |
7011761 |
28 Apr 2011 |
1 May 2011 to 30 Oct 2011 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
EP/MD/12-037 |
20 Jul 2011 |
20 Jul 2011 to 19 Jan 2012 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate
Sites) & Type 2 ¡V Confined Marine disposal) |
EP/MD/12-042 |
28 Jul 2011 |
1 Aug 2011 to 31 Aug 2011 |
Expired |
EP/MD/12-051 |
29 Aug 2011 |
1 Sep 2011 to 30 Sep 2011 |
Valid till 30 Sep 2011 |
|
|
EP/MD/12-069 |
27 Sep 2011 |
1 Oct 2011 to 31 Oct 2011 |
To be Valid on 1 Oct 2011 |
Dumping Permit (Type 3 ¡V Special Treatment / Disposal
contained in Geosynthetic Containers) |
EP/MD/12-015 |
26 Sep 2011 |
11 Oct 2011 to 10 Nov 2011 |
Valid |
Table
3.9 Summary of submission status under
FEP-04/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.7 |
Amendment for Works Schedule
and Location Plans |
12 Nov 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan
Rev 2 |
11 May 2011 |
Condition 2.9 |
Silt Screen Deployment Plan
Rev3 |
15 Jun 2011 |
Condition 2.18 |
Amendment for Proposal for the
Removal of Odorous Sediment and Slime |
2 Aug 2011 |
Condition 2.21 |
Landscape Plan |
18 Feb 2011 |
Amendment for Noise Management
Plan |
27 Jan 2011 |
3.1.8.
Implementation status of the recommended mitigation
measures during this reporting period is presented in Appendix 3.1.
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line
3.1.9.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no. HK/2010/06
under EP-356/2009 are shown in Table 3.10 and Table 3.11.
Table
3.10 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2010/06
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
N/A |
Valid |
Notification of Works Under APCO |
326344 |
18 Jan 2011 |
N/A |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0293-11 |
1 Apr 2011 |
6 Apr 2011 to 5 Oct 2011 |
Valid |
|
GW-RS0605-11 |
29 Jun
2011 |
13 Jul 2011 to 12 Jan 2012 |
Valid |
|
GW-RS0879-11 |
22 Sept 2011 |
6 Oct 2011 to 5 Apr 2012 |
Valid |
Billing Account under Waste Disposal Ordinance |
7012338 |
16 Feb 2011 |
N/A |
Valid |
Registration as Chemical Waste Producer |
WPN5213-134-G2533-01 |
11 Feb 2011 |
N/A |
Valid |
Water Discharge Licence |
WT00009619-2011 |
11 July 2011 |
11 July 2011 to 31 July 2016 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
EP/MD/12-030 |
11 Aug 11 |
12 Aug 2011 to 11 Feb 2012 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate
Sites) & Type 2 ¡V Confined Marine disposal) |
EP/MD/12-029 |
11 Aug 2011 |
12 Aug 2011 to 11 Sept 2011 |
Expired |
EP/MD/12-059 |
11 Sep 2011 |
12 Sep 2011 to 11 Oct 2011 |
Valid |
Table
3.11 Summary of
submission status under EP-356/2009 and FEP-05/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.7 |
Works Schedule and Location
Plans |
11 March 2011 |
Condition 2.8 |
Revised Silt Curtain Deployment
Plan |
31 Aug 2011 |
Condition 2.9 |
Silt Screen Deployment Plan |
11 April 2011 |
Condition 2.23 |
Noise Management Plan |
11 March 2011 |
Noise Monitoring Stations
4.1.1.
The noise monitoring stations for the Project are
listed and shown in Table 4.1 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.1 Noise
Monitoring Station
Station |
Description |
M1a |
Harbour
Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria
Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta
Secondary School |
Real-time Noise Monitoring Stations
4.1.2.
The real-time noise monitoring stations for the
Project are listed and shown in Table 4.2 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.2 Real Time Noise Monitoring Station
District |
Station |
Description |
Tin
Hau |
RTN1 |
FEHD Hong Kong Transport Section
Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison
Centre |
Noise Monitoring Parameters, Frequency and Duration
4.1.3.
The construction noise
level shall be measured in terms of the A-weighted equivalent continuous sound
pressure level (Leq). Leq (30 minutes) shall be used as
the monitoring parameter for the time period between 0700 and 1900 hours on
normal weekdays. For all other time periods, Leq (5 minutes) shall
be employed for comparison with the Noise Control Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
4.1.4.
Noise monitoring shall be carried out at all the
designated monitoring stations. The monitoring frequency shall depend on the
scale of the construction activities. The following is an initial guide on the
regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
¡P
one set of
measurements between 0700 and 1900 hours on normal weekdays.
4.1.5.
If construction works are extended to include works
during the hours of 1900 ¡V 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
Monitoring Equipment
4.1.6.
As referred to in the Technical Memorandum ™ issued
under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring.
Immediately prior to and following each noise measurement the accuracy of the
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements may be accepted as
valid only if the calibration level from before and after the noise measurement
agree to within 1.0 dB.
4.1.7.
Noise measurements shall not be made in fog, rain,
wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s.
The wind speed shall be checked with a portable wind speed meter capable of
measuring the wind speed in m/s.
Air Quality Monitoring Stations
4.2.1.
The air monitoring stations for the Project are
listed and shown in Table 4.3 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table
4.3 Air Monitoring Station
Station ID |
Monitoring Location |
Description |
CMA1b |
Oil Street Community Liaison Centre |
North
Point |
CMA2a |
Causeway Bay Community Centre |
Causeway
Bay |
CMA3a |
CWB PRE
Site Office * |
Causeway
Bay |
CMA4a |
Society for the Prevention of
Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds opposite to
Pedestrian Plaza |
Wan Chai |
CMA6a |
WDII PRE
Site Office * |
Wan Chai |
* Remarks:
As per the ENPC meeting in January 2011, the monitoring stations CMA3a - Future
CWB site office at Wanchai Waterfront Promenade and CMA6a - Future AECOM site
office at Work Area were renamed as remark.
Air Monitoring Parameters, Frequency and Duration
4.2.2.
One-hour and 24-hour TSP levels should be measured
to indicate the impacts of construction dust on air quality. The 24-hour TSP
levels shall be measured by following the standard high volume sampling method
as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part
50), Appendix B.
4.2.3.
All relevant data including temperature, pressure,
weather conditions, elapsed-time meter reading for the start and stop of the
sampler, identification and weight of the filter paper, and any other local
atmospheric factors affecting or affected by site conditions, etc., shall be
recorded down in detail.
4.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and Monitoring Equipment
4.2.5.
High volume samplers (HVSs) in compliance with the
following specifications shall be used for carrying out the 1-hour and 24-hour
TSP monitoring:
¡P
0.6 - 1.7 m3 per
minute adjustable flow range;
¡P
equipped with a
timing / control device with +/- 5 minutes accuracy for 24 hours operation;
¡P
installed with
elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
¡P
capable of
providing a minimum exposed area of 406 cm2;
¡P
flow control
accuracy: +/- 2.5% deviation over 24-hour sampling period;
¡P
equipped with a
shelter to protect the filter and sampler;
¡P
incorporated
with an electronic mass flow rate controller or other equivalent devices;
¡P
equipped with a
flow recorder for continuous monitoring;
¡P
provided with a
peaked roof inlet;
¡P
incorporated
with a manometer;
¡P
able to hold and
seal the filter paper to the sampler housing at horizontal position;
¡P
easily
changeable filter; and
¡P
capable of
operating continuously for a 24-hour period.
4.2.6.
Initial calibration of dust monitoring equipment
shall be conducted upon installation and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally recognized
primary standard and be calibrated annually. The concern parties such as IEC shall
properly document the calibration data for future reference. All the data
should be converted into standard temperature and pressure condition.
Laboratory Measurement / Analysis
4.2.7.
A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
4.2.8.
An alternative non-HOKLAS accredited
laboratory was set-up for carrying out the laboratory
analysis, the laboratory equipment was approved by the ER on 8 February 2011 and the measurement procedures were witnessed by the IEC. Any measurement performed by the laboratory was be demonstrated to the satisfaction of the ER and IEC. IEC shall
regularly audit to the measurement performed by the laboratory to ensure the
accuracy of measurement results.
4.2.9.
Filter paper of size 8" x 10" shall be
labelled before sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over 24-hours and
be pre-weighed before use for the sampling.
4.2.10. After
sampling, the filter paper loaded with dust shall be kept in a clean and
tightly sealed plastic bag. The filter paper shall then be returned to the
laboratory for reconditioning in the humidity controlled chamber followed by
accurate weighing by an electronic balance with readout down to 0.1 mg. The
balance shall be regularly calibrated against a traceable standard.
4.2.11. All the
collected samples shall be kept in a good condition for 6 months before
disposal.
impact monitoring for odour patrol
4.2.12. Odour
patrols along the shorelines of Causeway Bay Typhoon Shelter and ex-Wan Chai
Public Cargo Working Area when there is temporary reclamation in Causeway Bay
Typhoon Shelter and/or in the ex-Wan Chai Public Cargo Working Area, or when
there is dredging of the odorous sediment and slime at the south-western corner
of the Causeway Bay Typhoon Shelter. Odour patrols will be carried out at
bi-weekly intervals during July, August and September by a qualified person of
the ET who shall:
¡P
be at least 16
years of age;
¡P
be free from any
respiratory illnesses; and
¡P
not be allowed
to smoke, eat, drink (except water) or use chewing gum or sweets 30 min
¡P
before and
during odour patrol
4.2.13. Odour
patrol shall be conducted by independent trained personnel / competent persons
patrolling and sniffing around the shore as shown in Figure 4.1 to detect any odour at
the concerned hours (afternoon is preferred for higher daily temperature).
4.2.14. The
qualified person will use the nose (olfactory sensor) to sniff odours at
different locations. The main odour emission sources and the areas to be
affected by the odour nuisance will be identified.
4.2.15. The
perceived odour intensity is to be divided into 5 levels which are ranked in
the descending order as follows:
¡P
0 - Not
detected. No odour perceived or an odour so weak that it cannot be easily characterized
or described;
¡P
1 - Slight
Identifiable odour, and slight chance to have odour nuisance;
¡P
2 - Moderate
Identifiable odour, and moderate chance to have odour nuisance;
¡P
3 - Strong
Identifiable, likely to have odour nuisance;
¡P
4 - Extreme
Severe odour, and unacceptable odour level.
4.2.16.
The findings including odour intensity, odour
nature and possible odour sources, and also the local wind speed and direction
at each location will be recorded. In addition, some relevant meteorological
and tidal data such as daily average temperature, and daily average humidity,
on that surveyed day will be obtained from the Hong Kong Observatory Station
for reference. The Action and Limit levels for odour patrol are shown in Appendix 6.1.
4.2.17.
The qualified odour patrol member has individual
n-butanol thresholds complied with the requirement of European Standard Method
of Air Quality ¡V Determination of Odour Concentration by Dynamic Olfactometry
(EN13725) in the range of 20 to 80 ppb. The certificate for the qualified odour
panel member is shown in Appendix
4.2.
4.3.1.
The EIA Report has identified that the key water
quality impact would be associated with the dredging works during the
construction phase. Marine water quality monitoring for dissolved oxygen (DO),
suspended solid (SS) and turbidity is therefore recommended to be carried out
at selected WSD flushing water intakes. The impact monitoring should be carried
out during the proposed dredging works to ensure the compliance with the water
quality standards.
4.3.2.
The updated EM&A Manual for EP-356/2009
(Version in March 2011) is approval by EPD on 29 April 2011. As such, the Action
Level and Limit Level for the wet season (April ¡V September) will be effected
and applied to the water quality monitoring data from 30 April 2011.
Water Quality Monitoring Stations
4.3.3.
It is proposed to monitor the water quality at 9
WSD salt water intakes and 12 cooling water intakes along the seafront of the
Victoria Harbour. The proposed water quality monitoring stations of the Project
are shown in Table 4.4 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.4 Marine
Water Quality Stations for Water Quality Monitoring
Station Ref. |
Location |
Easting |
Northing |
WSD Salt
Water Intake |
|||
WSD7 |
Kowloon South |
834150.0 |
818300.3 |
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
Quarry Bay |
839790.3 |
817032.2 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
Kennedy Town |
830750.6 |
816030.3 |
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
RW21 |
Wan Chai (Reprovision) |
836188.8 |
815911.1 |
Cooling
Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C2 |
Telecom House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase I |
835836.2 |
815910.0 |
C4e |
Wan Chai Tower and Great Eagle
Centre (Eastern) |
835932.8 |
815888.2 |
C4w |
Wan Chai Tower and Great Eagle
Centre (Western) |
835629.8 |
815889.2 |
C5e |
Sun Hung Kai Centre (Eastern) |
836250.1 |
815932.2 |
C5w |
Sun Hung Kai Centre (Western) |
836248.1 |
815933.2 |
C6 |
Excelsior
Hotel |
837009.6 |
815999.3 |
C7 |
Windsor House |
837193.7 |
816150.0 |
C8 |
City Garden |
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
RC1 |
Proposed
HKAPA Extension |
835487.7 |
815987.7 |
RC5 |
Sun Hung
Kai Centre (Reprovision) |
836291.4 |
816029.7 |
RC7 |
Windsor House (Temporary Dilution) |
837245.2 |
816156.6 |
Water Quality Parameters
4.3.4.
Monitoring of dissolved oxygen (DO), turbidity and
suspended solids (SS) shall be carried out at WSD flushing water intakes and
cooling water intakes. DO and Turbidity are measured in-situ while SS is
determined in laboratory.
4.3.5.
In association with the water quality parameters,
other relevant data shall also be measured, such as monitoring
location/position, time, sampling depth, water temperature, pH, salinity,
dissolved oxygen (DO) saturation, weather conditions, sea conditions, tidal
stage, and any special phenomena and work underway at the construction site
etc.
Sampling Procedures and Monitoring Equipment
4.3.6.
The interval between two sets of monitoring should
not be less than 36 hours except where there are exceedances of Action and/or
Limit Levels, in which case the monitoring frequency will be increased. Table
4.5 shows the proposed monitoring frequency and water quality
parameters. Duplicate in-situ measurements and water sampling should be carried
out in each sampling event. For selection of tides for in-situ measurement and
water sampling, tidal range of individual flood and ebb tides should be not
less than 0.5m.
Table 4.5 Marine
Water Quality Monitoring Frequency and Parameters
Activities |
Monitoring Frequency1 |
Parameters2 |
During the 4-week baseline
monitoring period |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
During marine
construction works |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
After
completion of marine construction works |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
Notes:
1.
For selection of tides for in-situ measurement and water
sampling, tidal range of individual flood and ebb tides should be not less than
0.5m.
2.
Turbidity should be measured in situ whereas SS should be
determined by laboratory.
Dissolved Oxygen and Temperature Measuring
Equipment
4.3.7.
The instrument should be a portable, weatherproof
dissolved oxygen measuring instrument complete with cable, sensor,
comprehensive operation manuals, and use a DC power source. It should be
capable of measuring:
¡P
a dissolved
oxygen level in the range of 0-20 mg/l and 0-200% saturation
¡P
a temperature of
0-45 degree Celsius
4.3.8.
It should have a membrane electrode with automatic
temperature compensation complete with a cable. Sufficient stocks of spare
electrodes and cables should be available for replacement where necessary.
(e.g. YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with
reel and cable or an approved similar instrument).
4.3.9.
Should salinity compensation not be build-in in the
DO equipment, in-situ salinity shall be measured to calibrate the DO equipment
prior to each DO measurement.
Turbidity Measurement Instrument
4.3.10. The
instrument should be a portable, weatherproof turbidity-measuring instrument
complete with comprehensive operation manual. The equipment should use a DC
power source. It should have a photoelectric sensor capable of measuring
turbidity between 0‑1000 NTU and be complete with a cable (e.g. Hach model
2100P or an approved similar instrument).
Sampler
4.3.11. A water
sampler comprises a transparent PVC cylinder, with a capacity of not less than
2 litres, and can be effectively sealed with latex cups at both ends. The
sampler should have a positive latching system to keep it open and prevent
premature closure until released by a messenger when the sampler is at the
selected water depth (e.g. Kahlsico Water Sampler or an approved similar
instrument).
Sample Container and Storage
4.3.12. Water
samples for suspended solids measurement should be collected in high-density
polythene bottles, packed in ice (cooled to 4¢XC without being frozen), and
delivered to ALS Technichem (HK) Pty Ltd. as soon as possible after collection
for analysis.
Water Depth Detector
4.3.13. A
portable, battery-operated echo sounder shall be used for the determination of
water depth at each designated monitoring station. This unit can either be
handheld or affixed to the bottom of the workboat, if the same vessel is to be
used throughout the monitoring programme.
Salinity
4.3.14. A portable
salinometer capable of measuring salinity in the range of 0-40 ppt shall be
provided for measuring salinity of the water at each of monitoring location.
Monitoring Position Equipment
4.3.15. A
hand-held or boat-fixed type digital Global Positioning System (GPS) with
waypoint bearing indication or other equivalent instrument of similar accuracy
shall be provided and used during monitoring to ensure the monitoring vessel is
at the correct location before taking measurements.
Calibration of In-situ Instruments
4.3.16. All
in-situ monitoring instrument shall be checked, calibrated and certified by a
laboratory accredited under HOKLAS or equivalent before use, and subsequently
re-calibrated at 3 monthly intervals throughout all stages of the water quality
monitoring. Responses of sensors and electrodes should be checked with
certified standard solutions before each use. Wet bulb calibration for a DO
meter shall be carried out before measurement at each monitoring location.
4.3.17. For the on
site calibration of field equipment by the ET, the BS 127:1993, "Guide to
Field and on-site test methods for the analysis of waters" should be
observed.
4.3.18. Sufficient
stocks of spare parts should be maintained for replacements when necessary. Backup
monitoring equipment shall also be made available so that monitoring can proceed
uninterrupted even when some equipment is under maintenance, calibration, etc.
4.3.19. Current
calibration certificates of equipments are presented in Appendix
4.2.
Laboratory Measurement / Analysis
4.3.20. Analysis
of suspended solids has been carried out in a HOKLAS accredited laboratory, ALS
Technichem (HK) Pty Ltd. Water samples of about 1L shall be collected at the
monitoring stations for carrying out the laboratory SS determination. The SS
determination work shall start within 24 hours after collection of the water
samples. The SS determination shall follow APHA 19ed or equivalent methods
subject to the approval of IEC and EPD.
Enhanced Water Quality
Monitoring in the ex-Wan Chai Public Cargo
Working Area and the
Causeway Bay Typhoon Shelter
4.3.21. The
enhanced water quality monitoring and audit programme is to avoid aggravation
of odour nuisance from seawater arising from temporary reclamation in the
ex-Wan Chai Public Cargo Working Area and the Causeway Bay Typhoon Shelter.
4.3.22. Dissolved
oxygen monitoring at the intakes C6 and C7 in Causeway Bay Typhoon Shelter when
there is temporary reclamation in Causeway Bay Typhoon Shelter and at the
south-western and south-eastern corners of the ex-Wan Chai Public Cargo Working
Area. The proposed water quality monitoring stations of the Project are shown
in Table 4.6 and Figure 4.1.
Table
4.6 Marine Water
Quality Stations for Enhanced Water Quality Monitoring
Station |
Location |
C6 |
Excelsior Hotel |
C7 |
Windsor
House |
Ex-WPCWA-SW |
South-western of the ex-Wan Chai Public Cargo
Working Area |
Ex-WPCWA-SE |
South-eastern of the ex-Wan Chai Public Cargo
Working Area |
4.3.23. The
monitoring of dissolved oxygen are to be carried out 3 days per week, at
mid-flood and mid-ebb tides for 3 water depths (1m below water surface,
mid-depth and 1m above sea bed, except where the water depth less than 6m, the
mid-depth may be omitted. If the water depth be equal to or less than 3m, only
the mid-depth will be monitored).
Daily SS Monitoring and 24
hours Turbidity Monitoring System
4.3.24.
During dredging of the sediment at the
south-western corner of the Causeway Bay Typhoon Shelter, daily monitoring of
suspended solids and 24 hour monitoring of turbidity at the cooling water
intakes (C6 and C7) shall be conducted.
4.3.25.
The 24 hours monitoring of turbidty at the cooling water
intakes (C6 and C7) shall be established by setting up a continuous water quality
monitoring station in front of the intakes during the dredging activities. The
monitoring system include the turbidity sensor and data logger which is capable
of data capturing at every 5 minutes. The data sahll be downloaded daily and
compared with the Action and Limit level determined during the baseline water
qualtiy monitoring at the cooling water intake locations.
5.0.1.
The environmental monitoring will be implemented
based on the division of works areas of each designed project managed under
different contracts with separate FEP applied by individual contractors. Overall
layout showing work areas of various contracts, latest status of work
commencement and monitoring stations is shown in Figure
2.1 and Figure 4.1. The monitoring results
are presented in according to the Individual Contract(s).
5.0.2.
In the reporting month, the concurrent contracts
are as follows:
Contract no. HY/2009/11 Central - Wan Chai Bypass - North Point
Reclamation;
Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central-Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre; and
Contract no. HK/2009/02 Wan Chai Development Phase II ¡V Central-Wan Chai
Bypass at Wan Chai East
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section)
Contract no. HK/2010/06 Wan Chai Development Phase II ¡V Central-Wan Chai
Bypass over MTR Tsuen Wan Line
5.0.3.
The environment monitoring schedules for reporting
month and coming month are presented in Appendix 5.1.
Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass,
North Point Reclamation
5.1.1.
The proposed division of noise monitoring stations
for Contract no. HY/2009/11 are summarized in Table 5.1 below:
Table 5.1 Noise
Monitoring Stations for Contract no. HY/2009/11
Station |
Description |
M4b |
Victoria Centre |
M5b |
City Garden |
5.1.2.
Day time and evening period noise monitoring was
conducted at the City Garden and Victoria Centre in the reporting month.
5.1.3.
Noise monitoring results measured in this reporting
period are reviewed and summarized. No exceedance was recorded in the reporting
month. Details of noise monitoring results and graphical presentation can be
referred in Appendix
5.2.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC, Contract no. HK/2009/02 - Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East and Contract
no. HK/2010/06 Wan Chai Development Phase II ¡V Central-Wan Chai Bypass over MTR
Tsuen Wan Line
5.1.4.
The proposed division of noise monitoring stations
are summarized in Table 5.2 below.
Table 5.2 Noise
Monitoring Station for Contract nos. HK/2009/01, HK/2009/02 and HK/2010/06
Station |
Description |
M1a |
Harbour Road Sports Centre |
5.1.5.
Daytime and evening period noise monitoring was
conducted at the Harbour Road Sport Centre in the reporting month.
5.1.6.
Three limit level exceedances were recorded at M1a
- Harbour Road Sports Centre on 7, 15 and 20 September 2011 during restricted hour. Major noise source was
contributed from Tonnochy Road and water sport competition at Wan Chai Training
Swimming Pool.
Contract
no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter
Section)
5.1.7.
The noise monitoring for HY/2009/15 was commenced
on 10 November 2010. The proposed division of noise monitoring stations are
summarized in Table 5.3 below.
Table 5.3 Noise Monitoring Station for Contract no. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.8.
Noise monitoring results measured in the period of
daytime and restricted hour are reviewed and summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix
5.2.
5.2.1.
No
construction activity was conducted during night time period (2300 to 0700) in
this reporting month.
Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass,
North Point Reclamation
5.2.2.
The proposed divisions of real-time noise
monitoring stations are summarized in Table 5.4 below. Real time
noise monitoring for the filling works under contract no. HY/2009/11 was
commenced on 5 October 2010.
Table 5.4 Real
Time Noise Monitoring Station for Contract no. HY/2009/11
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong
Transport Section Whitefield
Depot |
North Point |
RTN2 |
Oil Street
Community Liaison Centre |
* Real time noise monitoring results and graphical presentation
during night time period are for information only.
5.2.3.
Real time noise monitoring results were reviewed
and no project-related Action and
Limit level exceedance were recorded in the reporting period. Details of
real time noise monitoring results and graphical presentation can be referred
to Appendix 5.5.
Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass,
North Point Reclamation
5.3.1.
The major construction activity of Contract no.
HY/2009/11 was filling works in the reporting month. Air monitoring had been
commenced on 11 August 2010. The proposed division of air monitoring stations is
summarized in Table 5.5 below.
Table 5.5 Air
Monitoring Stations for Contract no. HY/2009/11
Station |
Description |
CMA1b |
Oil Street Community Liaison Centre |
CMA2a |
Causeway Bay Community Centre |
5.3.2.
No exceedance was recorded in the reporting month.
Details of air monitoring results and graphical presentation can be referred in
Appendix 5.3.
5.3.3.
Since the land located the Oil Street Community
Liaison Centre will be handed-over to Food and Environmental Hygiene Department
(FEHD) for the construction of temporary FEHD depot by the end of September
2011, the air monitoring station
¡V CMA1b was then removed on
18 September 2011 and is not available for the air quality monitoring in the
existing location at Oil Street Community Liaison Centre. Owing to the
rejection
or no response from the nearby air sensitive receivers in allowing the
implementation of impact air quality monitoring,
CMA1b was proposed to be
temporary suspension until obtainment of a representative long-term air
monitoring station.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
5.3.4.
Air monitoring was commenced on 1 April 2011 in
response to the commencement of the land-filling work for Contract no.
HK/2009/01. The proposed division of air monitoring stations are summarized in Table
5.6 below. No exceedance was recorded in the reporting month.
Table 5.6 Air
Monitoring Stations for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to Pedestrian Plaza |
CMA6a |
WDII PRE Site Office |
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
5.3.5.
Air monitoring was commenced in mid-January 2011
for the land-filling work for Contract no. HK/2009/02. The proposed division of
air monitoring stations are summarized in Table 5.7 below. No
exceedance was recorded in the reporting month.
Table 5.7 Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
Contract no.
HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter
Section)
5.3.6.
Air monitoring was commenced on 15 March 2011 for
the land filling work for Contract no. HY/2009/15. The proposed division of air
monitoring stations are summarized in Table 5.8 below. No
exceedance was recorded in the reporting month.
Table
5.8 Air
Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.3.7.
The
odour patrol along the odour route with 8 sniffing locations was conducted by a
qualified odour patrol member on 7 and 20 September 2011 at the concerned hours (afternoon for higher daily
temperature).
The odour intensity detected at 8 locations was found to be from level 0 up to
level 1 which were below the Action Level. The details of the odour patrol
results and meteorological conditions and on the date of odour patrol are shown
in Appendix 5.3.
5.3.8.
Additional
sniffing location, OP2a was conducted for the place where is in the new
shoreline of ex-WPCWA (reclamation area) or odour likely detected by the odour
patrol member. The odour patrol route and the sniffing locations are shown in Figure 4.1.
Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass,
North Point Reclamation
5.4.1.
The proposed division of water monitoring stations
for Contract no. HY/2009/11 are summarized in Table 5.9 below:
Table 5.9 Water Monitoring Stations for Contract no. HY/2009/11
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
Quarry Bay |
839790.3 |
817032.2 |
Cooling Water Intake |
|||
C8 |
City Garden |
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
5.4.2.
Water monitoring for Contract no. HK/2009/01 was
commenced on 23 July 2010. The proposed division of water monitoring stations
are summarized in Table 5.10 below.
Table 5.10 Water
Monitoring Stations for Contract no. HK/2009/01
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD7 |
Kowloon South |
834150.0 |
818300.3 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
Kennedy Town |
830750.6 |
816030.3 |
Cooling Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C2 |
Telecom House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase I |
835836.2 |
815910.0 |
C4e |
Wan Chai Tower and Great
Eagle Centre (Eastern) |
835932.8 |
815888.2 |
C4w |
Wan Chai Tower and Great
Eagle Centre (Western) |
835629.8 |
815889.2 |
Remarks:
The water
monitoring stations for the dredging works under Contract No. HK/2009/01 should
also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at these
locations have not been carried out by others. Similarly, the water monitoring
stations for the dredging works under Contract No. HK/2009/02 should also
include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations have not been carried out by others.
Contract no. HK/2009/02 - Wan Chai Development Wan
Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
5.4.3.
Water monitoring for Contract no. HK/2009/02 was
commenced on 8 July 2010. The proposed division of water monitoring stations are
summarized in Table 5.11 below.
Table 5.11 Water
Monitoring Stations for Contract no. HK/2009/02
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
Cooling Water Intake |
|||
C5e |
Sun Hung Kai Centre (Eastern) |
836250.1 |
815932.2 |
C5w |
Sun Hung Kai Centre (Western) |
836248.1 |
815933.2 |
Remarks:
The water
monitoring stations for the dredging works under Contract No. HK/2009/01 should
also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at these
locations have not been carried out by others. Similarly, the water monitoring
stations for the dredging works under Contract No. HK/2009/02 should also
include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations has not been carried out by others.
Contract
no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over
MTR Tsuen Wan Line
5.4.4.
Water monitoring for Contract no. HK/2010/06 was
commenced on 8 March 2011. The proposed division of water monitoring stations
are summarized in Table 5.12 below.
Table 5.12 Water
Monitoring Stations for Contract no. HK/2009/02
Station Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C2 |
Telecom House |
835647.9 |
815864.4 |
Contract no.
HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter
Section)
5.4.5.
Due to the commencement of the maintenance dredging
on 10 November 2010, water quality monitoring for Contract no. HY/2009/15 was
commenced on 9 November 2010. The proposed division of water monitoring
stations are summarized in Table 5.13 below.
Table 5.13 Water
Monitoring Stations for Contract no. HY/2009/15
Station Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C6 |
Excelsior Hotel |
837009.6 |
815999.3 |
C7 |
Windsor House |
837193.7 |
816150.0 |
Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.
5.4.6.
The
enhanced water quality monitoring at C6, C7, Ex-WPCWA-SW and Ex-WPCWA-SE was
commenced on 13 January 2011. Dissolved oxygen levels at Ex-WPCWA and Causeway
Bay Typhoon Shelter on 29 August 2011, 1, 3, 5, 8, 10, 12, 14, 16, 19, 21, 24
and 26 September 2011 were exceeded. These DO exceedances were considered not
related to Project.
5.4.7.
There was no dredging of the sediment at the
south-western corner of the Causeway Bay Typhoon Shelter in this reporting
month. Thus, no daily monitoring of
suspended solids and 24 hours monitoring of turbidity
at the cooling water intakes at C7
was conducted.
5.4.8.
As
per the meeting with the representative of Excelsior Hotel and World Trade
Centre on 17 May 2011, they confirmed that the seawater intake for The
Excelsior was no longer in use and replaced by the connected permanent water
supply from WSD pipelines since 11 January 2011. Thus, the impact water quality
monitoring for the cooling intake - C6 was terminated effective from 26 May
2011 and no compliance checking for intake water monitoring at C6 was
undertaken in this reporting month.
5.4.9.
Water monitoring results measured in this reporting
period are reviewed and summarized. Details of water quality monitoring results
and graphical presentation can be referred in Appendix
5.4.
Table 5.14 Summary
of Water Quality Monitoring Exceedances in Reporting Month
Water Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
||
HY/2009/11 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD10 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD15 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C8 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
|
C9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/01 |
WSD19 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD20 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD7 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C3 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C4e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C4w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/01 & HK/2010/06 |
C2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
C5w |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD21 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HY/2009/15 |
C7 |
2 |
0 |
0 |
0 |
0 |
0 |
4 |
0 |
0 |
0 |
0 |
0 |
Total |
2 |
0 |
0 |
1 |
0 |
0 |
4 |
0 |
1 |
1 |
0 |
0 |
Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.
5.4.10. Enhanced DO monitoring at 4
monitoring stations in Causeway Bay Typhoon Shelter and Ex-Public Cargo Works
Area was conducted three days per week during the reporting period. The action
and limit level exceedances of water quality monitoring are summarized in Table 5.15.
Table 5.15 Summary
of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
AL |
LL |
AL |
LL |
||
HY/2009/15 |
C6 |
2 |
2 |
4 |
1 |
C7 |
3 |
0 |
4 |
2 |
|
Ex-WPCWA SW |
0 |
3 |
0 |
9 |
|
Ex-WPCWA SE |
1 |
5 |
5 |
8 |
|
Total |
6 |
10 |
13 |
20 |
5.4.11.
Investigations were found that the exceedances are
not related to the Project works. The details of the recorded excedances can be
referred to the Section 6.3.
Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass,
North Point Reclamation
5.5.1.
Non-inert C&D waste was disposed of in the
reporting month. Details of the waste flow table are summarized in Table
5.16.
Table
5.16 Details of
Waste Disposal for Contract no. HY/2009/11
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
NIL |
NIL |
N/A |
Inert
C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed, m3 |
146.25 |
589.875 |
SENT Landfill |
Non-inert
C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Chemical
waste disposed, kg |
N/A |
N/A |
N/A |
Marine
Sediment (Type 1 ¡V Open Sea Disposal), m3 |
0 (Bulk Volume) |
89,500 (Bulk Volume) |
South of Cheung Chau |
Marine
Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined
Marine Disposal) , m3 |
0 (Bulk Volume) |
129,200 (Bulk Volume) |
East of Sha Chau |
5.5.2.
Contractor submitted a letter dated 20 July 2011 to
confirm that the dredging works and dumping operation were completed.
Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central
¡VWanchai Bypass at HKCEC
5.5.3.
Inert and non- inert C&D waste were disposed of
in this reporting month. Details of the waste flow table are summarized in Table
5.17.
Table 5.17 Details of Waste Disposal for Contract no. HK/2009/01
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
2259.75 |
9,088.50 |
TKO137, TM38 |
Inert
C&D materials recycled, m3 |
0 |
389.96 |
N/A |
N/A |
|||
Non-inert
C&D materials disposed, m3 |
31.78 |
433.00 |
|
Non-inert
C&D materials recycled, kg |
459 |
116,917 |
N/A |
Chemical
waste disposed, kg |
1,000 |
4,830 |
N/A |
Marine
Sediment (Type 1 ¡V Open Sea Disposal), m3 |
6,163 (Bulk Volume) |
82,733.2 (Bulk Volume) |
South of Cheung Chau |
Marine
Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites)
& Type 2 ¡V Confined Marine Disposal) , m3 |
2,428 (Bulk Volume) |
15,027 (Bulk Volume) |
East of Cha Chau |
5.5.4.
There were marine sediments Type 1 ¡V Open Sea
Disposal disposed in the reporting month. The maximum dredging rate in HKCEC3w
and cross harbour water main are 446m3 and 623m3 per day
respectively, which is complied with the recommended maximum dredging rate,
1500m3 per day listed in Table 2 of FEP-02/356/2009.
Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at WanChai East
5.5.5.
Inert and non- inert C&D waste were disposed of
in this reporting month. Details of the waste flow table are summarized in Table
5.18.
Table
5.18 Details of
Waste Disposal for Contract no. HK/2009/02
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
12,712 |
38,347 |
TKO137 |
Inert
C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed, m3 |
16 |
184 |
SENT Landfill |
Non-inert
C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Chemical
waste disposed, kg |
0 |
2,115 |
N/A |
Marine
Sediment (Type 1 ¡V Open Sea Disposal), m3 |
0 |
150,157 (Bulk volume) |
South of Cheung Chau |
Marine
Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites)
& Type 2 ¡V Confined Marine Disposal) , m3 |
0 |
104,390 (Bulk volume) |
East of Sha Chau |
5.5.6.
There was no marine sediment disposed in the
reporting month.
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section)
5.5.7.
Inert and non- inert C&D waste were disposed of
in this reporting month. Details of the waste flow table are summarized in Table
5.19.
Table 5.19 Details of Waste Disposal for Contract no. HY/2009/15
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
16,543.8 |
26,093.7 |
Tuen Mun Area 38 |
|
5.4 |
64.1 |
TKO137 FB |
Inert
C&D materials recycled, m3 |
NIL |
184.0 |
To Contract HY/2009/11 |
275 |
304 |
ex-PCWA |
|
Non-inert
C&D materials disposed, m3 |
12.7 |
117.2 |
SENT Landfill |
Non-inert
C&D materials recycled, kg |
0 |
13,815 |
N/A |
Chemical
waste disposed, kg |
2,000 |
4,000 |
N/A |
Marine
Sediment (Type 1 ¡V Open Sea Disposal), m3 |
5,237 (Bulk Volume) |
32,900 (Bulk Volume) |
South of Cheung Chau |
Marine
Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined
Marine Disposal) , m3 |
560 (Bulk Volume) |
142,602 (Bulk Volume) |
East of Sha Chau |
Marine Sediment (Type 3 ¡V Special Treatment / Disposal
contained in Geosynthetic Containers) |
NIL (Bulk Volume) |
2,750 (Bulk Volume) |
East of Sha Chau |
5.5.8.
In
the reporting month, there were marine sediment Type 1 ¡V Open Sea Disposal and marine sediment Type 1 ¡V Open Sea
Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal disposed
from the maintenance dredging of navigation channel and mooring area. The
maximum dredging rate, 907m3 per day in the reporting month is
complied with the recommended maximum dredging rate as stipulated in FEP-04/356/2009
within the marine zones at TCBR.
Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass over MTR Tsuen Wan Line
5.5.9.
Inert C&D waste was disposed of in this
reporting month. Details of the waste flow table are summarized in Table
5.20.
Table 5.20 Details of Waste Disposal for Contract no. HK/2010/06
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
678 |
678 |
N/A |
Inert
C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert
C&D materials disposed, m3 |
NIL |
NIL |
N/A |
Non-inert
C&D materials recycled, kg |
NIL |
NIL |
N/A |
Chemical
waste disposed, L |
0 |
600 |
N/A |
Marine
Sediment (Type 1 ¡V Open Sea Disposal), m3 |
0 (Bulk Volume) |
2,338 (Bulk Volume) |
South Cheung Chau |
Marine
Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined
Marine Disposal) , m3 |
0 (Bulk Volume) |
11,165 |
East Sha Chau |
5.5.10. In the reporting month, there was no
dredging works at MTR tunnel crossing and no marine sediment disposed.
6.0.1.
The Event Action Plan for construction noise, air
quality and water quality are presented in Appendix 6.1.
Contract
no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation
6.1.1.
No exceedance was recorded in the reporting month.
Contract
no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at
HKCEC
6.1.2.
No exceedance was recorded in the reporting month.
Contract
no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
WanChai East
6.1.3.
Three limit level exceedances were recorded at M1a
- Harbour Road Sports Centre on 7, 15 and 20 September 2011
during restricted hour. Major noise source was
contributed from Tonnochy Road and water sport competition at Wan Chai Training
Swimming Pool. The construction works were complied with the conditions under
valid Construction Noise Permits during the measurement.
Contract no.
HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter
Section)
6.1.4.
No exceedance was recorded in the reporting month.
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line
6.1.5.
No exceedance was recorded in the reporting month.
Contract
no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation
6.2.1.
No
project-related exceedance was recorded in the reporting month.
6.3.1.
No exceedance was recorded in the TSP monitoring in
the reporting month.
6.3.2.
Odour
patrol was conducted on 7 and 20 September 2011. No exceedance was recorded in
reporting month.
Contract
no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation
6.4.1.
Referring to the
exceedances shown in Table 5.9, the turbidity exceedances were recorded
at C8 on 14 and 16 September 2011. Since there were numerous unknown outfalls
from the nearby coastal area closed to the cooling intakes C8, it causes the
potential for accumulation of pollutants near the intakes and may lead to
potential water quality deterioration at the seawater intake points.
6.4.2.
Major marine work was backfilling at NPR2E on 14
and 16 September 2011. Proper condition of silt curtain was provided between
the barge and the seawall during the filling material transportation. The
recorded turbidity exceedances were considered as not project-related.
Contract
no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at
HKCEC
6.4.3.
Exceedance
of turbidity level at WSD7 was recorded on 1 September 2011. Checked with
Contractor's works on 1 Sep 2011, there was no marine works at Tsim Sha Tsui
and Cross Harbour Water Main. In view that the water quality at monitoring
stations located nearest the marine work site were well below the Action level
and the silt screen at WSD7 was in proper condition, it was considered that recorded
exceedance was no related to Project.
Contract no. HK/2009/02 -
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
6.4.4.
No exceedance was recorded in the reporting month.
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)
6.4.5.
There
were DO level exceedances recorded at the ex- WPCWA and Causeway Bay Typhoon
Shelter on 31 August, 1, 3, 5 , 8, 10, 12, 14, 16, 19, 21, 24 and 26 September
2011. The low DO levels were possible in relation to the low flow and recorded low
water depth. In view that no odour nuisance was detected during monitoring, the
DO exceedances were considered not related to the Project. With reference to
the odour patrol results on 7 and 20 September 2011, the detected odour
intensity at ex- WPCWA and Causeway Bay Typhoon Shelter was found to be from
level 0 up to level 1 which were below the Action Level. These DO exceedances
were considered as the natural variation and not related to the Project works.
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line
6.4.6.
No exceedance was recorded in the reporting month.
6.4.7.
Summary for notification of exceedances can be
referred to Appendix
6.2.
6.5.1.
There was no non-compliance from the site audits in
the reporting period. The observations and recommendations made in each individual
site audit session were presented in Section 8.
6.6.1.
There was no particular action taken since no
project-related non-compliance was recorded from the site audits and
environmental monitoring in the reporting period.
7.0.1.
According to Condition 3.4 of the EP-356/2009, this
section addresses the relevant cumulative construction impact due to the
concurrent activities of the current projects including the Central Reclamation
Phase III, Central-Wanchai Bypass and Island Eastern Corridor Link projects.
7.0.2.
From the Monthly EM&A report (August 2011) of
Central Reclamation Phase III (CRIII) the key works in September 2011 are as
follows:
¡P
Type A filling
in FRAW and FRAE above +2.5mPD;
¡P
General filling
works above +2.5mPD in IRAE;
¡P
Surcharging in
FRAW and FRAE;
¡P
Installation of
removable panels at caisson;
¡P
Installation of
remaining seawall blocks and retaining wall on the west side of culvert F;
¡P
Construction of
storm and foul drainage and gullies in hinterlands for Road P2 and Road D9;
¡P
Roadworks for
Road P2;
¡P
Construction of
GPO boundary wall;
¡P
Construction of
PLA boundary wall and entrance;
¡P
Construction of
Promenade enhancement works;
¡P
Construction of
buildings at PLA berth;
¡P
Road P2
Underpass structures;
¡P
Construction of
CWB structure;
¡P
Backfilling and
waterproofing works for CWB structure;
¡P
Importation of
fill material; and
¡P
Strengthening of
Man Yiu Street Footbridge
7.0.3.
According to the construction programme of Wan Chai
Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link
projects, the major construction activities at Reclamation Shoreline Sub-zones
under Wan Chai Development Phase II were the filling works at NPR2E and HKCEC1,
seawall block construction at TCBR1W, maintenance dredging of navigation
channel and mooring area, HKCEC3w and marine bored piling at MTR Tunnel
Crossing in the reporting month. The major environmental impact was water
quality impact at North Point, Causeway Bay and Wan Chai.
7.0.4.
The major environmental impacts generated from the
filling work at Central Reclamation Phase III were only located along the coastline
of Central and Admiralty. As no project related exceedance was recorded in the
Project, it was considered no adverse environmental impact caused by the
Project works. Thus, it is evaluated the cumulative construction impact from
the concurrent projects including Wan Chai Development Phase II and Central
Reclamation Phase III was insignificant.
8.0.1.
During this reporting month, weekly environmental
site audits were conducted for Contracts no. HY/2009/11, HK/2009/01, HK/2009/02,
HY/2009/15 and HK/2010/06. No non-conformance was identified during the site
audits.
8.0.2.
Five site inspections for Contract no. HY/2009/11
were carried out on 31 August, 6, 14, 20 and 27 September 2011. The results of
these inspections and outcomes are summarized in Table 8.1.
Table 8.1 Summary
of Environmental Inspections
for Contract no. HY/2009/11
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
110831_01 |
31-Aug-11 |
No
particular finding. |
-- |
-- |
110906_01 |
6-Sep-11 |
As the material at the seafront dropped into the
sea at NPR3 during the filling material transshipment, silty water was observed
between caisson seawall and barge. Even though silt curtain
was deployed during the operation, the contractor should clear those filling
materials near the seafront. |
Removal of the filling materials near the
seafront |
Completion
as observed on 20-Sep-11 |
110914_01 |
14-Sep-11 |
Fill
material accumulated along the seafront of NPR3 due to dropping off during
transshipment used to be cleaned up before end of work everyday. |
Removal of the filling materials near the
seafront |
Completion
as observed on 20-Sep-11 |
110914_02 |
14-Sep-11 |
Fill
material temporary stored at the north of channel U need to be cleaned to
avoid being washed by tidal wave. |
Removal of the fill material in the U-channel |
Completion
as observed on 20-Sep-11 |
110920_01 |
20-Sep-11 |
No
particular finding |
-- |
Completion
as observed on 27-Sep-11 |
110927_01 |
27-Sep-11 |
Idle
stockpiles shall be covered well or transported away from seafront. |
Trimming down the stockpile and cover the
stockpile where applicable. |
Completion
as observed on 4-Oct-11 |
8.0.3.
Four site inspections for Contract no. HK/2009/01
were carried out on 31 August, 7, 14 and 22 September 2011. Results of these
inspections and outcomes are summarized in Table 8.2.
Table
8.2 Summary of
Environmental Inspections for Contract no. HK/2009/01
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
110831_01 |
31-Aug-11 |
Floating
silt curtain at HKCEC water channel and east bridge shall be maintained. |
Weighting
down the silt curtain |
Completion
as observed on 7-Sep-11 |
110831_02 |
31-Aug-11 |
3-sides
with top cover enclosure for the grouting work shall be enhanced the
effectiveness to avoid dust emission. |
Providing
the proper shelter when grouting mixing |
Completion
as observed on 7-Sep-11 |
110831_03 |
31-Aug-11 |
FEP
and relevant CNP shall be displayed at site access of Pump House P5. |
Adhering
permit s and licences at the site access |
Completion
as observed on 7-Sep-11 |
110831_04 |
31-Aug-11 |
Material
shall be relocated away from the trees at P5. |
Relocation of the material away from the trees |
Completion
as observed on 7-Sep-11 |
110907_01 |
7-Sep-11 |
Contractor
was reminded to close the door of the plants to avoid noise emission. |
Closure of the door of plants |
Completion
as observed on 14-Sep-11 |
110914_01 |
14-Sep-11 |
The
discharge pipes arrangement at TST shall be improved to proceed the wastewater
treatment |
Improvement of the drainage system at TST |
Completion
as observed on 22-Sep-11 |
110922_01 |
22-Sep-11 |
The
construction material was found located closed to the trees at TST.
Contractor was reminded to relocate the materials away from the trees. |
Relocation of the material away from the trees |
Completion
as observed on 28-Sep-11 |
110922_02 |
22-Sep-11 |
The
drain hole of the drip tray at HKCEC1 shall
be plugged. |
Plugging
the drain hole of the drip tray and remove the stagnant water
inside it |
Completion
as observed on 28-Sep-11 |
8.0.4.
Four site inspections for Contract no. HK/2009/02
were carried out on 1, 8, 15 and 21 September 2011 during this reporting
period. The results of these inspections and outcomes are summarized in Table
8.3.
Table
8.3 Summary of
Environmental Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
110901_01 |
1-Sep-11 |
Protective
screen at mud-barge shall be regular maintained. |
Providing
the proper protective screen at the mud barge |
Completion
as observed on 8-Sep-11 |
110908_01 |
8-Sep-11 |
Rock-fill
material along the walkway of derrick barge (B22338Y) shall be removed. |
Regular
removal of the fill material at the walkway |
Completion
as observed on 15-Sep-11 |
110908_02 |
8-Sep-11 |
Sand
was observed located next to the gully at Wan Shing Street.
Protective measure to the drain shall be provided. |
Removal of the sand near the gully. Sand bags
were provided around the gully. |
Completion
as observed on 15-Sep-11 |
110908_03 |
8-Sep-11 |
Idling
stockpile at Wan Shing Street and Finger Pier shall be covered or other
measures to avoid dust emission. |
Covered the stockpile by tarpaulin sheet |
Completion
as observed on 15-Sep-11 |
110915_01 |
15-Sep-11 |
Oil
leakage was observed from the crawler drill rig at receiving pit. |
Maintenance
of the excavator and clearance of the oil stain. |
Completion
as observed on 21-Sep-11 |
110921_01 |
21-Sep-11 |
The
silt curtain shall be enhanced to have sufficient depth for the rock filling
works. |
Providing proper silt curtain when the rock filling
work was undertaken. |
Completion
as observed on 30-Sep-11 |
110921_01 |
21-Sep-11 |
The
sedimentation tank shall be enhanced for the wastewater treatment in Wan
Shing Street. |
Additional sedimentation tanks were provided at
Wan Ching Street. |
Completion
as observed on 30-Sep-11 |
110921_01 |
21-Sep-11 |
Chemical
container at Wan Shing Street shall be properly stored. |
Drip tray was provided for the chemical
container. |
Completion
as observed on 30-Sep-11 |
8.0.5.
Five site inspections for Contract no. HY/2009/15
were carried out on 30 August, 6, 15, 20 and 27 September 2011 in reporting
month. The results of these inspections and outcomes are summarized in Table
8.4.
Table
8.4 Summary of
Environmental Inspections for Contract no. HY/2009/15
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
110830_01 |
30-Aug-11 |
Drip
tray shall be plug and the stagnant water inside it shall be removed. |
Plugging
the drain hole of the drip tray and removed the stagnant water
inside it |
Completion
as observed on 6-Sep-11 |
110830_02 |
30-Aug-11 |
Water spraying shall be conducted for dust suppression. |
Water spraying on dry dusty surface. |
Completion
as observed on 6-Sep-11 |
110830_03 |
30-Aug-11 |
The
contractor was reminded to instruct the concrete driver to use wheel washing facilities at EXTCPWA. |
Instructed the concrete trucks¡¦
drivers to use wheel washing facilities |
Completion
as observed on 6-Sep-11 |
110906_01 |
6-Sep-11 |
Gaps
were found between seawall blocks (SE and NE corner of TS1). The contractor
was reminded to fill them up in order to prevent any overflow. |
Filling the gaps up in order to prevent any overflow of surface runoff |
Completion
as observed on 15-Sep-11 |
110906_02 |
6-Sep-11 |
Drip
tray shall be provided for oil drum as well as chemical label. |
Providing drip tray and chemical label for oil
drum |
Completion
as observed on 15-Sep-11 |
110915_01 |
15-Sep-11 |
Oil
leakage was observed from the broken oil drums. The contractor should provide
drip tray for oil drum storage, and disposed of the oil stains as chemical waste. (abutment A) |
Provide drip tray for oil drum and treated the contaminated soil as chemical waste |
Completion
as observed on 27-Sep-11 |
110915_02 |
15-Sep-11 |
Silty
water was observed discharged into the sea, even through the water was
treated by waste water treatment plant. The contractor was reminded to review
the efficiency of the waste water treatment plant. (TS1) |
Reviewed the efficiency of the waste water treatment plant |
Completion
as observed on 20-Sep-11 |
110920_01 |
20-Sep-11 |
Some
Gaps between seawall blocks were found not filled at TS1. |
Filling the gaps up in order to prevent any overflow |
Completion
as observed on 27-Sep-11 |
110920_02 |
20-Sep-11 |
Wastewater
from shoes washing facility was found leakage from the drainage at TS1. The
contractor should improve the drainage system to collect the water |
Improvement of the drainage system to collect and treat the waste water |
Completion
as observed on 27-Sep-11 |
110920_03 |
20-Sep-11 |
Relocation
of the oil drums under abutment A was observed and without drip tray. The soil
was contaminated by the leakage oil. |
Provided drip tray for oil drum and treated the contaminated soil as chemical waste |
Completion
as observed on 27-Sep-11 |
110920_04 |
20-Sep-11 |
Stockpile
at TS4 near the seafront should be covered properly. |
Provide tarpaulin or clean up the stockpile near
the seafront |
Completion
as observed on 27-Sep-11 |
110927_01 |
27-Sep-11 |
Wastewater
was found discharged to the u-channel near POC. The contractor was
reminded to treat the water prior to discharge properly. |
Treated the water prior to discharge properly |
Completion
as observed on 4-Oct-11 |
110927_02 |
27-Sep-11 |
Wastewater
leakage generated from the hydraulic excavator was observed at
Ex-WPCWA. |
Tidy up the wastewater |
Completion
as observed on 4-Oct-11 |
110927_03 |
27-Sep-11 |
The
contractor was reminded to enclose the dredging point by silt curtain
(temporary monitoring area) |
Enclosed the dredging point by silt curtain |
Completion
as observed on 4-Oct-11 |
Table 8.5 Summary
of Environmental Inspections for Contract no. HK/2010/06
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
110829_01 |
29-Aug-11 |
Floating debris was found between
western platform and barge. It shall be cleared up. |
Maintenance
of the silt curtain |
Completion as observed on 5-Sep-11 |
110829_02 |
29-Aug-11 |
Drain pipe shall be extended the edge at eastern platform. |
Extension
of drain pipe to the edge at eastern platform. |
Completion as observed on 5-Sep-11 |
110905_01 |
5-Sep-11 |
Floating debris inside the silt
curtain shall be removed. |
Regular
clearance of floating debris. |
Completion as observed on 12-Sep-11 |
110912_01 |
12-Sep-11 |
Drainage pipe along the west
platform shall be improved |
Improvement
of the drainage pipe at west platform. |
Completion as observed on 22-Sep-11 |
110922_01 |
22-Sep-11 |
The tarpaulin for the shelter of
grouting mixer shall be sealed up to achieve the dust suppression. |
Sealing
up the tarpaulin for the shelter |
Completion as observed on 27-Sep-11 |
110922_02 |
22-Sep-11 |
Regular water spraying on the dusty
surface on the platform. |
Water
spraying on the surface regularly. |
Completion as observed on 27-Sep-11 |
110927_01 |
27-Sep-11 |
The debris at west platform shall
be removed. |
Removal
of debris at the platform. |
Completion as observed on 4-Oct-11 |
9.0.1.
There
was one environmental complaint received on 26 August 2011 for the investigation
and follow-up action in the reporting month.
9.0.2.
A water impact complaint was received by ET on 29 August
2011. It was complained by Mr. Au from Cayley Property Management Limited
(CPML) that large amount of rubbishes were found at the harbour front adjacent
to their cooling water intake suction which caused 3 times of system breakdown
of the sea water pump on 9, 22 and 25 August 2011 after the contractors set up
the temporary garbage defender in function and collect the floating refuses,
but cannot eliminate all refuses, in particular the refuse coming from the
seabed. An ad-hoc inspection of the effectiveness of garbage defender was
conducted with RSS (CWB project team), contractors of HY/200911 and HY/2009/19,
ET and IEC on 29 August 2011.
9.0.3.
During on-site inspection, floating refuses were observed
occasionally outside the garbage defender. No conclusion could be made for the
source of these floating refuses. On the other hand, some of the refuses were
observed floating behind the garbage defender during investigation. All daily
cleaning actions had been taken by contractor to minimize floating refuse
inside the construction site. It was noted that the cooling water intake was
accessible to the public. As such, fish breeding and fishing activities were
observed even though a notice has already hoisted. Also, tripping of rubbish by
the passers-by could result in a lot of rubbish accumulated around the intake
point. Referring to the record provided by CPML, there were a lot of nylon/
plastic bags and nylon wire mesh that matched those rubbishes generated from
the public activities. The contractors were reminded to strengthen the
communication with City Garden and no further complaint from complainant was
received after proposed the mitigation measure.
9.0.4.
To follow up the
ICC complaint no. 1 ¡V 306740207 regarding the discharged muddy
water from work site to the seafront near Oil Street during heavy rain in last month, it was confirmed with RE that muddy
water was caused by a heap of earth being washed to the sea by heavy rain. The
heap of earth was referred as a small stockpile placed close to the seafront in
front of Oil Street within the site area under handover transition period from
contract HY/2009/11 to contract HY/2009/19. The necessary mitigation measures to
protect the small stockpile against rainfall were missing at the time of
complaint.
9.0.5.
Due to the
missing of mitigation measures to protect the small stockpile during handover
transition period, loose material was washed into the harbour when heavy rain came.
Muddy water was formed and dispersed in the sea that caused the water quality
and visual concern to the public. The complaint was considered as valid.
9.0.6.
Contractors were
advised to relocate the loose materials away from the coastline as far as
practicable. Any loose material placed which needed to be placed near the coastline
shall be properly compacted or covered as appropriate. To avoid any further
environmental deficiency, Contractors shall ensure all necessary environmental mitigation
measures will not be missing during site area handover.
9.0.7.
The details of cumulative complaint log and updated
summary of complaints are presented in Appendix
9.1.
9.0.8.
Cumulative statistic on complaints and successful
prosecutions are summarized in Table 9.1 and Table 9.2
respectively.
Table
9.1 Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement works (Mar 2010) to last
reporting month |
21 |
September 2011 |
1 |
Project-to-Date |
22 |
Table
9.2 Cumulative Statistics on Successful
Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1. The
EM&A programme was carried out in accordance with the EM&A Manual
requirements, minor alterations to the programme proposed were made in response
to changing circumstances.
10.0.2. The
scheduled construction activities and the recommended mitigation measures for
the coming month are listed in Table 10.1.
Table 10.1 Construction
Activities and Recommended Mitigation Measures in
Coming Reporting Month
Contract
No. |
Key Construction Works |
Recommended
Mitigation Measures |
HY/2009/11 |
¡P
Reclamation works; ¡P
Slotted panel fixing; ¡P
Geo-textile laying; ¡P
Drainage Construction works; ¡P
Outfall construction works
(Open Channel U); ¡P
Sheet Pilling; ¡P
Pre-casting and Installation of
Coping; and ¡P
Construction and installation
of seawall concrete block |
¡P
To avoid concurrent noisy operation ¡P
To locate the plant and
equipments far away to the noise sensitive receivers ¡P
Daily visual inspection of silt screen and silt curtain to
ensure its operation properly ¡P
Daily clearance of floating debris behind the silt screen |
HK/2009/01 |
¡P
Dredging works from CH190to
CH260 for the reclamation of HKCEC3W would be commenced upon giving 7-day
advance notice to EPD; ¡P
Reclamation of HKCEC3W (up to
CH120) within the HKCEC Water Channel; ¡P
Installation of sheet pile
water channel at Dome Promenade (from CH120 to CH160); ¡P
Installation of silt screen
(type 3) at TST; ¡P
Dredging woks from CH50 to
Ch250 for subsequent cross-harbour watermains installation off TST would be
commenced. A trial dredging operation near the Avenue of Stars would be
demonstrated to the representatives of LCSD on 22 September. ¡P
Installation of cross harbour
watermains nos. A9 &B9 and A10 & B10; ¡P
Sheet pipe pile wall and the
associated ground treatment works for the trenches of the proposed cross harbour
watermaines nos. A18 & B18 works be commenced after the subsequent
removal of the temporary steel platform; ¡P
Trench excavation works at Zone
A1-2; ¡P
Works would be continued out at
Zone A2-3B, A3-3, A3-2A, A4-3B, A4-3B, A4-3C, A5-5, B1-4, B4-2 and B4-5; ¡P
Heading Nos. H2, H5 and H6
(Mainlaying works by trenchless method); and ¡P
Heading Nos. H3, H4 and H9
(Mainlaying works by trenchless method) would be commenced after their
corresponding jacking pits had been excavated in Convention Avenue. |
¡P
To conform the installation and setting as in the silt
screen deployment plan ¡P
Frequency spray water on the dry dusty road and on the
surface of concrete breaking ¡P
To cover the dusty material or stockpile by impervious
sheet ¡P
To space out noisy equipment
and position as far as possible from sensitive receiver. ¡P
To well maintain the mechanical
equipments / machineries to avoid abnormal noise nuisance. ¡P
Machines and plant that may be
in intermittent use should be shut down between work periods or should be
throttled down to a minimum ¡P
Daily visual inspection of silt screen and silt curtain to
ensure its operation properly |
HK/2009/02 |
¡P
Operating Tseung Kwan O Public
Fill Sorting Facility; ¡P
Construction of passenger
terminal; ¡P
Demolition of remaining finger
pier; ¡P
Construction of mass seawall
coping at Expo Drive East; ¡P
Trench excavation and pipe
laying works along Harbour Road; ¡P
Trench excavation and deck over
at Tonnochy Road; ¡P
Top soffit slab at P7, P8 &
P9 pump stations; ¡P
Construction above -0.8mPDat
Wan Shing Street for WSD Salt Water Intake; ¡P
Pipeline jacking WSD intake A. ¡P
Pre-bored sheet pile works for
salt water intake culvert Bay1b & Bay 2; ¡P
Pre-bored H-pile for Box
Culvert N1 at WCR1 Area; ¡P
The 3rd and 4th loading test of
New Ferry Pier; ¡P
All piles excavation at new
ferry pier; ¡P
Grouting plug in piles of New
Ferry Pier; ¡P
Concreting for marine piles at
new ferry pier; ¡P
Dredging and fabrication of HDPE
pipe diffuser section for submarine outfall pipes; ¡P
Backfilling of bagged concrete
and rockfills for the installed submarine outfall pipes; ¡P
Excavation and lateral support
for receiving pits at Hung Hing Road; ¡P
Installation of temporary sheet
piles wall at WCR2; and ¡P
Installation of the temporary
water diversion steel frame |
¡P
To cover the dusty material or stockpile by impervious
sheet; ¡P
Frequency spray water on the dry dusty road and on the
surface of concrete breaking ¡P
To well maintain the mechanical equipments / machineries
to avoid abnormal noise nuisance and dark smoke emission ¡P
To conform the installation and setting as in the silt
screen and silt curtain deployment plan ¡P
Movable noise barrier shall be
deployed for demolition works ¡P
Daily visual inspection of silt screen and silt curtain to
ensure its operation properly |
HY/2009/15 |
¡P
Mooring rearrangement and
dredging at ME4; ¡P
Night time protection works at
CHT; ¡P
Construction of dewatering well
at Hung Hing Road and POC; and ¡P
Precautionary works at Abutment
A |
¡P
To conform the installation and setting as in the silt
screen and silt curtain deployment plan ¡P
Frequency spray water on the dry dusty road and on the
surface of concrete breaking ¡P
To cover the dusty material or stockpile by impervious
sheet ¡P
To space out noisy equipment
and position as far as possible from sensitive receiver. ¡P
Daily visual inspection of silt screen and silt curtain to
ensure its operation properly |
HK/2010/06 |
¡P
Installation of bored pile casing; ¡P
Excavation of bored piles; ¡P
Bored Pile Concreting; ¡P
Pre-drilling works; and ¡P
Installation of temporary
staging platforms |
¡P
To conform the installation and setting as in the silt
screen and silt curtain deployment plan ¡P
To space out noisy equipment
and position as far as possible from sensitive receiver. ¡P
Daily visual inspection of silt screen and silt curtain to
ensure its operation properly |