Contract No: HK/2009/05

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Work (Stage 1)

 

Environmental Permit no. EP-356/2009,

Further Evironmental permit nos. fep-01/356/2009, fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009 and Fep-05/356/2009

 

Monthly Environmental Monitoring & Audit Report

 

- September 2011 -

 

CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

Certified by:



 

 

 

 

 

                                               

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

11 October 2011


Table of contents

 

EXECUTIVE SUMMARY. 4

1.     Introduction. 9

1.1        Scope of the Report 11

1.2        Structure of the Report 11

2.     Project Background. 13

2.1        Background. 13

2.2        Scope of the Project and Site Description. 13

2.3        Division of the Project Responsibility. 14

2.4        Project Organization and Contact Personnel 15

3.     Status of Regulatory Compliance. 21

3.1        Status of Environmental Licensing and Permitting under the Project 21

4.     Monitoring Requirements. 30

4.1        Noise Monitoring. 30

4.2        Air Monitoring. 31

4.3        Water Quality Monitoring. 34

5.     Monitoring Results. 39

5.1        Noise Monitoring Results. 39

5.2        Real-time Noise Monitoring. 40

5.3        Air Monitoring Results. 41

5.4        Water Monitoring Results. 42

5.5        Waste Monitoring Results. 46

6.     Compliance Audit. 50

6.1        Noise Monitoring. 50

6.2        Real-time noise Monitoring. 50

6.3        Air Monitoring. 50

6.4        Water Quality Monitoring. 51

6.5        Review of the Reasons for and the Implications of Non-compliance. 51

6.6        Summary of action taken in the event of and follow-up on non-compliance. 51

7.     Cumulative Construction Impact due to the Concurrent Projects. 52

8.     Environmental Site Audit. 53

9.     Complaints, Notification of Summons and Prosecution. 56

10.    Conclusion. 59


lIST OF TABLES

 

Table I         Summary of Water Quality Monitoring Exceedances in Reporting Month

Table II        Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month

Table 2.1     Schedule 2 Designated Projects under this Project

Table 2.2      Details of Individual Contracts under the Project

Table 2.3      Contact Details of Key Personnel

Table 3.1      Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Table 3.2      Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/11

Table 3.3      Summary of submission status under FEP-01/356/2009 Condition

Table 3.4      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Table 3.5      Summary of submission status under FEP-02/356/2009 Condition

Table 3.6      Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Table 3.7      Summary of submission status under FEP-03/356/2009 Condition

Table 3.8      Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Table 3.9      Summary of submission status under FEP-04/356/2009 Condition

Table 3.10    Cumulative Summary of Valid Licences and Permits under Contract no. HK/2010/06

Table 3.11    Summary of submission status under EP-356/2009 and FEP-05/356/2009 Condition

Table 4.1      Noise Monitoring Station

Table 4.2      Real Time Noise Monitoring Station

Table 4.3      Air Monitoring Station

Table 4.4     Marine Water Quality Stations for Water Quality Monitoring

Table 4.5      Marine Water Quality Monitoring Frequency and Parameters

Table 4.6     Marine Water Quality Stations for Enhanced Water Quality Monitoring

Table 5.1     Noise Monitoring Stations for Contract no. HY/2009/11

Table 5.2     Noise Monitoring Station for Contract nos. HK/2009/01, HK/2009/02 and HK/2010/06

Table 5.3     Noise Monitoring Station for Contract no. HY/2009/15

Table 5.4      Real Time Noise Monitoring Station for Contract no. HY/2009/11

Table 5.5     Air Monitoring Stations for Contract no. HY/2009/11

Table 5.6     Air Monitoring Stations for Contract no. HK/2009/01

Table 5.7     Air Monitoring Station for Contract no. HK/2009/02

Table 5.8     Air Monitoring Station for Contract no. HY/2009/15

Table 5.9     Water Monitoring Stations for Contract no. HY/2009/11

Table 5.10    Water Monitoring Stations for Contract no. HK/2009/01

Table 5.11    Water Monitoring Stations for Contract no. HK/2009/02

Table 5.12    Water Monitoring Stations for Contract no. HK/2009/02

Table 5.13    Water Monitoring Stations for Contract no. HY/2009/15

Table 5.14    Summary of Water Quality Monitoring Exceedances in Reporting Month

Table 5.15    Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month

Table 5.16    Details of Waste Disposal for Contract no. HY/2009/11

Table 5.17    Details of Waste Disposal for Contract no. HK/2009/01

Table 5.18    Details of Waste Disposal for Contract no. HK/2009/02

Table 5.19    Details of Waste Disposal for Contract no. HY/2009/15

Table 5.20    Details of Waste Disposal for Contract no. HK/2010/06

Table 8.1      Summary of Environmental Inspections for Contract no. HY/2009/11

Table 8.2     Summary of Environmental Inspections for Contract no. HK/2009/01

Table 8.3     Summary of Environmental Inspections for Contract no. HK/2009/02

Table 8.4     Summary of Environmental Inspections for Contract no. HY/2009/15

Table 8.5     Summary of Environmental Inspections for Contract no. HK/2010/06

Table 9.1      Cumulative Statistics on Complaints

Table 9.2      Cumulative Statistics on Successful Prosecutions

Table 10.1    Construction Activities and Recommended Mitigation Measures in Coming Reporting Month

 

 

lIST OF FIGUREs

 

Figure 2.1          Project Layout

Figure 2.2          Project Organization Chart

Figure 4.1         Locations of Environmental Monitoring Stations

 

 

 

lIST OF APPENDIces

 

Appendix 3.1     Environmental Mitigation Implementation Schedule

Appendix 4.1     Action and Limit Level

Appendix 4.2     Copies of Calibration Certificates

Appendix 5.1     Monitoring Schedule for Reporting Month and Coming month

Appendix 5.2     Noise Monitoring Results and Graphical Presentations

Appendix 5.3     Air Quality Monitoring Results and Graphical Presentations, and Odour Patrol Results

Appendix 5.4     Water Quality Monitoring Results and Graphical Presentations

Appendix 5.5     Real-time Noise Monitoring Results and Graphical Presentations

Appendix 6.1     Event Action Plans

Appendix 6.2     Summary for Notification of Exceedance

Appendix 9.1     Complaint Log

Appendix 10.1   Construction Programme of Individual Contracts

EXECUTIVE SUMMARY

  1. This is the Environmental Monitoring and Audit (EM&A) Monthly Report ¡V September 2011 for the Project of Wan Chai Development Phase II and Central-Wanchai Bypass under Environmental Permit no. EP-356/2009 and Further Environmental permit nos. FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009. This report presents the environmental monitoring findings and information recorded during the period 28th August 2011 to 27th September 2011. The cut-off date of reporting is at 27th of each reporting month.

 

Construction Activities for the Reported Period

  1. During this reporting period, the major work activities for Contract no. HY/2009/11 included:

¡P          Reclamation works;

¡P          Geo-textile laying;

¡P          Drainage Construction works;

¡P          Outfall construction works (Open Channel U);

¡P          Sheet Pilling;

¡P          Pre-casting of Coping; and

¡P          Construction & installation of Seawall Concrete Block

 

  1. During this reporting period, the major work activities for Contract no. HK/2009/01 included:

¡P          Installation of silt screen (type 1) at TST;

¡P          Seawall toe block installation for reinstating seawall at Zone B1-3;

¡P          Dredging within HKCEC Water Channel from CH160 to CH190 for Type 1 & 2 sediment;

¡P          Trench backfilling and seawall reinstatement for both the completed cross-harbour watermains and the seawall near Expo Promenade (Zone B1-3);

¡P          Installation of cross-harbour watermains nos. A8 & B8;

¡P          Final trimming within Principle Fairway for cross-harbour watermains installation;

¡P          Platform erection for crawler crane mobilization near the existing seawall at Salisbury Garden had been completed and WSD¡¦s consent had been given for mobilization of crawler crane to the jack-up barge. Mobilization;

¡P          The trench excavation works at Zone B1-4, B4-2, A1-2, A2-4A, A3-3, A4-3B, A4-3B, A4-3C and A5-5;

¡P          Trench excavation works at Zone A3-2A;

¡P          Excavation for jacking pits for pipe laying works by heading method along Convention Avenue at Zone A1-2A, A1-4A and A2-4A;

¡P          Heading No. H2, H5 and H6 (Mainlaying works by trenchless method); and

¡P          Trench excavation for a 1000 dia. Watermains at Salisbury Garden

 

  1. During this reporting period, the major work activities for Contract no. HK/2009/02 included:

¡P          Tseung Kwan O public fill sorting facility 18,615.6 m3 sorted fill produced this month.

¡P          Steel fixing of Passenger Terminal Building was completed on 8 September 2011;

¡P          Demolition of existing ferry pier;

¡P          Racking piles and dredging work of Ferry Pier;

¡P          Formwork for lift shaft of Passenger Terminal Building;

¡P          Fixing G/F to 1/F R.C wall waling on Passenger Terminal Building;

¡P          Construction of wash out chamber at Harbour Road and access manhole at Harbour Centre;

¡P          Reinstatement work for footpath and existing inspection chamber at Great Eagle Centre;

¡P          Trench excavation and deck over works along Tonnochy Road;

¡P          Approximate 55m cooling water pipe was laid at Harbour Centre, Harbour Road and ex-pet garden;

¡P          Grouting for the cross road pipeline of Harbour Road;

¡P          Installation of PVC and G.I cable ducts was ongoing at Harbour Road;

¡P          Wall and column construction below -0.8 mPD;

¡P          Installation of submarine outfall pipe up to CHA-105 and CHB-130, continue backfill on the HDPE pipelines;

¡P          Dredging for submarine outfall pipe;

¡P          3 out of 12 nos of pre-bored H-pile for box culverts N1 was reached to founding levels;

¡P          1st and 2nd loading test of New Ferry Pier;

¡P          Marine piling works for new ferry pier was ongoing. 83 out of 83 nos. marine piles;

¡P          Dredging inside the piles was ongoing. 45 out of 83 piles;

¡P          Wall and column construction below -0.8 mPD;

¡P          Casting of the base slab of WSD Receiving Pit;

¡P          Excavation and lateral support for DSD receiving pits;

¡P          Half landing slab for P7, P8 & P9 Pumping Stations was completed, top slab false work & formwork erection;

¡P          Expo Drive East mass concreting coping formwork erection;

¡P          Levelling for proposed bream blocks in progress at Vertical Seawall T4 to T6; and

¡P          Commenced fabricating the steel frames for water diversion and temporary sheet piles walls for WCR2 reclamation.

 

  1. During this reporting period, the major work activities for Contract no. HY/2009/15 included:

¡P          Seawall block construction, reclamation work at TS4;

¡P          Maintenance dredging of navigation channel and mooring area;

¡P          Night time protection works at CHT;

¡P          Construction of dewatering well at Hung Hing Road and POC; and

¡P          Precautionary works at Abutment A

 

  1. During this reporting period, the major work activities for Contract no. HK/2010/06 included:

¡P          Installation of bored pile casing;

¡P          Excavation of bored piles;

¡P          Pre-drilling works; and

¡P          Installation of temporary staging platforms

 

Noise Monitoring

  1. Noise monitoring during daytime and restricted hour were conducted at the stations M1a, M2b, M3a, M4b and M5b on a weekly basis in the reporting month. Three limit level exceedances were recorded at M1a - Harbour Road Sports Centre on 7, 15 and 20 September 2011 during restricted hour. Investigation found that major traffic noise was contributed in the noise monitoring and not related to the Project.

 

Real-time Noise Monitoring

  1. Real-time noise monitoring at FEHD Hong Kong Transport Section Whitefield Depot and Oil Street Community Centre have been commenced on 5 October 2010 for the filling works of Contract no. HY/2009/11. No project-related exceedance was recorded in the reporting month.

 

Air Quality Monitoring

  1. Air quality monitoring has been conducted at stations CMA1b, CMA2a, CMA3a, CMA4a, CMA5a and CMA6a. No exceedance was recorded in the reporting month.

 

  1. The odour patrol along the odour route with 8 sniffing locations was conducted by a qualified odour patrol member on 7 and 20 September 2011 at the concerned hours (afternoon for higher daily temperature). The odour intensity detected at 8 locations was found to be from level 0 up to level 1 which were below the Action Level.

 

Water Quality Monitoring

  1. Water quality monitoring at 18 monitoring stations was conducted three days per week during the reporting period. The action and limit level exceedances of water quality monitoring are summarized in Table I.

 

Table I    Summary of Water Quality Monitoring Exceedances in Reporting Month

Contract no.

Water Monitoring Station

Mid-flood

Mid-ebb

DO

Turbidity

SS

DO

Turbidity

SS

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

HY/2009/11

WSD9

0

0

0

0

0

0

0

0

0

0

0

0

 

WSD10

0

0

0

0

0

0

0

0

0

0

0

0

 

WSD15

0

0

0

0

0

0

0

0

0

0

0

0

 

WSD17

0

0

0

0

0

0

0

0

0

0

0

0

 

C8

0

0

0

0

0

0

0

0

1

1

0

0

 

C9

0

0

0

0

0

0

0

0

0

0

0

0

HK/2009/01

WSD19

0

0

0

0

0

0

0

0

0

0

0

0

 

WSD20

0

0

0

0

0

0

0

0

0

0

0

0

 

WSD7

0

0

0

1

0

0

0

0

0

0

0

0

 

C1

0

0

0

0

0

0

0

0

0

0

0

0

 

C3

0

0

0

0

0

0

0

0

0

0

0

0

 

C4e

0

0

0

0

0

0

0

0

0

0

0

0

 

C4w

0

0

0

0

0

0

0

0

0

0

0

0

HK/2009/01

& HK/2010/06

C2

0

0

0

0

0

0

0

0

0

0

0

0

HK/2009/02

C5e

0

0

0

0

0

0

0

0

0

0

0

0

 

C5w

0

0

0

0

0

0

0

0

0

0

0

0

 

WSD21

0

0

0

0

0

0

0

0

0

0

0

0

HY/2009/15

C7

2

0

0

0

0

0

4

0

0

0

0

0

Total

2

0

0

1

0

0

4

0

1

1

0

0

Remarks: -    The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.

 

  1. Enhanced DO monitoring at 4 monitoring stations in Causeway Bay Typhoon Shelter and Ex-Public Cargo Works Area was conducted three days per week during the reporting period. The action and limit level exceedances of water quality monitoring are summarized in Table II.

 

Table II    Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month

Contract no.

Water Monitoring Station

Mid-flood

Mid-ebb

DO

DO

AL

LL

AL

LL

HY/2009/15

C6

2

2

4

1

C7

3

0

4

2

Ex-WPCWA SW

0

3

0

9

Ex-WPCWA SE

1

5

5

8

Total

6

10

13

20

 

Complaints, Notifications of Summons and Successful Prosecutions

  1. There was one environmental complaints received on 26 August 2011. No further complaint was received after follow-up action and investigation in this reporting month.

 

Site Inspections and Audit

  1. The Environmental Team (ET) conducted weekly site inspections for Contract nos. HY/2009/11, HK/2009/01, HK/2009/02, HY/2009/15 and HK/2010/06 under EP no. EP-356/2009 in the reporting month. Major observations and recommendations made during the audit sessions were rectified by the Contractors. No non-conformance was identified during the site inspections.

 

Future Key Issues

  1. In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

 

Contract no. HY/2009/11- North Point Reclamation

¡P          Reclamation works;

¡P          Slotted panel fixing;

¡P          Geo-textile laying;

¡P          Drainage Construction works;

¡P          Outfall construction works (Open Channel U);

¡P          Sheet Pilling;

¡P          Pre-casting and Installation of Coping; and

¡P          Construction & installation of Seawall Concrete Block

 

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

¡P          Dredging works from CH190to CH260 for the reclamation of HKCEC3W would be commenced upon giving 7-day advance notice to EPD;

¡P          Reclamation of HKCEC3W (up to CH120) within the HKCEC Water Channel;

¡P          Installation of sheet pile water channel at Dome Promenade (from CH120 to CH160);

¡P          Installation of silt screen (type 3) at TST;

¡P          Dredging woks from CH50 to Ch250 for subsequent cross-harbour watermains installation off TST would be commenced. A trial dredging operation near the Avenue of Stars would be demonstrated to the representatives of LCSD on 22 September.

¡P          Installation of cross harbour watermains nos. A9 &B9 and A10 & B10;

¡P          Sheet pipe pile wall and the associated ground treatment works for the trenches of the proposed cross harbour watermaines nos. A18 & B18 works be commenced after the subsequent removal of the temporary steel platform;

¡P          Trench excavation works at Zone A1-2;

¡P          Works would be continued out at Zone A2-3B, A3-3, A3-2A, A4-3B, A4-3B, A4-3C, A5-5, B1-4, B4-2 and B4-5;

¡P          Heading Nos. H2, H5 and H6 (Mainlaying works by trenchless method); and

¡P          Heading Nos. H3, H4 and H9 (Mainlaying works by trenchless method) would be commenced after their corresponding jacking pits had been excavated in Convention Avenue.

 

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

¡P          Operating Tseung Kwan O Public Fill Sorting Facility;

¡P          Construction of passenger terminal;

¡P          Demolition of remaining finger pier;

¡P          Construction of mass seawall coping at Expo Drive East;

¡P          Trench excavation and pipe laying works along Harbour Road;

¡P          Trench excavation and deck over at Tonnochy Road;

¡P          Top soffit slab at P7, P8 & P9 pump stations;

¡P          Construction above -0.8mPDat Wan Shing Street for WSD Salt Water Intake;

¡P          Pipeline jacking WSD intake A.

¡P          Pre-bored sheet pile works for salt water intake culvert Bay1b & Bay 2;

¡P          Pre-bored H-pile for Box Culvert N1 at WCR1 Area;

¡P          The 3rd and 4th loading test of New Ferry Pier;

¡P          All piles excavation at new ferry pier;

¡P          Grouting plug in piles of New Ferry Pier;

¡P          Concreting for marine piles at new ferry pier;

¡P          Dredging and fabrication of HDPE pipe diffuser section for submarine outfall pipes;

¡P          Backfilling of bagged concrete and rockfills for the installed submarine outfall pipes;

¡P          Excavation and lateral support for receiving pits at Hung Hing Road;

¡P          Installation of temporary sheet piles wall at WCR2; and

¡P          Installation of the temporary water diversion steel frame

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

¡P          Mooring rearrangement and dredging at ME4;

¡P          Night time protection works at CHT;

¡P          Construction of dewatering well at Hung Hing Road and POC; and

¡P          Precautionary works at Abutment A

 

Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line

¡P          Installation of bored pile casing;

¡P          Excavation of bored piles;

¡P          Bored Pile Concreting;

¡P          Pre-drilling works; and

¡P          Installation of temporary staging platforms

1.         Introduction

1.1               Scope of the Report

1.1.1.        Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009 and Further Environmental permit nos. FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-014/2001).

1.1.2.        This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and ¡§Environmental Monitoring and Audit Requirements¡¨ under Particular Specification Section 27.

1.1.3.        This report documents the finding of EM&A works for Environmental Permit no. EP-356/2009, Further Environmental Permit no. FEP-01/356/2009, FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 and during the period 28th August to 27th September 2011. The cut-off date of reporting is at 27th of each reporting month.

 

1.2               Structure of the Report

 

Section 1        Introduction ¡V details the scope and structure of the report.

 

Section 2        Project Background ¡V summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3        Status of Regulatory Compliance ¡V summarizes the status of valid Environmental Permits / Licenses during the reporting period.

 

Section 4        Monitoring Requirements ¡V summarizes all monitoring parameters, monitoring methodology and equipment, monitoring locations, monitoring frequency, criteria and respective event and action plan and monitoring programmes.

 

Section 5        Monitoring Results ¡V summarizes the monitoring results obtained in the reporting period.

 

Section 6        Compliance Audit ¡V summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 7        Cumulative Construction Impact due to the Concurrent Projects ¡V summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8       Site Inspection ¡V summarizes the findings of weekly site inspections undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.

 

Section 9        Complaints, Notification of summons and Prosecution ¡V summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 10      Conclusion

2.         Project Background

2.1               Background

2.1.1.        ¡§Wan Chai Development phase II and Central-Wan Chai Bypass¡¨ and ¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨ (hereafter called ¡§the Project¡¨) are Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.        The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.        There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2               Scope of the Project and Site Description

2.2.1.        The Project is located mainly in Wan Chai North, Causeway Bay and North Point, and is demarcated by Gloucester Road and Victoria Park Road to the south, Fenwick Pier Street to the west and Tong Shui Road Interchange to the east, as shown in Figure 2.1.

2.2.2.        The study area encompasses existing developments along the Wan Chai, Causeway Bay and North Point shorelines. Major land uses include the Hong Kong Convention & Exhibition Centre (HKCEC) Extension, the Wan Chai Ferry Pier, the ex-Wan Chai Public Cargo Working Area (ex-PCWA), the Royal Hong Kong Yacht Club (RHKYC), the Police Officers¡¦ Club, the Causeway Bay Typhoon Shelter (CBTS) and commercial and residential developments.

2.2.3.        The scope of the Project comprises:

¡P          Land formation for key transport infrastructure and facilities, including the Trunk Road (i.e. CWB) and the associated slip roads for connection to the Trunk Road and for through traffic from Central to Wan Chai and Causeway Bay. The land formed for the above transport infrastructure will provide opportunities for the development of an attractive waterfront promenade for the enjoyment of the public

¡P          Reprovisioning / protection of the existing facilities and structures affected by the land formation works mentioned above

¡P          Extension, modification, reprovisioning or protection of existing storm water drainage outfalls, sewerage outfalls and watermains affected by the revised land use and land formation works mentioned above

¡P          Upgrading of hinterland storm water drainage system and sewerage system, which would be rendered insufficient by the land formation works mentioned above

¡P          Provision of the ground level roads, flyovers, footbridges, necessary transport facilities and the associated utility services

¡P          Construction of the new waterfront promenade, landscape works and the associated utility services

¡P          The Trunk Road (i.e. CWB) within the study area and the associated slip roads for connection to the Trunk Road.

 

2.2.4.        The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1      Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

2.3               Division of the Project Responsibility

2.3.1.        Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced. Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits (FEP) such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.2.        The details of individual contracts are summarized in Table 2.2.

 

 

 

Table 2.2 Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HK/2009/01

Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at Hong Kong Convention and Exhibition Centre

DP3, DP6

23 July 2010

DP1, DP2

25 August 2011

HK/2009/02

Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

DP3, DP5

5 July 2010

DP1

26 April 2011

HY/2009/11

Wan Chai Development Phase II and Central ¡V Wan Chai Bypass ¡V North Point Reclamation

DP3

17 March 2010

HY/2009/15

Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

DP3

10 November 2010

DP1

13 July 2011

HK/2010/06

Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen Wan Line

DP3

22 March 2011

04/HY/2006

Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street

DP1

September 2010

HY/2009/17

Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works.

DP1

5 October 2010

HY/2009/18

Central - Wan Chai Bypass (CWB) ¡V Central Interchange

DP1

21 April 2011

HY/2009/19

Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

DP1

24 March 2011

 

2.4               Project Organization and Contact Personnel

2.4.1.        Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.        The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2. Key personnel and contact particulars are summarized in Table 2.3:

Table 2.3 Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer for WDII

Principal Resident Engineer

Mr. Frankie Fan

2587 1778

2587 1877

Engineer for CWB

Principal Resident Engineer

Mr. Peter Poon

3916 1818

3529 2829

China Harbour- CRBC Joint Venture

Contractor under Contract no. HY/2009/11

Project Director

Mr. Cho Yu Fun

3157 1086

3157 1085

Project Manager

Mr. Gregory Wong

3157 1086

Site Agent

Mr. Daniel Cheung

3157 1086

Environmental Officer

Mr. C. M. Wong

3157 1086

Chun Wo ¡V Leader Joint Venture

Contractor under Contract no. HK/2009/01

Project Director

Mr. Simon Tong

9124 2471

2634 1626

Site Agent

Mr. Paul Yu

9456 9819

Operation Manager

Mr. Lau Yee Ching

9466 3918

Construction Manager

Mr. Jerry Siu

9493 3664

Construction Manager

Mr. Ricky Lai

9487 6549

Construction Manager

Mr. KK Yuen

3498 1213

Environmental Officer (Compliance Manager)

Mr. Andy Mak

9103 2370

Chun Wo ¡V CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Project Manager

Mr. Chan Sing Cho

3658 3002

2827 9996

Site Agent

Mr. Mak Kam Wing

3658 3044

Quality & Environmental Manager

Mr. C.P. Ho

3658 3000

Environmental Officer

Ms. Flora Ng

3658 3064

China State Construction Engineering (HK) Ltd.

Contractor under Contract no. HY/2009/15

Project Manager

Mr. M Y Wong

2823 7879

2528 5651

Site Agent

Mr. Simon Tang

3557 6358

2566 2192

 

 

Construction Manager

Mr. C K Kwok

9779 2162

 

 

 

Assistant Construction Manager (East)

Mr. Gene Cheung

6105 4880

 

 

 

Assistant Construction Manager (West)

Mr. Tony Chiu

9090 0606

 

 

 

Environmental Officer

Mr. Daniel Sin

3557 6215

 

Gammon

-Leader JV

Contractor under Contract no. HK/2010/06

Project Manager

Mr. Simon Tong

9124 2471

2529 2880

Site Agent

Mr. Keith Tse

2529 2068

Environmental Officer

Mr. Lee Wai Man

9481 6024

ENVIRON Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3743 0788

3548 6988

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

 

2.4.3.        For Contract no. HY/2009/11, the principal work activities in this reporting month included:

¡P          Reclamation works;

¡P          Geo-textile laying;

¡P          Drainage Construction works;

¡P          Outfall construction works (Open Channel U);

¡P          Sheet Pilling;

¡P          Pre-casting of Coping; and

¡P          Construction & installation of Seawall Concrete Block

 

2.4.4.        For Contract no. HK/2009/01, the principal work activities in this reporting month included:

¡P          Installation of silt screen (type 1) at TST;

¡P          Seawall toe block installation for reinstating seawall at Zone B1-3;

¡P          Dredging within HKCEC Water Channel from CH160 to CH190 for Type 1 & 2 sediment;

¡P          Trench backfilling and seawall reinstatement for both the completed cross-harbour watermains and the seawall near Expo Promenade (Zone B1-3);

¡P          Installation of cross-harbour watermains nos. A8 & B8;

¡P          Final trimming within Principle Fairway for cross-harbour watermains installation;

¡P          Platform erection for crawler crane mobilization near the existing seawall at Salisbury Garden had been completed and WSD¡¦s consent had been given for mobilization of crawler crane to the jack-up barge. Mobilization;

¡P          The trench excavation works at Zone B1-4, B4-2, A1-2, A2-4A, A3-3, A4-3B, A4-3B, A4-3C and A5-5;

¡P          Trench excavation works at Zone A3-2A;

¡P          Excavation for jacking pits for pipe laying works by heading method along Convention Avenue at Zone A1-2A, A1-4A and A2-4A;

¡P          Heading No. H2, H5 and H6 (Mainlaying works by trenchless method); and

¡P          Trench excavation for a 1000 dia. Watermains at Salisbury Garden

2.4.5.        For Contract no. HK/2009/02, the principal work activities in this reporting month included:

¡P          Tseung Kwan O public fill sorting facility 18,615.6 m3 sorted fill produced this month.

¡P          Steel fixing of Passenger Terminal Building was completed on 8 September 2011;

¡P          Demolition of existing ferry pier;

¡P          Racking piles and dredging work of Ferry Pier;

¡P          Formwork for lift shaft of Passenger Terminal Building;

¡P          Fixing G/F to 1/F R.C wall waling on Passenger Terminal Building;

¡P          Construction of wash out chamber at Harbour Road and access manhole at Harbour Centre;

¡P          Reinstatement work for footpath and existing inspection chamber at Great Eagle Centre;

¡P          Trench excavation and deck over works along Tonnochy Road;

¡P          Approximate 55m cooling water pipe was laid at Harbour Centre, Harbour Road and ex-pet garden;

¡P          Grouting for the cross road pipeline of Harbour Road;

¡P          Installation of PVC and G.I cable ducts was ongoing at Harbour Road;

¡P          Wall and column construction below -0.8 mPD;

¡P          Installation of submarine outfall pipe up to CHA-105 and CHB-130, continue backfill on the HDPE pipelines;

¡P          Dredging for submarine outfall pipe;

¡P          3 out of 12 nos of pre-bored H-pile for box culverts N1 was reached to founding levels;

¡P          1st and 2nd loading test of New Ferry Pier;

¡P          Marine piling works for new ferry pier was ongoing. 83 out of 83 nos. marine piles;

¡P          Dredging inside the piles was ongoing. 45 out of 83 piles;

¡P          Wall and column construction below -0.8 mPD;

¡P          Casting of the base slab of WSD Receiving Pit;

¡P          Excavation and lateral support for DSD receiving pits;

¡P          Half landing slab for P7, P8 & P9 Pumping Stations was completed, top slab falsework & formwork erection;

¡P          Expo Drive East mass concreting coping formwork erection;

¡P          Levelling for proposed bream blocks in progress at Vertical Seawall T4 to T6; and

¡P          Commenced fabricating the steel frames for water diversion and temporary sheet piles walls for WCR2 reclamation.

2.4.6.        For Contract no. HY/2009/15, the principal work activities in this reporting month included:

¡P          Seawall block construction, reclamation work at TS4;

¡P          Maintenance dredging of navigation channel and mooring area;

¡P          Night time protection works at CHT;

¡P          Construction of dewatering well at Hung Hing Road and POC; and

¡P          Precautionary works at Abutment A

2.4.7.        For Contract no. HK/2010/06, the principal work activities in this reporting month included:

¡P          Installation of bored pile casing;

¡P          Excavation of bored piles;

¡P          Pre-drilling works; and

¡P          Installation of temporary staging platforms

2.4.8.        In coming reporting month, the principal work activities of individual contracts are anticipated as follows:

Contract no. HY/2009/11- North Point Reclamation

¡P          Reclamation works;

¡P          Slotted panel fixing;

¡P          Geo-textile laying;

¡P          Drainage Construction works;

¡P          Outfall construction works (Open Channel U);

¡P          Sheet Pilling;

¡P          Pre-casting and Installation of Coping; and

¡P          Construction & installation of Seawall Concrete Block

 

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

¡P          Dredging works from CH190to CH260 for the reclamation of HKCEC3W would be commenced upon giving 7-day advance notice to EPD;

¡P          Reclamation of HKCEC3W (up to CH120) within the HKCEC Water Channel;

¡P          Installation of sheet pile water channel at Dome Promenade (from CH120 to CH160);

¡P          Installation of silt screen (type 3) at TST;

¡P          Dredging woks from CH50 to Ch250 for subsequent cross-harbour watermains installation off TST would be commenced. A trial dredging operation near the Avenue of Stars would be demonstrated to the representatives of LCSD on 22 September.

¡P          Installation of cross harbour watermains nos. A9 &B9 and A10 & B10;

¡P          Sheet pipe pile wall and the associated ground treatment works for the trenches of the proposed cross harbour watermaines nos. A18 & B18 works be commenced after the subsequent removal of the temporary steel platform;

¡P          Trench excavation works at Zone A1-2;

¡P          Works would be continued out at Zone A2-3B, A3-3, A3-2A, A4-3B, A4-3B, A4-3C, A5-5, B1-4, B4-2 and B4-5;

¡P          Heading Nos. H2, H5 and H6 (Mainlaying works by trenchless method); and

¡P          Heading Nos. H3, H4 and H9 (Mainlaying works by trenchless method) would be commenced after their corresponding jacking pits had been excavated in Convention Avenue.

 

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

¡P          Operating Tseung Kwan O Public Fill Sorting Facility;

¡P          Construction of passenger terminal;

¡P          Demolition of remaining finger pier;

¡P          Construction of mass seawall coping at Expo Drive East;

¡P          Trench excavation and pipe laying works along Harbour Road;

¡P          Trench excavation and deck over at Tonnochy Road;

¡P          Top soffit slab at P7, P8 & P9 pump stations;

¡P          Construction above -0.8mPDat Wan Shing Street for WSD Salt Water Intake;

¡P          Pipeline jacking WSD intake A.

¡P          Pre-bored sheet pile works for salt water intake culvert Bay1b & Bay 2;

¡P          Pre-bored H-pile for Box Culvert N1 at WCR1 Area;

¡P          The 3rd and 4th loading test of New Ferry Pier;

¡P          All piles excavation at new ferry pier;

¡P          Grouting plug in piles of New Ferry Pier;

¡P          Concreting for marine piles at new ferry pier;

¡P          Dredging and fabrication of HDPE pipe diffuser section for submarine outfall pipes;

¡P          Backfilling of bagged concrete and rockfills for the installed submarine outfall pipes;

¡P          Excavation and lateral support for receiving pits at Hung Hing Road;

¡P          Installation of temporary sheet piles wall at WCR2; and

¡P          Installation of the temporary water diversion steel frame

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

¡P          Mooring rearrangement and dredging at ME4;

¡P          Night time protection works at CHT;

¡P          Construction of dewatering well at Hung Hing Road and POC; and

¡P          Precautionary works at Abutment A

 

Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line

¡P          Installation of bored pile casing;

¡P          Excavation of bored piles;

¡P          Bored Pile Concreting;

¡P          Pre-drilling works; and

¡P          Installation of temporary staging platforms

 

3.         Status of Regulatory Compliance

3.1               Status of Environmental Licensing and Permitting under the Project

 

3.1.1.        A summary of the current status on licences and/or permits on environmental protection pertinent to the Project is shown in Table 3.1.

Table 3.1 Summary of the current status on licences and/or permits on environmental protection pertinent to the Project

Permits and/or Licences

Reference No.

Issued Date

Status

Environmental Permit

EP-356/2009

30 Jul 2009

Valid

Environmental Permit

EP-364/2009/A

4 Aug 2010

Valid

Environmental Permit

EP-364/2009

17 Aug 2009

Superseded

Environmental Permit

EP-376/2009

13 Nov 2010

Valid

Further Environmental Permit

FEP-01/356/2009

18 Feb 2010

Valid

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-04/356/2009

22 Nov 2010

Valid

Further Environmental Permit

FEP-05/356/2009

24 Mar 2011

Valid

Further Environmental Permit

FEP-01/364/2009

24 Mar 2010

Valid

Further Environmental Permit

FEP-02/364/2009

21 Apr 2010

Valid

Further Environmental Permit

FEP-03/364/2009

12 Jul 2010

Valid

Further Environmental Permit

FEP-04/364/2009/A

14 Oct 2010

Valid

Further Environmental Permit

FEP-05/364/2009/A

15 Nov 2010

Valid

Further Environmental Permit

FEP-06/364/2009/A

22 Nov 2010

Valid

Further Environmental Permit

FEP-07/364/2009/A

25 Feb 2011

Valid

 

3.1.2.        Due to the multi-contract nature of the Project, the status of permits and/or licences under the individual contract(s) are presented as below:

Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation

3.1.3.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission under FEP-01/356/2009 for contract no. HY/2009/11 are shown in Table 3.2 and Table 3.3.

3.1.4.        Contractor submitted a letter dated 20 July 2011 to confirm that the dredging works and dumping operation were completed.

Table 3.2 Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/11

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-01/356/2009

18 Feb 2010

N/A

Valid

Notification of Works Under APCO

314911

9 Mar 2010

N/A

Valid

 

331892

4 Jul. 2011

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0330-11

15 Apr 2011

1 May 2011 to 31 Oct 2011

Valid

Registration as a Chemical Waste Producer

WPN5213-151-C3631-02

12 Oct 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance

7010037

13 Jan 2010

N/A

Valid

Discharge Licence

WT00007942-2010

29 Nov 2010

30 Nov 2015

Valid

 

Table 3.3 Summary of submission status under FEP-01/356/2009 Condition

EP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

18 Dec 2009

Condition 2.7

Submission of works schedule and location plan

8 Feb 2010

Condition 2.8

Revised Silt Curtain Deployment Plan (Rev. 3)

4 Dec 2010

Condition 2.9

Silt Screen Deployment Plan (Rev. 6)

18 May 2011

Condition 2.10

Coral Translocation Plan

20 Nov 2009

Condition 2.16

Revised Noise Management Plan (Rev 5)

19 Feb 2011

Condition 2.17

Landscape Plan

12 May 2010

 

Revised landscape Plan

30 Jun 2010

 

Submission of Supplementary Information - Revised Management & Maintenance Schedule for Submitted Revised Landscape Plan

25 Aug 2010

 

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

3.1.5.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission for contract no. HK/2009/01 under FEP-02/356/2009 are shown in Table 3.4 and Table 3.5.

Table 3.4 Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/01

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-02/356/2009

24 Mar 2010

N/A

Valid

 

FEP-02/364/2009

21 Apr 2010

N/A

Valid

Notification of Works Under APCO

313088

6 Jan 2010

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0107-11

8 Feb 2011

16 Mar 2011 to 15 Sep 2011

Expired

 

GW-RS0384-11

29 Apr 2011

27 May 2011 to 26 Nov 2011

Valid

 

GW-RS0680-11

22 Jul 2011

29 Jul 2011 to 19 Jan 2012

Valid

 

GW-RS0689-11

28 Jul 2011

29 Jul 2011 to 28 Jan 2012

Valid

 

GW-RS0832-11

7 Sep 2011

03 Sep 2011 to 02 Mar 2012

Valid

 

GW-RS0850-11

12 Sept 2011

14 Sept 2011 to 13 Mar 2012

Valid

 

GW-RS0851-11

12 Sept 2011

16 Sept 2011 to 15 Mar 2012

Valid

 

GW-RE0683-11

16 Sept 2011

20 Sept 2011 to 19 Oct 2011

Valid

Discharge Licence

WT00006220-2010

18 Mar 2010

31 Mar 2015

Valid

 

WT00009641-2011

24 Jul 2011

31 Jul 2016

Valid

Billing account under Waste Disposal Ordinance

7010069

21 Jan 2010

N/A

Valid

Registration as a Chemical Waste Producer

WPN5213-134-C3585-01

21 Jan 2010

N/A

Valid

Dumping Permit (Type 1 ¡V Open Sea Disposal)

EP/MD/12-021

20 May 2011

24 May 2011 to 23 Nov 2011

Valid

Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal)

EP/MD/12-043

2 Aug 2011

08 Aug 2011 to 07 Sept 2011

Expired

EP/MD/12-057

5 Sep 2011

08 Sept 2011 to 07 Oct

Valid

Permit for Dumping at Sea - Dredged Sediment Requiring Type 3 ¡V Special Treatment / Disposal contained in Geosynthetic Containers

EP/MD/12-050

18 Aug 2011

19 Aug 2011 to 18 Sept 2011

Expired

EP/MD/12-063

22 Sept 2011

23 Sept 2011 to 22 Oct 2011

Valid

 

Table 3.5 Summary of submission status under FEP-02/356/2009 Condition

EP Condition

Submission

Date of Submission

Condition 2.6

Management Organization of Main Construction Companies

13 Apr 2010

Condition 2.7

Works Schedule and Location Plan

8 Apr 2010

Condition 2.8

Silt Curtain Deployment Plan

19 Apr 2010

Condition 2.9

Silt Screen Deployment Plan

19 Apr 2010

Conditions 2.8 and 2.9

Supplementary Document on Silt Curtain and Silt Screen Deployment Plan

19 Jul 2010

Report on Field Testing for Silt Curtain

26 Aug 2010

Report on Field Testing for Silt Curtain (Rev. A)

15 Nov 2010

Condition 2.12(d)

Alternative Proposal on Concurrent Dredging for Sewage Pipeline and Cross Harbour Water Mains

15 Apr 2011

Condition 2.17

Noise Management Plan

23 Apr 2010

Condition 2.18

Landscape Plan (Erection of Decorative Screen Hoarding along Construction Site around Hong Kong Exhibition and Convention Centre)

15 May 2010

Landscape Plan (Night-time Lighting)

22 Oct 2010

 

Landscape Plan (Rev. B)

15 Nov 2010

 

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

3.1.6.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission for contract no. HK/2009/02 under FEP-03/356/2009 are shown in Table 3.6 and Table 3.7.

Table 3.6 Cumulative Summary of Valid Licences and Permits under Contract no. HK/2009/02

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-03/356/2009

24 Mar 2010

N/A

Valid

 

FEP-01/364/2009

24 Mar 2010

N/A

Valid

Notification of Works Under APCO

313962

2 Feb 2010

N/A

Valid

Construction Noise Permit (CNP) for piling equipment

PP-RS0011-11

27 April 2011

1 June 2011 to

30 Nov 2011

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0343-11

11 April 2011

25 Apr 2011 to 10 Oct 2011

Valid

GW-RS0369-11

21 April 2011

1 May 2011 to

31 Oct 2011

Valid

 

GW-RS0377-11

27 April 2011

1 May 2011 to

31 Oct 2011

Valid

 

GW-RE0311-11

4 May 2011

5 May 2011 to 31 Oct 2011

Valid

 

GW-RS0401-11

3 May 2011

18 May 2011 to 17 Nov 2011

Valid

 

GW-RS0414-11

3 May 2011

9 May 2011 to 8 Nov 2011

Withdrawn

 

GW-RS0423-11

9 May 2011

22 May 2011 to 21 Nov 2011

Valid

 

GW-RS0430-11

9 May 2011

16 May 2011 to 15 Nov 2011

Withdrawn

 

GW-RS0453-11

19 May 2011

23 May 2011 to 22 Nov 2011

Valid

 

GW-RS0461-11

19 May 2011

23 May 2011 to 22 Nov 2011

Valid

 

GW-RS0473-11

27 May 2011

01 Jun 2011 to 30 Nov 2011

Withdrawn

 

GW-RS0496-11

31 May 2011

07 Jun 2011 to 06 Dec 2011

Valid

 

GW-RS0502-11

8 Jun 2011

13 Jun 2011 to 12 Dec 2011

Valid

 

GW-RS0579-11

22 June 2011

17 July 2011 to 16 Jan 2012

Valid

 

GW-RS0645-11

18 July 2011

22 Jul 2011 to 21 Jan 2012

Valid

 

GW-RS0649-11

22 July 2011

1 Aug 2011 to 31 Jan 2012

Valid

 

GW-RS0691-11

25 July 2011

27 July 2011 to 26 Jan 2012

Valid

 

GW-RS0716-11

2 Aug 2011

12 Aug 2011 to 11 Feb 2012

Valid

 

GW-RS0722-11

2 Aug 2011

5 Aug 2011 to 5 Oct 2011

Valid

 

GW-RS0723-11

12 Aug 2011

15 Aug 2011 to 14 Feb 2012

Valid

 

GW-RS0833-11

8 Sept 2011

10 Sept 2011 to 4 Mar 2012

Valid

 

GW-RS0857-11

16 Sept 2011

6 Oct 2011 to 5 Apr 2011

Valid

Discharge Licence

WT00006249-2010

22 Mar 2010

31 Mar 2015

Valid

WT00006436-2010

15 Apr 2010

30 Apr 2015

Valid

WT00006673-2010

14 May 2010

31 May 2015

Valid

WT00006757-2010

28 May 2010

31 May 2015

Valid

WT00007129-2010

28 July 2010

31 Jul 2015

Valid

WT00008982-2011

26 April 2011

30 Apr 2016

Valid

WT00009691-2011

1 Aug 2011

31 July 2016

Valid

Billing Account under Waste Disposal Ordinance (Land)

7010255

10 Feb 2010

N/A

Valid

Billing Account under Waste Disposal Ordinance (Marine)

7011496

6 Oct 2010

N/A

Valid

Registration as Chemical Waste Producer

WPN5213-135-C3593-01

10 Mar 2010

N/A

Valid

WPN5213-839-C3593-02

22 Sep 2010

N/A

Valid

Dumping Permit (Type 1 ¡V Open Sea Disposal)

EP/MD/12-012

6 May 2011

29 May 2011 to 28 Nov 2011

Valid

Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine disposal)

EP/MD/12-046

4 Aug 2011

10 Aug 2011 to 9 Sept 2011

Expired

EP/MD/12-056

2 Sept 2011

10 Sept 2011 to 9 Oct 2011

Valid

 

Table 3.7 Summary of submission status under FEP-03/356/2009 Condition

EP Condition

Submission

Date of Submission

Condition 1.12

Commencement Date of Construction of Marine Works

8 April 2010

Condition 2.6

Management Organization of Main Construction Companies

10 April 2010

Condition 2.7

Works Schedule and Location Plans

8 April 2010

Condition 2.8

Silt Curtain Deployment Plan Rev. H

15 Feb 2011

Condition 2.9

Silt Screen Deployment Plan

21 April 2010

 

Supplementary Information for Existing WSD Salt Water Intakes at Quarry Bay and Sai Wan Ho

5 Oct 2010

Condition 2.12 (d)

Alternative Proposal on Concurrent Dredging for Sewage Pipeline and Cross Harbour Water Mains

19 Apr 2011

Condition 2.17

Noise Management Plan

6 May 2010

Condition 2.18

Landscape Plan (Combined Version)

5 Aug 2011

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

3.1.7.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission for contract no. HY/2009/15 under EP-356/2009 are shown in Table 3.8 and Table 3.9.

Table 3.8 Cumulative Summary of Valid Licences and Permits under Contract no. HY/2009/15

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-04/356/2009

22 Nov 2010

N/A

Valid

FEP-06/364/2009/A

22 Nov 2010

N/A

Valid

Notification of Works Under APCO

321822

24 Sep 2010

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0220-11

16 Mar 2011

16 Mar to

15 Sep 2011

Expired

 

GW-RS0308-11

1 Apr 2011

4 Apr to

27 Sep 2011

Cancelled

 

GW-RS0594-11

27 Jun 2011

29 Jun to

28 Dec 2011

Cancelled

 

GW-RS0710-11

3 Aug 2011

5 Aug 2011 to

1 Feb 2012

Cancelled

 

GW-RS0727-11

11 Aug 2011

24 Aug 2011 to

23 Feb 2012

Cancelled

 

GW-RS0749-11

11 Aug 2011

15 Aug 2011 to

7 Feb 2012

Valid

 

GW-RS0820-11

5 Sep 2011

8 Sep 2011 to

7 Mar 2012

Valid

 

GW-RS0847-11

14 Sep 2011

19 Sep 2011 to

16 Mar 2012

Valid

 

GW-RS0858-11

16 Sep 2011

18 Sep 2011 to

16 Mar 2012

Valid

 

GW-RS0883-11

4 Oct 2011

5 Oct 2011 to

4 Apr 2012

Valid

Registration as a Chemical Waste Producer

WPN5213-147-C1169-35

15 Nov 2010

N/A

Valid

Water Discharge Licence

WT00008780-2011

22 Mar 2011

22 Mar 2011 to 31 Mar 2016

Valid

 

WT00008905-2011

11 Apr 2011

11 Apr 2011 to 30 Apr 2016

Valid

Billing Account under Waste Disposal Ordinance

7011553

30 Sep 2010

27 Sep 2010 to 27 Jan 2016

Valid

Billing Account under Waste Disposal Ordinance (Dumping by Vessel)

7011761

28 Apr 2011

1 May 2011 to

30 Oct 2011

Valid

Dumping Permit (Type 1 ¡V Open Sea Disposal)

EP/MD/12-037

20 Jul 2011

20 Jul 2011 to 19 Jan 2012

Valid

Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine disposal)

EP/MD/12-042

28 Jul 2011

1 Aug 2011 to

31 Aug 2011

Expired

EP/MD/12-051

29 Aug 2011

1 Sep 2011 to

30 Sep 2011

Valid till 30 Sep 2011

 

EP/MD/12-069

27 Sep 2011

1 Oct 2011 to

31 Oct 2011

To be Valid on 1 Oct 2011

Dumping Permit (Type 3 ¡V Special Treatment / Disposal contained in Geosynthetic Containers)

EP/MD/12-015

26 Sep 2011

11 Oct 2011 to

10 Nov 2011

Valid

 

Table 3.9 Summary of submission status under FEP-04/356/2009 Condition

EP Condition

Submission

Date of Submission

Condition 2.7

Amendment for Works Schedule and Location Plans

12 Nov 2010

Condition 2.8

Silt Curtain Deployment Plan Rev 2

11 May 2011

Condition 2.9

Silt Screen Deployment Plan Rev3

15 Jun 2011

Condition 2.18

Amendment for Proposal for the Removal of Odorous Sediment and Slime

2 Aug 2011

Condition 2.21

Landscape Plan

18 Feb 2011

Condition 2.23

Amendment for Noise Management Plan

27 Jan 2011

 

3.1.8.        Implementation status of the recommended mitigation measures during this reporting period is presented in Appendix 3.1.

Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line

3.1.9.        Summary of the current status on licences and/or permits on environmental protection pertinent and submission for contract no. HK/2010/06 under EP-356/2009 are shown in Table 3.10 and Table 3.11.

Table 3.10     Cumulative Summary of Valid Licences and Permits under Contract no. HK/2010/06

Permits and/or Licences

Reference No.

Issued Date

Valid Period/ Expiry Date

Status

Further Environmental Permit

FEP-05/356/2009

24 Mar 2011

N/A

Valid

Notification of Works Under APCO

326344

18 Jan 2011

N/A

Valid

Construction Noise Permit (CNP) for non-piling equipment

GW-RS0293-11

1 Apr 2011

6 Apr 2011 to

5 Oct 2011

Valid

 

GW-RS0605-11

29 Jun 2011

13 Jul 2011 to 12 Jan 2012

Valid

 

GW-RS0879-11

22 Sept 2011

6 Oct 2011 to 5 Apr 2012

Valid

Billing Account under Waste Disposal Ordinance

7012338

16 Feb 2011

N/A

Valid

Registration as Chemical Waste Producer

WPN5213-134-G2533-01

11 Feb 2011

N/A

Valid

Water Discharge Licence

WT00009619-2011

11 July 2011

11 July 2011 to 31 July 2016

Valid

Dumping Permit (Type 1 ¡V Open Sea Disposal)

EP/MD/12-030

11 Aug 11

12 Aug 2011 to

11 Feb 2012

Valid

Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine disposal)

EP/MD/12-029

11 Aug 2011

12 Aug 2011 to

11 Sept 2011

Expired

EP/MD/12-059

11 Sep 2011

12 Sep 2011 to

11 Oct 2011

Valid

 

Table 3.11     Summary of submission status under EP-356/2009 and FEP-05/356/2009 Condition

EP Condition

Submission

Date of Submission

Condition 2.7

Works Schedule and Location Plans

11 March 2011

Condition 2.8

Revised Silt Curtain Deployment Plan

31 Aug 2011

Condition 2.9

Silt Screen Deployment Plan

11 April 2011

Condition 2.23

Noise Management Plan

11 March 2011

 

4.         Monitoring Requirements

4.1               Noise Monitoring

Noise Monitoring Stations

4.1.1.        The noise monitoring stations for the Project are listed and shown in Table 4.1 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.1 Noise Monitoring Station

Station

Description

M1a

Harbour Road Sports Centre

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

 

Real-time Noise Monitoring Stations

4.1.2.        The real-time noise monitoring stations for the Project are listed and shown in Table 4.2 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.2 Real Time Noise Monitoring Station

District

Station

Description

Tin Hau

RTN1

FEHD Hong Kong Transport Section Whitefield Depot

North Point

RTN2

Oil Street Community Liaison Centre

 

Noise Monitoring Parameters, Frequency and Duration

4.1.3.        The construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq (5 minutes) shall be employed for comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

4.1.4.        Noise monitoring shall be carried out at all the designated monitoring stations. The monitoring frequency shall depend on the scale of the construction activities. The following is an initial guide on the regular monitoring frequency for each station on a weekly basis when noise generating activities are underway:

¡P          one set of measurements between 0700 and 1900 hours on normal weekdays.

4.1.5.        If construction works are extended to include works during the hours of 1900 ¡V 0700 as well as public holidays and Sundays, additional weekly impact monitoring shall be carried out during respective restricted hours periods. Applicable permits under NCO shall be obtained by the Contractor.

Monitoring Equipment

4.1.6.        As referred to in the Technical Memorandum ™ issued under the NCO, sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring. Immediately prior to and following each noise measurement the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

4.1.7.        Noise measurements shall not be made in fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.

 

4.2               Air Monitoring

Air Quality Monitoring Stations

4.2.1.        The air monitoring stations for the Project are listed and shown in Table 4.3 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.3 Air Monitoring Station

Station ID

Monitoring Location

Description

CMA1b

Oil Street Community Liaison Centre

North Point

CMA2a

Causeway Bay Community Centre

Causeway Bay

CMA3a

CWB PRE Site Office *

Causeway Bay

CMA4a

Society for the Prevention of Cruelty to Animals

Wan Chai

CMA5a

Children Playgrounds opposite to Pedestrian Plaza

Wan Chai

CMA6a

WDII PRE Site Office *

Wan Chai

* Remarks: As per the ENPC meeting in January 2011, the monitoring stations CMA3a - Future CWB site office at Wanchai Waterfront Promenade and CMA6a - Future AECOM site office at Work Area were renamed as remark.

 

Air Monitoring Parameters, Frequency and Duration

4.2.2.        One-hour and 24-hour TSP levels should be measured to indicate the impacts of construction dust on air quality. The 24-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.

4.2.3.        All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and any other local atmospheric factors affecting or affected by site conditions, etc., shall be recorded down in detail.

4.2.4.        For regular impact monitoring, the sampling frequency of at least once in every six-days, shall be strictly observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three times in every six-days should be undertaken when the highest dust impact occurs.

Sampling Procedure and Monitoring Equipment

4.2.5.        High volume samplers (HVSs) in compliance with the following specifications shall be used for carrying out the 1-hour and 24-hour TSP monitoring:

¡P          0.6 - 1.7 m3 per minute adjustable flow range;

¡P          equipped with a timing / control device with +/- 5 minutes accuracy for 24 hours operation;

¡P          installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;

¡P          capable of providing a minimum exposed area of 406 cm2;

¡P          flow control accuracy: +/- 2.5% deviation over 24-hour sampling period;

¡P          equipped with a shelter to protect the filter and sampler;

¡P          incorporated with an electronic mass flow rate controller or other equivalent devices;

¡P          equipped with a flow recorder for continuous monitoring;

¡P          provided with a peaked roof inlet;

¡P          incorporated with a manometer;

¡P          able to hold and seal the filter paper to the sampler housing at horizontal position;

¡P          easily changeable filter; and

¡P          capable of operating continuously for a 24-hour period.

 

4.2.6.        Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at bi-monthly intervals. The transfer standard shall be traceable to the internationally recognized primary standard and be calibrated annually. The concern parties such as IEC shall properly document the calibration data for future reference. All the data should be converted into standard temperature and pressure condition.

Laboratory Measurement / Analysis

4.2.7.        A clean laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS accredited.

4.2.8.        An alternative non-HOKLAS accredited laboratory was set-up for carrying out the laboratory analysis, the laboratory equipment was approved by the ER on 8 February 2011 and the measurement procedures were witnessed by the IEC. Any measurement performed by the laboratory was be demonstrated to the satisfaction of the ER and IEC. IEC shall regularly audit to the measurement performed by the laboratory to ensure the accuracy of measurement results.

4.2.9.        Filter paper of size 8" x 10" shall be labelled before sampling. It shall be a clean filter paper with no pinholes, and shall be conditioned in a humidity-controlled chamber for over 24-hours and be pre-weighed before use for the sampling.

4.2.10.    After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper shall then be returned to the laboratory for reconditioning in the humidity controlled chamber followed by accurate weighing by an electronic balance with readout down to 0.1 mg. The balance shall be regularly calibrated against a traceable standard.

4.2.11.    All the collected samples shall be kept in a good condition for 6 months before disposal.

impact monitoring for odour patrol

4.2.12.    Odour patrols along the shorelines of Causeway Bay Typhoon Shelter and ex-Wan Chai Public Cargo Working Area when there is temporary reclamation in Causeway Bay Typhoon Shelter and/or in the ex-Wan Chai Public Cargo Working Area, or when there is dredging of the odorous sediment and slime at the south-western corner of the Causeway Bay Typhoon Shelter. Odour patrols will be carried out at bi-weekly intervals during July, August and September by a qualified person of the ET who shall:

¡P          be at least 16 years of age;

¡P          be free from any respiratory illnesses; and

¡P          not be allowed to smoke, eat, drink (except water) or use chewing gum or sweets 30 min

¡P          before and during odour patrol

4.2.13.    Odour patrol shall be conducted by independent trained personnel / competent persons patrolling and sniffing around the shore as shown in Figure 4.1 to detect any odour at the concerned hours (afternoon is preferred for higher daily temperature).

4.2.14.    The qualified person will use the nose (olfactory sensor) to sniff odours at different locations. The main odour emission sources and the areas to be affected by the odour nuisance will be identified.

4.2.15.    The perceived odour intensity is to be divided into 5 levels which are ranked in the descending order as follows:

¡P          0 - Not detected. No odour perceived or an odour so weak that it cannot be easily characterized or described;

¡P          1 - Slight Identifiable odour, and slight chance to have odour nuisance;

¡P          2 - Moderate Identifiable odour, and moderate chance to have odour nuisance;

¡P          3 - Strong Identifiable, likely to have odour nuisance;

¡P          4 - Extreme Severe odour, and unacceptable odour level.

 

4.2.16.    The findings including odour intensity, odour nature and possible odour sources, and also the local wind speed and direction at each location will be recorded. In addition, some relevant meteorological and tidal data such as daily average temperature, and daily average humidity, on that surveyed day will be obtained from the Hong Kong Observatory Station for reference. The Action and Limit levels for odour patrol are shown in Appendix 6.1.

4.2.17.    The qualified odour patrol member has individual n-butanol thresholds complied with the requirement of European Standard Method of Air Quality ¡V Determination of Odour Concentration by Dynamic Olfactometry (EN13725) in the range of 20 to 80 ppb. The certificate for the qualified odour panel member is shown in Appendix 4.2.

 

4.3               Water Quality Monitoring

4.3.1.        The EIA Report has identified that the key water quality impact would be associated with the dredging works during the construction phase. Marine water quality monitoring for dissolved oxygen (DO), suspended solid (SS) and turbidity is therefore recommended to be carried out at selected WSD flushing water intakes. The impact monitoring should be carried out during the proposed dredging works to ensure the compliance with the water quality standards.

4.3.2.        The updated EM&A Manual for EP-356/2009 (Version in March 2011) is approval by EPD on 29 April 2011. As such, the Action Level and Limit Level for the wet season (April ¡V September) will be effected and applied to the water quality monitoring data from 30 April 2011.

Water Quality Monitoring Stations

4.3.3.        It is proposed to monitor the water quality at 9 WSD salt water intakes and 12 cooling water intakes along the seafront of the Victoria Harbour. The proposed water quality monitoring stations of the Project are shown in Table 4.4 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels for the monitoring works.

Table 4.4      Marine Water Quality Stations for Water Quality Monitoring

Station Ref.

Location

Easting

Northing

WSD Salt Water Intake

WSD7

Kowloon South

834150.0

818300.3

WSD9

Tai Wan

837921.0

818330.0

WSD10

Cha Kwo Ling

841900.9

817700.1

WSD15

Sai Wan Ho

841110.4

816450.1

WSD17

Quarry Bay

839790.3

817032.2

WSD19

Sheung Wan

833415.0

816771.0

WSD20

Kennedy Town

830750.6

816030.3

WSD21

Wan Chai

836220.8

815940.1

RW21

Wan Chai (Reprovision)

836188.8

815911.1

Cooling Water Intake

C1

HKCEC Extension

835885.6

816223.0

C2

Telecom House

835647.9

815864.4

C3

HKCEC Phase I

835836.2

815910.0

C4e

Wan Chai Tower and Great Eagle Centre (Eastern)

835932.8

815888.2

C4w

Wan Chai Tower and Great Eagle Centre (Western)

835629.8

815889.2

C5e

Sun Hung Kai Centre (Eastern)

836250.1

815932.2

C5w

Sun Hung Kai Centre (Western)

836248.1

815933.2

C6

Excelsior Hotel

837009.6

815999.3

C7

Windsor House

837193.7

816150.0

C8

City Garden

837970.6

816957.3

C9

Provident Garden

838355.0

817116.6

RC1

Proposed HKAPA Extension

835487.7

815987.7

RC5

Sun Hung Kai Centre (Reprovision)

836291.4

816029.7

RC7

Windsor House (Temporary Dilution)

837245.2

816156.6

 

Water Quality Parameters

4.3.4.        Monitoring of dissolved oxygen (DO), turbidity and suspended solids (SS) shall be carried out at WSD flushing water intakes and cooling water intakes. DO and Turbidity are measured in-situ while SS is determined in laboratory.

4.3.5.        In association with the water quality parameters, other relevant data shall also be measured, such as monitoring location/position, time, sampling depth, water temperature, pH, salinity, dissolved oxygen (DO) saturation, weather conditions, sea conditions, tidal stage, and any special phenomena and work underway at the construction site etc.

Sampling Procedures and Monitoring Equipment

4.3.6.        The interval between two sets of monitoring should not be less than 36 hours except where there are exceedances of Action and/or Limit Levels, in which case the monitoring frequency will be increased. Table 4.5 shows the proposed monitoring frequency and water quality parameters. Duplicate in-situ measurements and water sampling should be carried out in each sampling event. For selection of tides for in-situ measurement and water sampling, tidal range of individual flood and ebb tides should be not less than 0.5m.

Table 4.5 Marine Water Quality Monitoring Frequency and Parameters

Activities

Monitoring Frequency1

Parameters2

During the 4-week baseline monitoring period

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity

During marine construction works

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity

After completion of marine construction works

Three days per week, at mid-flood and mid-ebb tides

Turbidity, Suspended Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity

Notes:

1.       For selection of tides for in-situ measurement and water sampling, tidal range of individual flood and ebb tides should be not less than 0.5m.

2.       Turbidity should be measured in situ whereas SS should be determined by laboratory.

 

Dissolved Oxygen and Temperature Measuring Equipment

4.3.7.        The instrument should be a portable, weatherproof dissolved oxygen measuring instrument complete with cable, sensor, comprehensive operation manuals, and use a DC power source. It should be capable of measuring:

¡P          a dissolved oxygen level in the range of 0-20 mg/l and 0-200% saturation

¡P          a temperature of 0-45 degree Celsius

4.3.8.        It should have a membrane electrode with automatic temperature compensation complete with a cable. Sufficient stocks of spare electrodes and cables should be available for replacement where necessary. (e.g. YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with reel and cable or an approved similar instrument).

4.3.9.        Should salinity compensation not be build-in in the DO equipment, in-situ salinity shall be measured to calibrate the DO equipment prior to each DO measurement.

Turbidity Measurement Instrument

4.3.10.    The instrument should be a portable, weatherproof turbidity-measuring instrument complete with comprehensive operation manual. The equipment should use a DC power source. It should have a photoelectric sensor capable of measuring turbidity between 0‑1000 NTU and be complete with a cable (e.g. Hach model 2100P or an approved similar instrument).

Sampler

4.3.11.    A water sampler comprises a transparent PVC cylinder, with a capacity of not less than 2 litres, and can be effectively sealed with latex cups at both ends. The sampler should have a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth (e.g. Kahlsico Water Sampler or an approved similar instrument).

Sample Container and Storage

4.3.12.    Water samples for suspended solids measurement should be collected in high-density polythene bottles, packed in ice (cooled to 4¢XC without being frozen), and delivered to ALS Technichem (HK) Pty Ltd. as soon as possible after collection for analysis.

Water Depth Detector

4.3.13.    A portable, battery-operated echo sounder shall be used for the determination of water depth at each designated monitoring station. This unit can either be handheld or affixed to the bottom of the workboat, if the same vessel is to be used throughout the monitoring programme.

Salinity

4.3.14.    A portable salinometer capable of measuring salinity in the range of 0-40 ppt shall be provided for measuring salinity of the water at each of monitoring location.

Monitoring Position Equipment

4.3.15.    A hand-held or boat-fixed type digital Global Positioning System (GPS) with waypoint bearing indication or other equivalent instrument of similar accuracy shall be provided and used during monitoring to ensure the monitoring vessel is at the correct location before taking measurements.

Calibration of In-situ Instruments

4.3.16.    All in-situ monitoring instrument shall be checked, calibrated and certified by a laboratory accredited under HOKLAS or equivalent before use, and subsequently re-calibrated at 3 monthly intervals throughout all stages of the water quality monitoring. Responses of sensors and electrodes should be checked with certified standard solutions before each use. Wet bulb calibration for a DO meter shall be carried out before measurement at each monitoring location.

4.3.17.    For the on site calibration of field equipment by the ET, the BS 127:1993, "Guide to Field and on-site test methods for the analysis of waters" should be observed.

4.3.18.    Sufficient stocks of spare parts should be maintained for replacements when necessary. Backup monitoring equipment shall also be made available so that monitoring can proceed uninterrupted even when some equipment is under maintenance, calibration, etc.

4.3.19.    Current calibration certificates of equipments are presented in Appendix 4.2.

Laboratory Measurement / Analysis

4.3.20.    Analysis of suspended solids has been carried out in a HOKLAS accredited laboratory, ALS Technichem (HK) Pty Ltd. Water samples of about 1L shall be collected at the monitoring stations for carrying out the laboratory SS determination. The SS determination work shall start within 24 hours after collection of the water samples. The SS determination shall follow APHA 19ed or equivalent methods subject to the approval of IEC and EPD.

Enhanced Water Quality Monitoring in the ex-Wan Chai Public Cargo

Working Area and the Causeway Bay Typhoon Shelter

4.3.21.    The enhanced water quality monitoring and audit programme is to avoid aggravation of odour nuisance from seawater arising from temporary reclamation in the ex-Wan Chai Public Cargo Working Area and the Causeway Bay Typhoon Shelter.

4.3.22.    Dissolved oxygen monitoring at the intakes C6 and C7 in Causeway Bay Typhoon Shelter when there is temporary reclamation in Causeway Bay Typhoon Shelter and at the south-western and south-eastern corners of the ex-Wan Chai Public Cargo Working Area. The proposed water quality monitoring stations of the Project are shown in Table 4.6 and Figure 4.1.

Table 4.6      Marine Water Quality Stations for Enhanced Water Quality Monitoring

Station

Location

C6

Excelsior Hotel

C7

Windsor House

Ex-WPCWA-SW

South-western of the ex-Wan Chai Public Cargo Working Area

Ex-WPCWA-SE

South-eastern of the ex-Wan Chai Public Cargo Working Area

 

4.3.23.    The monitoring of dissolved oxygen are to be carried out 3 days per week, at mid-flood and mid-ebb tides for 3 water depths (1m below water surface, mid-depth and 1m above sea bed, except where the water depth less than 6m, the mid-depth may be omitted. If the water depth be equal to or less than 3m, only the mid-depth will be monitored).

Daily SS Monitoring and 24 hours Turbidity Monitoring System

4.3.24.    During dredging of the sediment at the south-western corner of the Causeway Bay Typhoon Shelter, daily monitoring of suspended solids and 24 hour monitoring of turbidity at the cooling water intakes (C6 and C7) shall be conducted.

4.3.25.    The 24 hours monitoring of turbidty at the cooling water intakes (C6 and C7) shall be established by setting up a continuous water quality monitoring station in front of the intakes during the dredging activities. The monitoring system include the turbidity sensor and data logger which is capable of data capturing at every 5 minutes. The data sahll be downloaded daily and compared with the Action and Limit level determined during the baseline water qualtiy monitoring at the cooling water intake locations.

 

 

 

5.         Monitoring Results

5.0.1.        The environmental monitoring will be implemented based on the division of works areas of each designed project managed under different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of various contracts, latest status of work commencement and monitoring stations is shown in Figure 2.1 and Figure 4.1. The monitoring results are presented in according to the Individual Contract(s).

5.0.2.        In the reporting month, the concurrent contracts are as follows:

Ÿ         Contract no. HY/2009/11 Central - Wan Chai Bypass - North Point Reclamation;

Ÿ         Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central-Wan Chai Bypass at Hong Kong Convention and Exhibition Centre; and

Ÿ         Contract no. HK/2009/02 Wan Chai Development Phase II ¡V Central-Wan Chai Bypass at Wan Chai East

Ÿ         Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

Ÿ         Contract no. HK/2010/06 Wan Chai Development Phase II ¡V Central-Wan Chai Bypass over MTR Tsuen Wan Line

5.0.3.        The environment monitoring schedules for reporting month and coming month are presented in Appendix 5.1.

 

5.1               Noise Monitoring Results

Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation

5.1.1.        The proposed division of noise monitoring stations for Contract no. HY/2009/11 are summarized in Table 5.1 below:

Table 5.1      Noise Monitoring Stations for Contract no. HY/2009/11

Station

Description

M4b

Victoria Centre

M5b

City Garden

 

5.1.2.        Day time and evening period noise monitoring was conducted at the City Garden and Victoria Centre in the reporting month.

5.1.3.        Noise monitoring results measured in this reporting period are reviewed and summarized. No exceedance was recorded in the reporting month. Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2.

 

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC, Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East and Contract no. HK/2010/06 Wan Chai Development Phase II ¡V Central-Wan Chai Bypass over MTR Tsuen Wan Line

 

5.1.4.        The proposed division of noise monitoring stations are summarized in Table 5.2 below.

Table 5.2      Noise Monitoring Station for Contract nos. HK/2009/01, HK/2009/02 and HK/2010/06

Station

Description

M1a

Harbour Road Sports Centre

 

5.1.5.        Daytime and evening period noise monitoring was conducted at the Harbour Road Sport Centre in the reporting month.

5.1.6.        Three limit level exceedances were recorded at M1a - Harbour Road Sports Centre on 7, 15 and 20 September 2011 during restricted hour. Major noise source was contributed from Tonnochy Road and water sport competition at Wan Chai Training Swimming Pool.

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

5.1.7.        The noise monitoring for HY/2009/15 was commenced on 10 November 2010. The proposed division of noise monitoring stations are summarized in Table 5.3 below.

Table 5.3      Noise Monitoring Station for Contract no. HY/2009/15

Station

Description

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

 

5.1.8.        Noise monitoring results measured in the period of daytime and restricted hour are reviewed and summarized. Details of noise monitoring results and graphical presentation can be referred in Appendix 5.2.

 

5.2               Real-time Noise Monitoring

5.2.1.        No construction activity was conducted during night time period (2300 to 0700) in this reporting month.

Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation

5.2.2.        The proposed divisions of real-time noise monitoring stations are summarized in Table 5.4 below. Real time noise monitoring for the filling works under contract no. HY/2009/11 was commenced on 5 October 2010.

Table 5.4 Real Time Noise Monitoring Station for Contract no. HY/2009/11

District

Station

Description

Tin Hau

RTN1

FEHD Hong Kong Transport Section Whitefield Depot

North Point

RTN2

Oil Street Community Liaison Centre

                  * Real time noise monitoring results and graphical presentation during night time period are for information only.

5.2.3.        Real time noise monitoring results were reviewed and no project-related Action and Limit level exceedance were recorded in the reporting period. Details of real time noise monitoring results and graphical presentation can be referred to Appendix 5.5.

 

5.3               Air Monitoring Results

Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation

5.3.1.        The major construction activity of Contract no. HY/2009/11 was filling works in the reporting month. Air monitoring had been commenced on 11 August 2010. The proposed division of air monitoring stations is summarized in Table 5.5 below.

Table 5.5      Air Monitoring Stations for Contract no. HY/2009/11

Station

Description

CMA1b

Oil Street Community Liaison Centre

CMA2a

Causeway Bay Community Centre

 

5.3.2.        No exceedance was recorded in the reporting month. Details of air monitoring results and graphical presentation can be referred in Appendix 5.3.

5.3.3.        Since the land located the Oil Street Community Liaison Centre will be handed-over to Food and Environmental Hygiene Department (FEHD) for the construction of temporary FEHD depot by the end of September 2011, the air monitoring station ¡V CMA1b was then removed on 18 September 2011 and is not available for the air quality monitoring in the existing location at Oil Street Community Liaison Centre. Owing to the rejection or no response from the nearby air sensitive receivers in allowing the implementation of impact air quality monitoring, CMA1b was proposed to be temporary suspension until obtainment of a representative long-term air monitoring station.

 

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

5.3.4.        Air monitoring was commenced on 1 April 2011 in response to the commencement of the land-filling work for Contract no. HK/2009/01. The proposed division of air monitoring stations are summarized in Table 5.6 below. No exceedance was recorded in the reporting month.

Table 5.6      Air Monitoring Stations for Contract no. HK/2009/01

Station

Description

CMA5a

Children Playgrounds opposite to Pedestrian Plaza

CMA6a

WDII PRE Site Office

 

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

5.3.5.        Air monitoring was commenced in mid-January 2011 for the land-filling work for Contract no. HK/2009/02. The proposed division of air monitoring stations are summarized in Table 5.7 below. No exceedance was recorded in the reporting month.

Table 5.7      Air Monitoring Station for Contract no. HK/2009/02

Station

Description

CMA4a

Society for the Prevention of Cruelty to Animals

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

5.3.6.        Air monitoring was commenced on 15 March 2011 for the land filling work for Contract no. HY/2009/15. The proposed division of air monitoring stations are summarized in Table 5.8 below. No exceedance was recorded in the reporting month.

Table 5.8      Air Monitoring Station for Contract no. HY/2009/15

Station

Description

CMA3a

CWB PRE Site Office

 

5.3.7.        The odour patrol along the odour route with 8 sniffing locations was conducted by a qualified odour patrol member on 7 and 20 September 2011 at the concerned hours (afternoon for higher daily temperature). The odour intensity detected at 8 locations was found to be from level 0 up to level 1 which were below the Action Level. The details of the odour patrol results and meteorological conditions and on the date of odour patrol are shown in Appendix 5.3.

5.3.8.        Additional sniffing location, OP2a was conducted for the place where is in the new shoreline of ex-WPCWA (reclamation area) or odour likely detected by the odour patrol member. The odour patrol route and the sniffing locations are shown in Figure 4.1.

 

5.4               Water Monitoring Results

 

Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation

5.4.1.        The proposed division of water monitoring stations for Contract no. HY/2009/11 are summarized in Table 5.9 below:

Table 5.9      Water Monitoring Stations for Contract no. HY/2009/11

Station Ref.

Location

Easting

Northing

WSD Salt Water Intake

WSD9

Tai Wan

837921.0

818330.0

WSD10

Cha Kwo Ling

841900.9

817700.1

WSD15

Sai Wan Ho

841110.4

816450.1

WSD17

Quarry Bay

839790.3

817032.2

Cooling Water Intake

C8

City Garden

837970.6

816957.3

C9

Provident Garden

838355.0

817116.6

 

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

5.4.2.        Water monitoring for Contract no. HK/2009/01 was commenced on 23 July 2010. The proposed division of water monitoring stations are summarized in Table 5.10 below.

Table 5.10    Water Monitoring Stations for Contract no. HK/2009/01

Station Ref.

Location

Easting

Northing

WSD Salt Water Intake

WSD7

Kowloon South

834150.0

818300.3

WSD19

Sheung Wan

833415.0

816771.0

WSD20

Kennedy Town

830750.6

816030.3

Cooling Water Intake

C1

HKCEC Extension

835885.6

816223.0

C2

Telecom House

835647.9

815864.4

C3

HKCEC Phase I

835836.2

815910.0

C4e

Wan Chai Tower and Great Eagle Centre (Eastern)

835932.8

815888.2

C4w

Wan Chai Tower and Great Eagle Centre (Western)

835629.8

815889.2

Remarks:

The water monitoring stations for the dredging works under Contract No. HK/2009/01 should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at these locations have not been carried out by others. Similarly, the water monitoring stations for the dredging works under Contract No. HK/2009/02 should also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality monitoring at these locations have not been carried out by others.

 

Contract no. HK/2009/02 - Wan Chai Development Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

5.4.3.        Water monitoring for Contract no. HK/2009/02 was commenced on 8 July 2010. The proposed division of water monitoring stations are summarized in Table 5.11 below.

Table 5.11    Water Monitoring Stations for Contract no. HK/2009/02

Station Ref.

Location

Easting

Northing

WSD Salt Water Intake

WSD21

Wan Chai

836220.8

815940.1

Cooling Water Intake

C5e

Sun Hung Kai Centre (Eastern)

836250.1

815932.2

C5w

Sun Hung Kai Centre (Western)

836248.1

815933.2

Remarks:

The water monitoring stations for the dredging works under Contract No. HK/2009/01 should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at these locations have not been carried out by others. Similarly, the water monitoring stations for the dredging works under Contract No. HK/2009/02 should also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality monitoring at these locations has not been carried out by others.

 

Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line

5.4.4.        Water monitoring for Contract no. HK/2010/06 was commenced on 8 March 2011. The proposed division of water monitoring stations are summarized in Table 5.12 below.

Table 5.12    Water Monitoring Stations for Contract no. HK/2009/02

Station Ref.

Location

Easting

Northing

Cooling Water Intake

C2

Telecom House

835647.9

815864.4

 

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

5.4.5.        Due to the commencement of the maintenance dredging on 10 November 2010, water quality monitoring for Contract no. HY/2009/15 was commenced on 9 November 2010. The proposed division of water monitoring stations are summarized in Table 5.13 below.

Table 5.13    Water Monitoring Stations for Contract no. HY/2009/15

Station Ref.

Location

Easting

Northing

Cooling Water Intake

C6

Excelsior Hotel

837009.6

815999.3

C7

Windsor House

837193.7

816150.0

Remarks: -    The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.

 

5.4.6.        The enhanced water quality monitoring at C6, C7, Ex-WPCWA-SW and Ex-WPCWA-SE was commenced on 13 January 2011. Dissolved oxygen levels at Ex-WPCWA and Causeway Bay Typhoon Shelter on 29 August 2011, 1, 3, 5, 8, 10, 12, 14, 16, 19, 21, 24 and 26 September 2011 were exceeded. These DO exceedances were considered not related to Project.

5.4.7.        There was no dredging of the sediment at the south-western corner of the Causeway Bay Typhoon Shelter in this reporting month. Thus, no daily monitoring of suspended solids and 24 hours monitoring of turbidity at the cooling water intakes at C7 was conducted.

5.4.8.        As per the meeting with the representative of Excelsior Hotel and World Trade Centre on 17 May 2011, they confirmed that the seawater intake for The Excelsior was no longer in use and replaced by the connected permanent water supply from WSD pipelines since 11 January 2011. Thus, the impact water quality monitoring for the cooling intake - C6 was terminated effective from 26 May 2011 and no compliance checking for intake water monitoring at C6 was undertaken in this reporting month.

5.4.9.        Water monitoring results measured in this reporting period are reviewed and summarized. Details of water quality monitoring results and graphical presentation can be referred in Appendix 5.4.

Table 5.14    Summary of Water Quality Monitoring Exceedances in Reporting Month

Contract no.

Water Monitoring Station

Mid-flood

Mid-ebb

DO

Turbidity

SS

DO

Turbidity

SS

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

AL

LL

HY/2009/11

WSD9

0

0

0

0

0

0

0

0

0

0

0

0

 

WSD10

0

0

0

0

0

0

0

0

0

0

0

0

 

WSD15

0

0

0

0

0

0

0

0

0

0

0

0

 

WSD17

0

0

0

0

0

0

0

0

0

0

0

0

 

C8

0

0

0

0

0

0

0

0

1

1

0

0

 

C9

0

0

0

0

0

0

0

0

0

0

0

0

HK/2009/01

WSD19

0

0

0

0

0

0

0

0

0

0

0

0

 

WSD20

0

0

0

0

0

0

0

0

0

0

0

0

 

WSD7

0

0

0

1

0

0

0

0

0

0

0

0

 

C1

0

0

0

0

0

0

0

0

0

0

0

0

 

C3

0

0

0

0

0

0

0

0

0

0

0

0

 

C4e

0

0

0

0

0

0

0

0

0

0

0

0

 

C4w

0

0

0

0

0

0

0

0

0

0

0

0

HK/2009/01

& HK/2010/06

C2

0

0

0

0

0

0

0

0

0

0

0

0

HK/2009/02

C5e

0

0

0

0

0

0

0

0

0

0

0

0

 

C5w

0

0

0

0

0

0

0

0

0

0

0

0

 

WSD21

0

0

0

0

0

0

0

0

0

0

0

0

HY/2009/15

C7

2

0

0

0

0

0

4

0

0

0

0

0

Total

2

0

0

1

0

0

4

0

1

1

0

0

Remarks: -    The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.

5.4.10.    Enhanced DO monitoring at 4 monitoring stations in Causeway Bay Typhoon Shelter and Ex-Public Cargo Works Area was conducted three days per week during the reporting period. The action and limit level exceedances of water quality monitoring are summarized in Table 5.15.

Table 5.15     Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month

Contract no.

Water Monitoring Station

Mid-flood

Mid-ebb

DO

DO

AL

LL

AL

LL

HY/2009/15

C6

2

2

4

1

C7

3

0

4

2

Ex-WPCWA SW

0

3

0

9

Ex-WPCWA SE

1

5

5

8

Total

6

10

13

20

 

5.4.11.    Investigations were found that the exceedances are not related to the Project works. The details of the recorded excedances can be referred to the Section 6.3.

5.5               Waste Monitoring Results

Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation

5.5.1.        Non-inert C&D waste was disposed of in the reporting month. Details of the waste flow table are summarized in Table 5.16.

Table 5.16     Details of Waste Disposal for Contract no. HY/2009/11

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

NIL

NIL

N/A

Inert C&D materials recycled, m3

NIL

NIL

N/A

Non-inert C&D materials disposed, m3

146.25

589.875

SENT Landfill

Non-inert C&D materials recycled, m3

NIL

NIL

N/A

Chemical waste disposed, kg

N/A

N/A

N/A

Marine Sediment (Type 1 ¡V Open Sea Disposal), m3

0

(Bulk Volume)

89,500

(Bulk Volume)

South of Cheung Chau

Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) , m3

0

(Bulk Volume)

129,200

(Bulk Volume)

East of Sha Chau

 

5.5.2.        Contractor submitted a letter dated 20 July 2011 to confirm that the dredging works and dumping operation were completed.

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

5.5.3.        Inert and non- inert C&D waste were disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.17.

Table 5.17     Details of Waste Disposal for Contract no. HK/2009/01

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

2259.75

9,088.50

TKO137, TM38

Inert C&D materials recycled, m3

0

389.96

N/A

N/A

Non-inert C&D materials disposed, m3

31.78

433.00

SENT Landfill

Non-inert C&D materials recycled, kg

459

116,917

N/A

Chemical waste disposed, kg

1,000

4,830

N/A

Marine Sediment (Type 1 ¡V Open Sea Disposal), m3

6,163

(Bulk Volume)

82,733.2

(Bulk Volume)

South of Cheung Chau

Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) , m3

2,428

(Bulk Volume)

15,027

(Bulk Volume)

East of Cha Chau

 

5.5.4.        There were marine sediments Type 1 ¡V Open Sea Disposal disposed in the reporting month. The maximum dredging rate in HKCEC3w and cross harbour water main are 446m3 and 623m3 per day respectively, which is complied with the recommended maximum dredging rate, 1500m3 per day listed in Table 2 of FEP-02/356/2009.

 

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

5.5.5.        Inert and non- inert C&D waste were disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.18.

Table 5.18     Details of Waste Disposal for Contract no. HK/2009/02

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

12,712

38,347

TKO137

Inert C&D materials recycled, m3

NIL

NIL

N/A

Non-inert C&D materials disposed, m3

16

184

SENT Landfill

Non-inert C&D materials recycled, m3

NIL

NIL

N/A

Chemical waste disposed, kg

0

2,115

N/A

Marine Sediment (Type 1 ¡V Open Sea Disposal), m3

0

150,157

(Bulk volume)

South of Cheung Chau

Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) , m3

0

104,390

(Bulk volume)

East of Sha Chau

5.5.6.        There was no marine sediment disposed in the reporting month.

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

5.5.7.        Inert and non- inert C&D waste were disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.19.

Table 5.19     Details of Waste Disposal for Contract no. HY/2009/15

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

16,543.8

26,093.7

Tuen Mun

Area 38

 

5.4

64.1

TKO137 FB

Inert C&D materials recycled, m3

NIL

184.0

To Contract HY/2009/11

275

304

ex-PCWA

Non-inert C&D materials disposed, m3

12.7

117.2

SENT Landfill

Non-inert C&D materials recycled, kg

0

13,815

N/A

Chemical waste disposed, kg

2,000

4,000

N/A

Marine Sediment (Type 1 ¡V Open Sea Disposal), m3

5,237

(Bulk Volume)

32,900

(Bulk Volume)

South of Cheung Chau

Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) , m3

560

(Bulk Volume)

142,602

(Bulk Volume)

East of Sha Chau

Marine Sediment (Type 3 ¡V Special Treatment / Disposal contained in Geosynthetic Containers)

NIL

(Bulk Volume)

2,750

(Bulk Volume)

East of Sha Chau

 

 

5.5.8.        In the reporting month, there were marine sediment Type 1 ¡V Open Sea Disposal and marine sediment Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal disposed from the maintenance dredging of navigation channel and mooring area. The maximum dredging rate, 907m3 per day in the reporting month is complied with the recommended maximum dredging rate as stipulated in FEP-04/356/2009 within the marine zones at TCBR.

Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line

5.5.9.        Inert C&D waste was disposed of in this reporting month. Details of the waste flow table are summarized in Table 5.20.

Table 5.20     Details of Waste Disposal for Contract no. HK/2010/06

Waste Type

Quantity this month

Cumulative Quantity-to-Date

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

678

678

N/A

Inert C&D materials recycled, m3

NIL

NIL

N/A

Non-inert C&D materials disposed, m3

NIL

NIL

N/A

Non-inert C&D materials recycled, kg

NIL

NIL

N/A

Chemical waste disposed, L

0

600

N/A

Marine Sediment (Type 1 ¡V Open Sea Disposal), m3

0

(Bulk Volume)

2,338

(Bulk Volume)

South Cheung Chau

Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) , m3

0

(Bulk Volume)

11,165

(Bulk Volume)

East Sha Chau

5.5.10.    In the reporting month, there was no dredging works at MTR tunnel crossing and no marine sediment disposed.

6.         Compliance Audit

6.0.1.        The Event Action Plan for construction noise, air quality and water quality are presented in Appendix 6.1.

 

6.1               Noise Monitoring

 

Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation

 

6.1.1.        No exceedance was recorded in the reporting month.

 

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

 

6.1.2.        No exceedance was recorded in the reporting month.

 

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

 

6.1.3.        Three limit level exceedances were recorded at M1a - Harbour Road Sports Centre on 7, 15 and 20 September 2011 during restricted hour. Major noise source was contributed from Tonnochy Road and water sport competition at Wan Chai Training Swimming Pool. The construction works were complied with the conditions under valid Construction Noise Permits during the measurement.

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

6.1.4.        No exceedance was recorded in the reporting month.

Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line

6.1.5.        No exceedance was recorded in the reporting month.

 

6.2               Real-time noise Monitoring

 

Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation

6.2.1.        No project-related exceedance was recorded in the reporting month.

 

6.3               Air Monitoring

6.3.1.        No exceedance was recorded in the TSP monitoring in the reporting month.

6.3.2.        Odour patrol was conducted on 7 and 20 September 2011. No exceedance was recorded in reporting month.

6.4               Water Quality Monitoring

Contract no. HY/2009/11 ¡V Central ¡V Wanchai Bypass, North Point Reclamation

6.4.1.        Referring to the exceedances shown in Table 5.9, the turbidity exceedances were recorded at C8 on 14 and 16 September 2011. Since there were numerous unknown outfalls from the nearby coastal area closed to the cooling intakes C8, it causes the potential for accumulation of pollutants near the intakes and may lead to potential water quality deterioration at the seawater intake points.

6.4.2.        Major marine work was backfilling at NPR2E on 14 and 16 September 2011. Proper condition of silt curtain was provided between the barge and the seawall during the filling material transportation. The recorded turbidity exceedances were considered as not project-related.

Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC

6.4.3.        Exceedance of turbidity level at WSD7 was recorded on 1 September 2011. Checked with Contractor's works on 1 Sep 2011, there was no marine works at Tsim Sha Tsui and Cross Harbour Water Main. In view that the water quality at monitoring stations located nearest the marine work site were well below the Action level and the silt screen at WSD7 was in proper condition, it was considered that recorded exceedance was no related to Project.

Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East

6.4.4.        No exceedance was recorded in the reporting month.

Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)

6.4.5.        There were DO level exceedances recorded at the ex- WPCWA and Causeway Bay Typhoon Shelter on 31 August, 1, 3, 5 , 8, 10, 12, 14, 16, 19, 21, 24 and 26 September 2011. The low DO levels were possible in relation to the low flow and recorded low water depth. In view that no odour nuisance was detected during monitoring, the DO exceedances were considered not related to the Project. With reference to the odour patrol results on 7 and 20 September 2011, the detected odour intensity at ex- WPCWA and Causeway Bay Typhoon Shelter was found to be from level 0 up to level 1 which were below the Action Level. These DO exceedances were considered as the natural variation and not related to the Project works.

Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line

6.4.6.        No exceedance was recorded in the reporting month.

6.4.7.        Summary for notification of exceedances can be referred to Appendix 6.2.

 

6.5               Review of the Reasons for and the Implications of Non-compliance

6.5.1.        There was no non-compliance from the site audits in the reporting period. The observations and recommendations made in each individual site audit session were presented in Section 8.

6.6               Summary of action taken in the event of and follow-up on non-compliance

6.6.1.        There was no particular action taken since no project-related non-compliance was recorded from the site audits and environmental monitoring in the reporting period.

7.         Cumulative Construction Impact due to the Concurrent Projects

7.0.1.        According to Condition 3.4 of the EP-356/2009, this section addresses the relevant cumulative construction impact due to the concurrent activities of the current projects including the Central Reclamation Phase III, Central-Wanchai Bypass and Island Eastern Corridor Link projects.

7.0.2.        From the Monthly EM&A report (August 2011) of Central Reclamation Phase III (CRIII) the key works in September 2011 are as follows:

¡P          Type A filling in FRAW and FRAE above +2.5mPD;

¡P          General filling works above +2.5mPD in IRAE;

¡P          Surcharging in FRAW and FRAE;

¡P          Installation of removable panels at caisson;

¡P          Installation of remaining seawall blocks and retaining wall on the west side of culvert F;

¡P          Construction of storm and foul drainage and gullies in hinterlands for Road P2 and Road D9;

¡P          Roadworks for Road P2;

¡P          Construction of GPO boundary wall;

¡P          Construction of PLA boundary wall and entrance;

¡P          Construction of Promenade enhancement works;

¡P          Construction of buildings at PLA berth;

¡P          Road P2 Underpass structures;

¡P          Construction of CWB structure;

¡P          Backfilling and waterproofing works for CWB structure;

¡P          Importation of fill material; and

¡P          Strengthening of Man Yiu Street Footbridge

7.0.3.        According to the construction programme of Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, the major construction activities at Reclamation Shoreline Sub-zones under Wan Chai Development Phase II were the filling works at NPR2E and HKCEC1, seawall block construction at TCBR1W, maintenance dredging of navigation channel and mooring area, HKCEC3w and marine bored piling at MTR Tunnel Crossing in the reporting month. The major environmental impact was water quality impact at North Point, Causeway Bay and Wan Chai.

7.0.4.        The major environmental impacts generated from the filling work at Central Reclamation Phase III were only located along the coastline of Central and Admiralty. As no project related exceedance was recorded in the Project, it was considered no adverse environmental impact caused by the Project works. Thus, it is evaluated the cumulative construction impact from the concurrent projects including Wan Chai Development Phase II and Central Reclamation Phase III was insignificant.

8.         Environmental Site Audit

8.0.1.        During this reporting month, weekly environmental site audits were conducted for Contracts no. HY/2009/11, HK/2009/01, HK/2009/02, HY/2009/15 and HK/2010/06. No non-conformance was identified during the site audits.

8.0.2.        Five site inspections for Contract no. HY/2009/11 were carried out on 31 August, 6, 14, 20 and 27 September 2011. The results of these inspections and outcomes are summarized in Table 8.1.

Table 8.1 Summary of Environmental Inspections for Contract no. HY/2009/11

Item

Date

Observations

Action taken by Contractor

Outcome

110831_01

31-Aug-11

No particular finding.

--

--

110906_01

6-Sep-11

As the material at the seafront dropped into the sea at NPR3 during the filling material transshipment, silty water was observed between caisson seawall and barge. Even though silt curtain was deployed during the operation, the contractor should clear those filling materials near the seafront.

Removal of the filling materials near the seafront

Completion as observed on 20-Sep-11

110914_01

14-Sep-11

Fill material accumulated along the seafront of NPR3 due to dropping off during transshipment used to be cleaned up before end of work everyday.

Removal of the filling materials near the seafront

Completion as observed on 20-Sep-11

110914_02

14-Sep-11

Fill material temporary stored at the north of channel U need to be cleaned to avoid being washed by tidal wave.

Removal of the fill material in the U-channel

Completion as observed on 20-Sep-11

110920_01

20-Sep-11

No particular finding

--

Completion as observed on 27-Sep-11

110927_01

27-Sep-11

Idle stockpiles shall be covered well or transported away from seafront.

Trimming down the stockpile and cover the stockpile where applicable.

Completion as observed on 4-Oct-11

 

8.0.3.        Four site inspections for Contract no. HK/2009/01 were carried out on 31 August, 7, 14 and 22 September 2011. Results of these inspections and outcomes are summarized in Table 8.2.

Table 8.2      Summary of Environmental Inspections for Contract no. HK/2009/01

Item

Date

Observations

Action taken by Contractor

Outcome

110831_01

31-Aug-11

Floating silt curtain at HKCEC water channel and east bridge shall be maintained.

Weighting down the silt curtain

Completion as observed on 7-Sep-11

110831_02

31-Aug-11

3-sides with top cover enclosure for the grouting work shall be enhanced the effectiveness to avoid dust emission.

Providing the proper shelter when grouting mixing

Completion as observed on 7-Sep-11

110831_03

31-Aug-11

FEP and relevant CNP shall be displayed at site access of Pump House P5.

Adhering permit s and licences at the site access

Completion as observed on 7-Sep-11

110831_04

31-Aug-11

Material shall be relocated away from the trees at P5.

Relocation of the material away from the trees

Completion as observed on 7-Sep-11

110907_01

7-Sep-11

Contractor was reminded to close the door of the plants to avoid noise emission.

Closure of the door of plants

Completion as observed on 14-Sep-11

110914_01

14-Sep-11

The discharge pipes arrangement at TST shall be improved to proceed the wastewater treatment

Improvement of the drainage system at TST

Completion as observed on 22-Sep-11

110922_01

22-Sep-11

The construction material was found located closed to the trees at TST. Contractor was reminded to relocate the materials away from the trees.

Relocation of the material away from the trees

Completion as observed on 28-Sep-11

110922_02

22-Sep-11

The drain hole of the drip tray at HKCEC1 shall be plugged.

Plugging the drain hole of the drip tray and remove the stagnant water inside it

Completion as observed on 28-Sep-11

 

8.0.4.        Four site inspections for Contract no. HK/2009/02 were carried out on 1, 8, 15 and 21 September 2011 during this reporting period. The results of these inspections and outcomes are summarized in Table 8.3.

Table 8.3      Summary of Environmental Inspections for Contract no. HK/2009/02

Item

Date

Observations

Action taken by Contractor

Outcome

110901_01

1-Sep-11

Protective screen at mud-barge shall be regular maintained.

Providing the proper protective screen at the mud barge

Completion as observed on 8-Sep-11

110908_01

8-Sep-11

Rock-fill material along the walkway of derrick barge (B22338Y) shall be removed.

Regular removal of the fill material at the walkway

Completion as observed on 15-Sep-11

110908_02

8-Sep-11

Sand was observed located next to the gully at Wan Shing Street. Protective measure to the drain shall be provided.

Removal of the sand near the gully. Sand bags were provided around the gully.

Completion as observed on 15-Sep-11

110908_03

8-Sep-11

Idling stockpile at Wan Shing Street and Finger Pier shall be covered or other measures to avoid dust emission.

Covered the stockpile by tarpaulin sheet

Completion as observed on 15-Sep-11

110915_01

15-Sep-11

Oil leakage was observed from the crawler drill rig at receiving pit.

Maintenance of the excavator and clearance of the oil stain.

Completion as observed on 21-Sep-11

110921_01

21-Sep-11

The silt curtain shall be enhanced to have sufficient depth for the rock filling works.

Providing proper silt curtain when the rock filling work was undertaken.

Completion as observed on 30-Sep-11

110921_01

21-Sep-11

The sedimentation tank shall be enhanced for the wastewater treatment in Wan Shing Street.

Additional sedimentation tanks were provided at Wan Ching Street.

Completion as observed on 30-Sep-11

110921_01

21-Sep-11

Chemical container at Wan Shing Street shall be properly stored.

Drip tray was provided for the chemical container.

Completion as observed on 30-Sep-11

 

8.0.5.        Five site inspections for Contract no. HY/2009/15 were carried out on 30 August, 6, 15, 20 and 27 September 2011 in reporting month. The results of these inspections and outcomes are summarized in Table 8.4.

Table 8.4      Summary of Environmental Inspections for Contract no. HY/2009/15

Item

Date

Observations

Action taken by Contractor

Outcome

110830_01

30-Aug-11

Drip tray shall be plug and the stagnant water inside it shall be removed.

Plugging the drain hole of the drip tray and removed the stagnant water inside it

Completion as observed on 6-Sep-11

110830_02

30-Aug-11

Water spraying shall be conducted for dust suppression.

Water spraying on dry dusty surface.

Completion as observed on 6-Sep-11

110830_03

30-Aug-11

The contractor was reminded to instruct the concrete driver to use wheel washing facilities at EXTCPWA.

Instructed the concrete trucks¡¦ drivers to use wheel washing facilities

Completion as observed on 6-Sep-11

110906_01

6-Sep-11

Gaps were found between seawall blocks (SE and NE corner of TS1). The contractor was reminded to fill them up in order to prevent any overflow.

Filling the gaps up in order to prevent any overflow of surface runoff

Completion as observed on 15-Sep-11

110906_02

6-Sep-11

Drip tray shall be provided for oil drum as well as chemical label.

Providing drip tray and chemical label for oil drum

Completion as observed on 15-Sep-11

110915_01

15-Sep-11

Oil leakage was observed from the broken oil drums. The contractor should provide drip tray for oil drum storage, and disposed of the oil stains as chemical waste. (abutment A)

Provide drip tray for oil drum and treated the contaminated soil as chemical waste

Completion as observed on 27-Sep-11

110915_02

15-Sep-11

Silty water was observed discharged into the sea, even through the water was treated by waste water treatment plant. The contractor was reminded to review the efficiency of the waste water treatment plant. (TS1)

Reviewed the efficiency of the waste water treatment plant

Completion as observed on 20-Sep-11

110920_01

20-Sep-11

Some Gaps between seawall blocks were found not filled at TS1.

Filling the gaps up in order to prevent any overflow

Completion as observed on 27-Sep-11

110920_02

20-Sep-11

Wastewater from shoes washing facility was found leakage from the drainage at TS1. The contractor should improve the drainage system to collect the water

Improvement of the drainage system to collect and treat the waste water

Completion as observed on 27-Sep-11

110920_03

20-Sep-11

Relocation of the oil drums under abutment A was observed and without drip tray. The soil was contaminated by the leakage oil.

Provided drip tray for oil drum and treated the contaminated soil as chemical waste

Completion as observed on 27-Sep-11

110920_04

20-Sep-11

Stockpile at TS4 near the seafront should be covered properly.

Provide tarpaulin or clean up the stockpile near the seafront

Completion as observed on 27-Sep-11

110927_01

27-Sep-11

Wastewater was found discharged to the u-channel near POC. The contractor was reminded to treat the water prior to discharge properly.

Treated the water prior to discharge properly

Completion as observed on 4-Oct-11

110927_02

27-Sep-11

Wastewater leakage generated from the hydraulic excavator was observed at Ex-WPCWA.

Tidy up the wastewater

Completion as observed on 4-Oct-11

110927_03

27-Sep-11

The contractor was reminded to enclose the dredging point by silt curtain (temporary monitoring area)

Enclosed the dredging point by silt curtain

Completion as observed on 4-Oct-11

8.0.6.        Five site inspections for Contract no. HK/2010/06 were carried out on 29 August, 5, 12, 22 and 27 September 2011 in reporting month. The results of these inspections and outcomes are summarized in Table 8.5.

Table 8.5      Summary of Environmental Inspections for Contract no. HK/2010/06

Item

Date

Observations

Action taken by Contractor

Outcome

110829_01

29-Aug-11

Floating debris was found between western platform and barge. It shall be cleared up.

Maintenance of the silt curtain

Completion as observed on 5-Sep-11

110829_02

29-Aug-11

Drain pipe shall be extended the edge at eastern platform.

Extension of drain pipe to the edge at eastern platform.

Completion as observed on 5-Sep-11

110905_01

5-Sep-11

Floating debris inside the silt curtain shall be removed.

Regular clearance of floating debris.

Completion as observed on 12-Sep-11

110912_01

12-Sep-11

Drainage pipe along the west platform shall be improved

Improvement of the drainage pipe at west platform.

Completion as observed on 22-Sep-11

110922_01

22-Sep-11

The tarpaulin for the shelter of grouting mixer shall be sealed up to achieve the dust suppression.

Sealing up the tarpaulin for the shelter

Completion as observed on 27-Sep-11

110922_02

22-Sep-11

Regular water spraying on the dusty surface on the platform.

Water spraying on the surface regularly.

Completion as observed on 27-Sep-11

110927_01

27-Sep-11

The debris at west platform shall be removed.

Removal of debris at the platform.

Completion as observed on 4-Oct-11

 

 

 

9.         Complaints, Notification of Summons and Prosecution

9.0.1.        There was one environmental complaint received on 26 August 2011 for the investigation and follow-up action in the reporting month.

9.0.2.        A water impact complaint was received by ET on 29 August 2011. It was complained by Mr. Au from Cayley Property Management Limited (CPML) that large amount of rubbishes were found at the harbour front adjacent to their cooling water intake suction which caused 3 times of system breakdown of the sea water pump on 9, 22 and 25 August 2011 after the contractors set up the temporary garbage defender in function and collect the floating refuses, but cannot eliminate all refuses, in particular the refuse coming from the seabed. An ad-hoc inspection of the effectiveness of garbage defender was conducted with RSS (CWB project team), contractors of HY/200911 and HY/2009/19, ET and IEC on 29 August 2011.

9.0.3.        During on-site inspection, floating refuses were observed occasionally outside the garbage defender. No conclusion could be made for the source of these floating refuses. On the other hand, some of the refuses were observed floating behind the garbage defender during investigation. All daily cleaning actions had been taken by contractor to minimize floating refuse inside the construction site. It was noted that the cooling water intake was accessible to the public. As such, fish breeding and fishing activities were observed even though a notice has already hoisted. Also, tripping of rubbish by the passers-by could result in a lot of rubbish accumulated around the intake point. Referring to the record provided by CPML, there were a lot of nylon/ plastic bags and nylon wire mesh that matched those rubbishes generated from the public activities. The contractors were reminded to strengthen the communication with City Garden and no further complaint from complainant was received after proposed the mitigation measure.

9.0.4.        To follow up the ICC complaint no. 1 ¡V 306740207 regarding the discharged muddy water from work site to the seafront near Oil Street during heavy rain in last month, it was confirmed with RE that muddy water was caused by a heap of earth being washed to the sea by heavy rain. The heap of earth was referred as a small stockpile placed close to the seafront in front of Oil Street within the site area under handover transition period from contract HY/2009/11 to contract HY/2009/19. The necessary mitigation measures to protect the small stockpile against rainfall were missing at the time of complaint.

9.0.5.        Due to the missing of mitigation measures to protect the small stockpile during handover transition period, loose material was washed into the harbour when heavy rain came. Muddy water was formed and dispersed in the sea that caused the water quality and visual concern to the public. The complaint was considered as valid.

9.0.6.        Contractors were advised to relocate the loose materials away from the coastline as far as practicable. Any loose material placed which needed to be placed near the coastline shall be properly compacted or covered as appropriate. To avoid any further environmental deficiency, Contractors shall ensure all necessary environmental mitigation measures will not be missing during site area handover.

9.0.7.        The details of cumulative complaint log and updated summary of complaints are presented in Appendix 9.1.

9.0.8.        Cumulative statistic on complaints and successful prosecutions are summarized in Table 9.1 and Table 9.2 respectively.

Table 9.1 Cumulative Statistics on Complaints

Reporting Period

No. of Complaints

Commencement works (Mar 2010) to last reporting month

21

September 2011

1

Project-to-Date

22

 

Table 9.2 Cumulative Statistics on Successful Prosecutions

Environmental Parameters

Cumulative No. Brought Forward

No. of Successful Prosecutions this month (Offence Date)

Cumulative No. Project-to-Date

Air

-

0

0

Noise

-

0

0

Water

-

0

0

Waste

-

0

0

Total

-

0

0

 

 

 

10.        Conclusion

10.0.1.    The EM&A programme was carried out in accordance with the EM&A Manual requirements, minor alterations to the programme proposed were made in response to changing circumstances.

10.0.2.    The scheduled construction activities and the recommended mitigation measures for the coming month are listed in Table 10.1.

Table 10.1     Construction Activities and Recommended Mitigation Measures in Coming Reporting Month

Contract No.

Key Construction Works

Recommended Mitigation Measures

HY/2009/11

¡P          Reclamation works;

¡P          Slotted panel fixing;

¡P          Geo-textile laying;

¡P          Drainage Construction works;

¡P          Outfall construction works (Open Channel U);

¡P          Sheet Pilling;

¡P          Pre-casting and Installation of Coping; and

¡P          Construction and installation of seawall concrete block

¡P          To avoid concurrent noisy operation

¡P          To locate the plant and equipments far away to the noise sensitive receivers

¡P          Daily visual inspection of silt screen and silt curtain to ensure its operation properly

¡P          Daily clearance of floating debris behind the silt screen

HK/2009/01

¡P          Dredging works from CH190to CH260 for the reclamation of HKCEC3W would be commenced upon giving 7-day advance notice to EPD;

¡P          Reclamation of HKCEC3W (up to CH120) within the HKCEC Water Channel;

¡P          Installation of sheet pile water channel at Dome Promenade (from CH120 to CH160);

¡P          Installation of silt screen (type 3) at TST;

¡P          Dredging woks from CH50 to Ch250 for subsequent cross-harbour watermains installation off TST would be commenced. A trial dredging operation near the Avenue of Stars would be demonstrated to the representatives of LCSD on 22 September.

¡P          Installation of cross harbour watermains nos. A9 &B9 and A10 & B10;

¡P          Sheet pipe pile wall and the associated ground treatment works for the trenches of the proposed cross harbour watermaines nos. A18 & B18 works be commenced after the subsequent removal of the temporary steel platform;

¡P          Trench excavation works at Zone A1-2;

¡P          Works would be continued out at Zone A2-3B, A3-3, A3-2A, A4-3B, A4-3B, A4-3C, A5-5, B1-4, B4-2 and B4-5;

¡P          Heading Nos. H2, H5 and H6 (Mainlaying works by trenchless method); and

¡P          Heading Nos. H3, H4 and H9 (Mainlaying works by trenchless method) would be commenced after their corresponding jacking pits had been excavated in Convention Avenue.

¡P          To conform the installation and setting as in the silt screen deployment plan

¡P          Frequency spray water on the dry dusty road and on the surface of concrete breaking

¡P          To cover the dusty material or stockpile by impervious sheet

¡P          To space out noisy equipment and position as far as possible from sensitive receiver.

¡P          To well maintain the mechanical equipments / machineries to avoid abnormal noise nuisance.

¡P          Machines and plant that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum

¡P          Daily visual inspection of silt screen and silt curtain to ensure its operation properly

HK/2009/02

¡P          Operating Tseung Kwan O Public Fill Sorting Facility;

¡P          Construction of passenger terminal;

¡P          Demolition of remaining finger pier;

¡P          Construction of mass seawall coping at Expo Drive East;

¡P          Trench excavation and pipe laying works along Harbour Road;

¡P          Trench excavation and deck over at Tonnochy Road;

¡P          Top soffit slab at P7, P8 & P9 pump stations;

¡P          Construction above -0.8mPDat Wan Shing Street for WSD Salt Water Intake;

¡P          Pipeline jacking WSD intake A.

¡P          Pre-bored sheet pile works for salt water intake culvert Bay1b & Bay 2;

¡P          Pre-bored H-pile for Box Culvert N1 at WCR1 Area;

¡P          The 3rd and 4th loading test of New Ferry Pier;

¡P          All piles excavation at new ferry pier;

¡P          Grouting plug in piles of New Ferry Pier;

¡P          Concreting for marine piles at new ferry pier;

¡P          Dredging and fabrication of HDPE pipe diffuser section for submarine outfall pipes;

¡P          Backfilling of bagged concrete and rockfills for the installed submarine outfall pipes;

¡P          Excavation and lateral support for receiving pits at Hung Hing Road;

¡P          Installation of temporary sheet piles wall at WCR2; and

¡P         Installation of the temporary water diversion steel frame

¡P          To cover the dusty material or stockpile by impervious sheet;

¡P          Frequency spray water on the dry dusty road and on the surface of concrete breaking

¡P          To well maintain the mechanical equipments / machineries to avoid abnormal noise nuisance and dark smoke emission

¡P          To conform the installation and setting as in the silt screen and silt curtain deployment plan

¡P          Movable noise barrier shall be deployed for demolition works

¡P          Daily visual inspection of silt screen and silt curtain to ensure its operation properly

 

HY/2009/15

¡P          Mooring rearrangement and dredging at ME4;

¡P          Night time protection works at CHT;

¡P          Construction of dewatering well at Hung Hing Road and POC; and

¡P          Precautionary works at Abutment A

¡P          To conform the installation and setting as in the silt screen and silt curtain deployment plan

¡P          Frequency spray water on the dry dusty road and on the surface of concrete breaking

¡P          To cover the dusty material or stockpile by impervious sheet

¡P          To space out noisy equipment and position as far as possible from sensitive receiver.

¡P          Daily visual inspection of silt screen and silt curtain to ensure its operation properly

HK/2010/06

¡P          Installation of bored pile casing;

¡P          Excavation of bored piles;

¡P          Bored Pile Concreting;

¡P          Pre-drilling works; and

¡P          Installation of temporary staging platforms

 

¡P          To conform the installation and setting as in the silt screen and silt curtain deployment plan

¡P          To space out noisy equipment and position as far as possible from sensitive receiver.

¡P          Daily visual inspection of silt screen and silt curtain to ensure its operation properly